Bombay High Court Dismisses Appeals Against RERA Orders on Pre-2017 Agreements, Upholding Retrospective Application of MahaRERA. Court holds that Section 3(1) of RERA applies to ongoing projects even if agreements were executed before the Act came into force.

The judgment concerns three connected second appeals filed before the Bombay High Court under the Civil Appellate Jurisdiction. The appeals were filed...

© Image Copyrights Juris Services & Technology

Bombay High Court Allows Promoter's Appeal in RERA Case, Holding That Acceptance of Delayed Possession Without Protest Does Not Waive Right to Interest Under Section 18 of RERA. Statutory Right to Interest Under RERA Cannot Be Waived by Mere Acceptance of Possession Without a Clear Agreement.

The case involves a Second Appeal filed by CCI Projects Private Limited (the promoter) against an order of the Maharashtra Real Estate Appellate Tribu...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses Builder's Appeal in RERA Interest Case for Delayed Possession. Builder directed to pay interest at SBI MCLR plus 2% from 1 January 2018 till possession for delay in handing over flats in slum rehabilitation project.

The case involves a Second Appeal filed by Era Realtors Private Limited (Appellant) against the judgment of the Maharashtra Real Estate Appellate Trib...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses Promoter's Appeal in RERA Delayed Possession Case, Upholds Allottees' Right to Interest. Section 18 of RERA Overrides Section 55 of Contract Act; Acceptance of Delayed Possession Does Not Waive Right to Compensation.

The case involves a Second Appeal filed by CCI Projects Private Limited (the promoter) against the judgment of the Maharashtra Real Estate Appellate T...

© Image Copyrights Juris Services & Technology

High Court of Bombay Considers Second Appeals in RERA Delayed Possession Matter. Builder Challenges Appellate Tribunal's Direction to Pay Interest at 10.05% p.a. from February 2014.

These Second Appeals were filed before the High Court of Judicature at Bombay by Runwal Constructions, a registered partnership firm, challenging the ...

© Image Copyrights Juris Services & Technology

Bombay High Court Partly Allows Promoter's Appeal in RERA Interest Case. Appellate Tribunal's Suo Motu Adjudication on Termination of Agreement Set Aside as Without Jurisdiction.

The case involves an appeal under Section 58 of the Real Estate (Regulation and Development) Act, 2016 (RERA Act) filed by Satyam Developers, the prom...