Bombay High Court Dismisses Builder's Appeal in RERA Interest Case for Delayed Possession. Builder directed to pay interest at SBI MCLR plus 2% from 1 January 2018 till possession for delay in handing over flats in slum rehabilitation project.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 144
Judgement Image
Font size:
Print

Case Note & Summary

The case involves a Second Appeal filed by Era Realtors Private Limited (Appellant) against the judgment of the Maharashtra Real Estate Appellate Tribunal, Mumbai, dated 17 March 2023. The Appellant had undertaken a residential housing project under the Slum Rehabilitation Scheme on property in Malad, Mumbai. The Respondents, Prakash Shah and Niket Shah, booked two flats in the project for a total consideration of Rs.3,91,04,400 each. Letters of allotment were issued on 11 September 2013, with possession promised by 1 June 2017, with a six-month grace period. The Respondents paid part consideration of Rs.3,29,20,062 for each flat. However, possession was delayed. The Respondents filed a complaint before the Maharashtra Real Estate Regulatory Authority (MahaRERA), which on 25 November 2020 directed the Appellant to pay interest at SBI MCLR plus 2% from 1 January 2018 till possession. The Appellant appealed to the Appellate Tribunal, which partly allowed the appeal but maintained the interest direction. The Appellant then filed the present Second Appeal. The High Court considered the issues of whether the Appellate Tribunal was justified in directing interest and whether RERA applies to the project. The court held that the project was ongoing as no completion certificate was obtained before RERA came into force, and thus RERA provisions apply. The court also held that the Appellant was liable to pay interest for the delay as per Section 18 of RERA. The court dismissed the appeal, upholding the direction to pay interest at SBI MCLR plus 2% from 1 January 2018 till possession, and also upheld the costs of Rs.10,000.

Headnote

A) Real Estate - Interest on Delayed Possession - Section 18 of Real Estate (Regulation and Development) Act, 2016 - Promoter's Liability - The issue pertained to delay in handing over possession of flats in a slum rehabilitation project. The court held that the promoter is liable to pay interest to the allottee for the period of delay as per Section 18 of RERA, and the rate of interest is SBI MCLR plus 2% as prescribed under the Act. (Paras 1-20)

B) Real Estate - Applicability of RERA to Ongoing Projects - Section 3 of Real Estate (Regulation and Development) Act, 2016 - Transitional Provisions - The court considered whether RERA applies to projects where completion certificate was obtained before the Act came into force. Held that RERA applies to projects for which completion certificate is not obtained before the Act's commencement, and the project in question was ongoing, hence RERA provisions apply. (Paras 10-15)

C) Real Estate - Compensation for Delay - Section 18 of Real Estate (Regulation and Development) Act, 2016 - Allottee's Right - The court examined the allottee's right to compensation for delay in possession. Held that the allottee is entitled to interest from the date of default as per the agreement, and the promoter cannot avoid liability by citing force majeure or other excuses unless proven. (Paras 16-20)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Appellate Tribunal was justified in directing the Appellant to pay interest on the amount paid by the allottees at SBI MCLR plus 2% from 1 January 2018 till possession, and whether the Appellant is entitled to any relief against such direction.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The High Court dismissed the Second Appeal, upholding the direction of the Appellate Tribunal to pay interest at SBI MCLR plus 2% from 1 January 2018 till the date of handing over possession of the subject apartments to the Respondents, and also upheld the costs of Rs.10,000.

Law Points

  • Interest on delayed possession
  • RERA Section 18
  • Promoter's obligation to compensate allottee
  • Slum Rehabilitation Scheme
  • Applicability of RERA to ongoing projects
Subscribe to unlock Law Points Subscribe Now

Case Details

2024 LawText (BOM) (03) 81

SECOND APPEAL (STAMP) NO.27241 OF 2023

2024-03-14

SANDEEP V. MARNE, J.

2024:BHC-AS:12379

Mr. Shakeeb Shaikh with Mr. Noorain Patel i/b M/s. Diamondwala & Co. for the Appellant. Mr. Aseem Naphade with Mr. Rajendra Mishra, Mr. Mukesh Gupta & Ms. Asmita Yadav i/b. M/s. Solicis Lex for Respondents.

Era Realtors Private Limited

Prakash Shah and Niket Shah

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Second Appeal under Section 58 of the Real Estate (Regulation and Development) Act, 2016 challenging the order of the Maharashtra Real Estate Appellate Tribunal.

Remedy Sought

Appellant sought to set aside the direction to pay interest at SBI MCLR plus 2% from 1 January 2018 till possession and costs of Rs.10,000.

Filing Reason

Appellant aggrieved by the Appellate Tribunal's order partly allowing the Respondents' appeal and modifying the MahaRERA order.

Previous Decisions

MahaRERA order dated 25 November 2020 directed interest at SBI MCLR plus 2% from 1 January 2018 till possession. Appellate Tribunal order dated 17 March 2023 partly allowed appeal but maintained interest direction.

Issues

Whether the Appellate Tribunal was justified in directing the Appellant to pay interest on the amount paid by the allottees at SBI MCLR plus 2% from 1 January 2018 till possession? Whether the Appellant is entitled to any relief against such direction?

Submissions/Arguments

Appellant argued that the project was a slum rehabilitation scheme and delays were due to factors beyond its control, and that RERA does not apply to projects where completion certificate was obtained before the Act came into force. Respondents argued that the Appellant failed to hand over possession within the agreed timeline and is liable to pay interest under Section 18 of RERA.

Ratio Decidendi

The promoter is liable to pay interest to the allottee for delay in possession under Section 18 of RERA at the prescribed rate of SBI MCLR plus 2%, and the applicability of RERA extends to ongoing projects where completion certificate has not been obtained before the Act's commencement.

Judgment Excerpts

Appellant has been directed to pay interest to the allottees on the amount paid by them at the rate of SBI’s Highest Marginal Costs of Lending Rate (MCLR) plus 2% with effect from 1 January 2018 till the date of handing over possession of subject apartments to the Respondents. Petitioner is also directed to pay costs of Rs.10,000/- to the Respondents.

Procedural History

The Respondents filed a complaint before MahaRERA, which on 25 November 2020 directed the Appellant to pay interest. The Appellant appealed to the Maharashtra Real Estate Appellate Tribunal, which on 17 March 2023 partly allowed the appeal but maintained the interest direction. The Appellant then filed the present Second Appeal before the Bombay High Court, which was dismissed on 14 March 2024.

Acts & Sections

  • Real Estate (Regulation and Development) Act, 2016: Section 18, Section 3
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Allows Appellant in Land Acquisition Compensation Dispute Due to Erroneous Deduction of Developmental Costs from Agricultural Land. Court Held That Valuation of Large Extent of Agricultural Land on Square Foot Basis is Per Se Illegal an...
Related Judgement
High Court High Court Allows Writ Petition Against Revenue Authorities for Failure to Conduct Phodi Despite Evidence of Ownership. Court Directs Tahsildar to Update Revenue Records and Remove Illegal Board from Property, Holding That Government Circular on Gran...