Bombay High Court Dismisses Promoter's Appeal in RERA Delayed Possession Case, Upholds Allottees' Right to Interest. Section 18 of RERA Overrides Section 55 of Contract Act; Acceptance of Delayed Possession Does Not Waive Right to Compensation.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 3
Judgement Image
Font size:
Print

Case Note & Summary

The case involves a Second Appeal filed by CCI Projects Private Limited (the promoter) against the judgment of the Maharashtra Real Estate Appellate Tribunal dated 10th March 2021, which had quashed the MahaRERA order dated 17th September 2018 and directed the promoter to pay interest for delayed possession to the allottees (Rajesh Kumar Chaudhary and others). The allottees had booked apartments in a project called 'Rivali Park' and the possession was delayed beyond the agreed date. The promoter argued that the allottees had accepted possession without protest and thus waived their right to claim interest under Section 55 of the Indian Contract Act, 1872. The promoter also raised force majeure as a defense. The court framed three substantial questions of law: (i) whether acceptance of delayed performance disentitles the promisee from claiming compensation under Section 55 of the Contract Act; (ii) whether Section 18 of RERA overrides Section 55 of the Contract Act; and (iii) whether force majeure events listed in the contract could be ignored under Section 32 of the Contract Act. The court held that Section 18 of RERA is a special provision that overrides the general provisions of the Contract Act, and the right to interest under RERA is not subject to waiver by acceptance of possession. The court also held that the promoter failed to prove force majeure as the cause of delay. The appeal was dismissed, and the allottees were entitled to interest for the period of delay.

Headnote

A) Real Estate Law - Delayed Possession - Interest under Section 18 of RERA - Overriding Effect - The court held that Section 18 of RERA is a substantive provision that overrides Section 55 of the Indian Contract Act, 1872, and acceptance of delayed possession does not disentitle the allottee from claiming interest for the period of delay. (Paras 1-32)

B) Contract Law - Waiver of Right - Acceptance of Delayed Performance - The court held that mere acceptance of possession after the stipulated date does not constitute waiver of the right to claim compensation for delay under Section 55 of the Contract Act, and in any case, Section 18 of RERA provides an independent remedy. (Paras 1-32)

C) Real Estate Law - Force Majeure - Burden of Proof - The court held that force majeure events must be specifically pleaded and proved by the promoter; general allegations are insufficient. The promoter failed to establish that the delay was caused solely by force majeure events listed in the agreement. (Paras 1-32)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether acceptance of delayed possession disentitles allottees from claiming interest under Section 18 of RERA; whether Section 18 of RERA overrides Section 55 of Contract Act; whether force majeure events listed in the contract can be ignored under Section 32 of Contract Act.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Second Appeal is dismissed. The judgment of the Appellate Tribunal dated 10th March 2021 is upheld. The promoter is directed to pay interest for delayed possession as per Section 18 of RERA.

Law Points

  • Section 18 of RERA overrides Section 55 of Contract Act
  • acceptance of delayed possession does not waive right to compensation
  • force majeure events must be specifically pleaded and proved
  • Section 32 of Contract Act does not apply to RERA claims
Subscribe to unlock Law Points Subscribe Now

Case Details

2026:BHC-AS:9416

Second Appeal No. 479 of 2021

2026-06-18

Sharmila U. Deshmukh, J.

2026:BHC-AS:9416

Mr. Naushad Engineer, Senior Advocate i/b Wadia Ghandy and Co. for Appellant; Mr. Harshad Bhadbhade for Respondents

CCI Projects Private Limited

Mr. Rajesh Kumar Chaudhary, Mrs. Sapna Chaudhary, Mr. Abhijit Kumar Phanikumar, Ms. Nandini Hiten Khatau, Ms. Maithili Hiten Khatau, Mr. Pradip Haridas Udeshi, Ms. Nayna Bharat Pasta

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Second Appeal under Section 100 CPC against judgment of Maharashtra Real Estate Appellate Tribunal in a RERA complaint for delayed possession.

Remedy Sought

Allottees sought interest for delayed possession under Section 18 of RERA.

Filing Reason

Promoter challenged the Appellate Tribunal's order directing payment of interest for delayed possession.

Previous Decisions

MahaRERA order dated 17th September 2018 in Complaint No. CC006000000054636 was quashed by the Appellate Tribunal on 10th March 2021, which directed the promoter to pay interest.

Issues

Whether acceptance of delayed possession disentitles allottees from claiming interest under Section 18 of RERA? Whether Section 18 of RERA overrides Section 55 of the Indian Contract Act? Whether force majeure events listed in the contract can be ignored under Section 32 of the Indian Contract Act?

Submissions/Arguments

Promoter argued that allottees accepted possession without protest, thus waiving right to claim interest under Section 55 of Contract Act. Promoter argued that delay was due to force majeure events. Allottees argued that Section 18 of RERA provides an independent right to interest and overrides Contract Act. Allottees argued that force majeure was not proved.

Ratio Decidendi

Section 18 of RERA is a special provision that overrides the general provisions of the Indian Contract Act, 1872. The right to interest under Section 18 is not subject to waiver by acceptance of possession. Force majeure must be specifically pleaded and proved; general allegations are insufficient.

Judgment Excerpts

The Second Appeal is filed at the instance of the promoter, challenging the judgment dated 10th March, 2021 passed by Maharashtra Real Estate Appellate Tribunal... By order dated 11th December, 2025, this Court framed the following substantial questions of law...

Procedural History

Allottees filed complaint under Section 31 of RERA before MahaRERA. MahaRERA passed order on 17th September 2018. Promoter appealed to Maharashtra Real Estate Appellate Tribunal, which quashed MahaRERA order and directed promoter to pay interest on 10th March 2021. Promoter filed Second Appeal No. 479 of 2021 before Bombay High Court. High Court framed substantial questions of law on 11th December 2025 and pronounced judgment on 18th June 2026.

Acts & Sections

  • Real Estate (Regulation and Development) Act, 2016: Section 18, Section 31
  • Indian Contract Act, 1872: Section 32, Section 55
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Promoter's Appeal in RERA Delayed Possession Case, Upholds Allottees' Right to Interest. Section 18 of RERA Overrides Section 55 of Contract Act; Acceptance of Delayed Possession Does Not Waive Right to Compensation.
Related Judgement
High Court Bombay High Court Acquits Appellants in Murder Case Due to Unreliable Eyewitness Testimony. Conviction under Section 302 read with Section 34 IPC set aside as sole eyewitness's evidence was inconsistent and uncorroborated.