Bombay High Court Dismisses Builder's Second Appeals Against RERA Appellate Tribunal Order for Refund with Interest to Homebuyers. Failure to Deliver Possession Within Agreed Time Constitutes 'Default' Under Section 18 of Real Estate (Regulation and Development) Act, 2016, Entitling Allottees to Full Refund with Interest.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 1
Judgement Image
Font size:
Print

Case Note & Summary

The appellant, Balaji Construction Company, a promoter, entered into agreements with various allottees for the sale of apartments in a project. The agreements stipulated a possession date, which the promoter failed to meet. The allottees filed complaints before the Maharashtra Real Estate Regulatory Authority (RERA) seeking refund with interest under Section 18 of the Real Estate (Regulation and Development) Act, 2016. The Authority dismissed the complaints, holding that the delay was due to force majeure. The allottees appealed to the Maharashtra Real Estate Appellate Tribunal, which allowed the appeals and directed the promoter to refund the amounts paid with interest. The promoter filed second appeals before the High Court under Section 58 of the RERA Act. The High Court considered whether the Appellate Tribunal's order was sustainable. The court noted that the promoter had failed to deliver possession within the agreed period, which constitutes 'default' under Section 18. The promoter's claim of force majeure was not supported by evidence. The court held that the Appellate Tribunal had correctly applied the law and directed refund with interest. The High Court dismissed the second appeals, finding no substantial question of law involved. The court also disposed of the interim applications.

Headnote

A) Real Estate Law - Default in Possession - Section 18 of Real Estate (Regulation and Development) Act, 2016 - Refund with Interest - The appellant-promoter failed to deliver possession of the apartment within the stipulated period as per the agreement. The allottees sought refund under Section 18. The Appellate Tribunal directed refund with interest. The High Court held that failure to deliver possession within the agreed time constitutes 'default' under Section 18, entitling the allottee to refund with interest. The promoter's plea of force majeure was rejected as no evidence was produced. (Paras 1-20)

B) Real Estate Law - Appellate Tribunal's Powers - Section 44 of Real Estate (Regulation and Development) Act, 2016 - The Appellate Tribunal has the power to pass interim orders and final orders including refund. The High Court upheld the Tribunal's order as it was within its jurisdiction and based on facts. (Paras 15-18)

C) Real Estate Law - Second Appeal - Section 58 of Real Estate (Regulation and Development) Act, 2016 - The High Court's jurisdiction in second appeal is limited to substantial questions of law. The court found no substantial question of law involved as the Tribunal's findings were based on evidence and law. (Paras 19-20)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Maharashtra Real Estate Appellate Tribunal was justified in directing the promoter to refund the amounts paid by the allottees with interest for failure to deliver possession within the agreed period, and whether such direction is sustainable in law.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The High Court dismissed all the second appeals, upholding the order of the Maharashtra Real Estate Appellate Tribunal directing the appellant to refund the amounts paid by the allottees with interest. The interim applications were also disposed of.

Law Points

  • Section 18 of RERA Act
  • 2016
  • Default in possession
  • Refund with interest
  • Promoter's obligation
  • Appellate Tribunal's powers
  • Second appeal under Section 58 of RERA Act
Subscribe to unlock Law Points Subscribe Now

Case Details

2024 LawText (BOM) (02) 195

Second Appeal No. 731 of 2023 with connected matters

2024-02-20

Sandeep V. Marne J.

2024:BHC-AS:8201

Mr. Gauraj Shah a/w Mr. Keyur Adhvaryu i/b Mr. Yatin R. Shah, for the Appellants in all Second Appeals. Mr. Harshad Bhadbhade a/w Ms. Arya Sapre, for Respondents in SA/731/2023, SA/734/2023, SA/737/2023, SA/736/2023, SA/733/2023, SA/735/2023, SA/732/2023. Mr. Mutahhar Khan a/w Ms. Nehaa Shah i/b Mr. Dhiren H. Shah, for Respondent in SA/727/2023.

Balaji Construction Company

Anjusha Ajit Kadam & Ors. (in SA/731/2023), Jayantilal Makwana (in SA/727/2023), Vikram B Shah (in SA/734/2023), Achala Abhijit Patil and Anr. (in SA/737/2023), Prashant Sukhadev Mahajan (in SA/736/2023), Chintan Mahesh Shah (in SA/733/2023), Shashikumar Mishra (in SA/735/2023), Hetal B Shah (in SA/732/2023)

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Second appeals under Section 58 of the Real Estate (Regulation and Development) Act, 2016 challenging the order of the Maharashtra Real Estate Appellate Tribunal directing refund with interest to allottees.

Remedy Sought

The appellant-promoter sought to set aside the Appellate Tribunal's order directing refund with interest to the allottees.

Filing Reason

The appellant failed to deliver possession of apartments within the agreed period, leading to complaints by allottees for refund under Section 18 of the RERA Act.

Previous Decisions

The Maharashtra Real Estate Regulatory Authority dismissed the allottees' complaints. The Maharashtra Real Estate Appellate Tribunal allowed the appeals and directed refund with interest.

Issues

Whether the failure to deliver possession within the agreed period constitutes 'default' under Section 18 of the RERA Act, 2016? Whether the Appellate Tribunal was justified in directing refund with interest?

Submissions/Arguments

Appellant argued that the delay was due to force majeure and that the allottees were not entitled to refund. Respondents argued that the promoter failed to deliver possession within the agreed time and thus they are entitled to refund with interest under Section 18.

Ratio Decidendi

Failure to deliver possession of an apartment within the stipulated period as per the agreement constitutes 'default' under Section 18 of the Real Estate (Regulation and Development) Act, 2016, entitling the allottee to seek refund with interest. The promoter's claim of force majeure must be supported by evidence; otherwise, the allottee is entitled to the statutory remedy.

Judgment Excerpts

These Second Appeals filed by the Appellant challenge common Order dated 27 October 2023 passed by Maharashtra Real Estate Appellate Tribunal directing Appellant to refund the amounts paid by the allottees with interest. The Appellate Tribunal has correctly applied the law and directed refund with interest.

Procedural History

The allottees filed complaints before the Maharashtra Real Estate Regulatory Authority, which were dismissed. They appealed to the Maharashtra Real Estate Appellate Tribunal, which allowed the appeals and directed refund with interest. The promoter filed second appeals before the High Court under Section 58 of the RERA Act.

Acts & Sections

  • Real Estate (Regulation and Development) Act, 2016: Section 18, Section 44, Section 58
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Quashes Demolition Notice Against Tenants in Municipal Corporation Dispute — Notice Issued Without Hearing Tenants Violates Principles of Natural Justice. Section 264(1) of Maharashtra Municipal Corporations Act, 1949 Requires Not...
Related Judgement
High Court High Court of Karnataka Dismisses Writ Petitions Challenging Election Calendar for Co-operative Society. Court holds that election process once commenced must be allowed to conclude and that the remedy of election petition is available to challenge i...