Bombay High Court Partially Allows Promoter's Appeal in RERA Interest Dispute — Interest on Delayed Possession to Run from 1 July 2016, Not 1 January 2020, But COVID Period Excluded from Interest Liability. The court held that the promoter is liable to pay interest from the date of default as per the agreement, but the COVID-19 pandemic period is excluded from interest liability.

High Court: Bombay High Court Bench: BOMBAY
  • 3
Judgement Image
Font size:
Print

Case Note & Summary

The case involves two appeals filed by M/s. Pragatej Builders And Developers Pvt. Ltd. (the promoter) against a common judgment and order dated 7 February 2023 passed by the MahaRERA Tribunal. The Tribunal had partly allowed appeals filed by the flat purchasers (Mr. Abhishek Anuj Sukhadia and Mrs. Chaya Anuj Sukhadia) and the promoter, directing the promoter to pay interest to the flat purchasers from 1 July 2016 (the date stipulated in the agreement for sale for handing over possession) instead of 1 January 2020 (as claimed by the promoter). The promoter was also aggrieved by the rejection of its prayer for exclusion of the COVID-19 pandemic period from interest liability. The High Court held that the promoter is liable to pay interest from the date of default as per the agreement, i.e., 1 July 2016, and not from the extended date claimed by the promoter. However, the court also held that the promoter is entitled to exclusion of the COVID-19 pandemic period from interest liability, as the pandemic constituted a force majeure event beyond the promoter's control. The court modified the Tribunal's order accordingly, directing that interest be calculated from 1 July 2016 but excluding the period from 25 March 2020 to 27 July 2021 and from 27 July 2021 to 30 September 2021.

Headnote

A) Real Estate Law - Interest on Delayed Possession - Date of Default - Under Section 18 of the Real Estate (Regulation and Development) Act, 2016 (RERA) read with agreement for sale - The court considered whether interest on delayed possession should run from the date stipulated in the agreement (1 July 2016) or from a later date (1 January 2020) as claimed by the promoter. Held that the promoter is liable to pay interest from the date of default as per the agreement, i.e., 1 July 2016, and not from the extended date claimed by the promoter (Paras 1-10).

B) Real Estate Law - Exclusion of COVID-19 Pandemic Period - Force Majeure - Under RERA and general law - The court examined whether the promoter is entitled to exclusion of the COVID-19 pandemic period (25 March 2020 to 27 July 2021 and 27 July 2021 to 30 September 2021) from interest liability. Held that the promoter is entitled to exclusion of the COVID-19 pandemic period from interest liability, as the pandemic constituted a force majeure event beyond the promoter's control (Paras 11-15).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the MahaRERA Tribunal correctly directed payment of interest from 1 July 2016 instead of 1 January 2020, and whether the COVID-19 pandemic period should be excluded from interest liability.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The High Court partially allowed the appeals. It held that the promoter is liable to pay interest from 1 July 2016 (the date stipulated in the agreement) and not from 1 January 2020. However, the court also held that the promoter is entitled to exclusion of the COVID-19 pandemic period from interest liability, i.e., from 25 March 2020 to 27 July 2021 and from 27 July 2021 to 30 September 2021. The order of the MahaRERA Tribunal was modified accordingly.

Law Points

  • Interest on delayed possession under RERA
  • Date of default for interest calculation
  • Exclusion of COVID-19 pandemic period from interest liability
  • Promoter's obligation to pay interest for delay in handing over possession
  • Interpretation of agreement for sale and RERA provisions
Subscribe to unlock Law Points Subscribe Now

Case Details

2024 LawText (BOM) (01) 189

Second Appeal No.688 of 2023 with Second Appeal No.689 of 2023

2024-01-23

Sandeep V. Marne, J.

Mr. K.K. Malpathak a/w Mr. Indravadan Buddhadev for Appellants; Mr. Farhan Khan a/w Mr. Rubin Vakil, Mr. Manish Doshi, Ms. Heena T. & Ms. Ankita i/b Vimadalal & Co. for Respondents

M/s. Pragatej Builders And Developers Pvt. Ltd.

Mr. Abhishek Anuj Sukhadia and Mrs. Chaya Anuj Sukhadia

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeals under Section 58 of the Real Estate (Regulation and Development) Act, 2016 challenging the order of the MahaRERA Tribunal regarding interest on delayed possession.

Remedy Sought

The promoter sought modification of the Tribunal's order to change the date from which interest is calculated from 1 July 2016 to 1 January 2020 and to exclude the COVID-19 pandemic period from interest liability.

Filing Reason

The promoter was aggrieved by the Tribunal's direction to pay interest from 1 July 2016 instead of 1 January 2020 and the rejection of its prayer for exclusion of the COVID-19 pandemic period.

Previous Decisions

The MahaRERA Authority passed an order on 27 July 2021, which was challenged by both parties before the MahaRERA Tribunal. The Tribunal passed a common judgment and order on 7 February 2023, partly allowing both appeals.

Issues

Whether the MahaRERA Tribunal correctly directed payment of interest from 1 July 2016 instead of 1 January 2020. Whether the COVID-19 pandemic period should be excluded from interest liability.

Submissions/Arguments

The promoter argued that the date for handing over possession was extended to 1 January 2020 due to various reasons, and interest should run from that date. The promoter also argued that the COVID-19 pandemic period should be excluded from interest liability as it was a force majeure event. The flat purchasers argued that the agreement stipulated 1 July 2016 as the date for possession, and the promoter is liable for delay from that date.

Ratio Decidendi

The promoter is liable to pay interest for delayed possession from the date stipulated in the agreement for sale, i.e., 1 July 2016, and not from any extended date claimed by the promoter. However, the COVID-19 pandemic period constitutes a force majeure event, and the promoter is entitled to exclusion of that period from interest liability.

Judgment Excerpts

These two Appeals are filed by the Promoter challenging common Judgment and Order dated 7 February 2023 in Appeal No.AT0006000000053317 of 2021 filed by the Respondents/flat purchasers and in Appeal No.AT0006000000093905 of 2022 filed by the promoter. The Appellant / Promoter is aggrieved by the MahaRERA Tribunal’s decision in directing payment of interest to the Respondents from 1 July 2016 instead of 1 January 2020.

Procedural History

The MahaRERA Authority passed an order on 27 July 2021. Both the flat purchasers and the promoter filed appeals before the MahaRERA Tribunal. The Tribunal passed a common judgment and order on 7 February 2023, partly allowing both appeals. The promoter then filed the present second appeals before the High Court.

Acts & Sections

  • Real Estate (Regulation and Development) Act, 2016: Section 18
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Writ Petition Challenging Rejection of Scheduled Tribe Certificate Validity for NEET-UG Candidate. Court Holds That Tribe Validity Certificate of Blood Relative Cannot Be Ignored Unless Cancelled.
Related Judgement
High Court High Court of Karnataka Dismisses Petition Seeking Stay of Divorce Proceedings Pending Nullity Petition Under Section 10 CPC. Nullity and Divorce Petitions Under Hindu Marriage Act, 1955 Involve Distinct Matters in Issue, Hence Section 10 CPC Stay No...