Bombay High Court Considers Whether Allottee's Withdrawal Right Under RERA Section 18 Is Unqualified After Possession with OC Was Offered; Questions If Such Possession Must Be Litigation-Free Under Section 19(10)

High Court: Bombay High Court Bench: BOMBAY
  • 2
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose under the Real Estate (Regulation and Development) Act, 2016 between a common developer and four sets of allottees for flats in project Aaryavarta at Mahale Farm, Off Mumbai-Agra Road, Nashik. Agreements for sale were executed in January and October 2013 with a promised possession date of 31/12/2017. The allottees paid various amounts under the agreements. In 2013, an ex-parte injunction order was passed by the High Court in third-party litigation and served upon the developer. The developer informed the allottees about the litigation through letters dated 22/05/2013, 12/07/2013 and 23/12/2015, and on 16/02/2016 informed them that the court decision had come in favour of the developer. The Occupation Certificate for the building was obtained on 11/07/2018. By first letter dated 21/12/2018, the developer informed the allottees that possession could be given, attached a copy of the OC, and demanded balance payment. By second letter dated 01/09/2019, the developer informed that the Completion Certificate was also obtained and again asked the allottees to make remaining payment and take possession. On 18/02/2020, the allottees demanded refund of amounts paid, alleging that the title of the land was defective and the developer was not in a position to offer possession for use and occupation. On 23/03/2020, the allottees filed complaints before MahaRERA seeking refund under Section 18 of the Act. MahaRERA by common order dated 17/02/2022 rejected the complaints refusing refund but kept open the claim of compensation under Sections 18(2) and 18(3). The allottees appealed to the Maharashtra Real Estate Appellate Tribunal, which by common judgment and order dated 30/01/2024 allowed the appeals, set aside the MahaRERA order, and directed the developer to refund all amounts including taxes and registration fees with interest from the date of receipt, with default interest and continuing charge on the flats until refund. The developer then filed four second appeals before the Bombay High Court. By order dated 19/06/2025, the High Court framed two substantial questions of law: (A) whether the allottee under Section 18 has an unqualified right to withdraw from the project even after possession with Occupation Certificate was offered; and (B) whether possession offered by the developer along with Occupation Certificate under Section 19(10) can only be possession without any litigation over the subject property. The appeals were admitted on these questions and heard finally by consent. The appellant argued that an allottee cannot wait indefinitely to demand refund, and that the decision must be made within a reasonable time, with Section 19(10) providing statutory indication of two months from receipt of OC; meanwhile the developer cannot sell the flat to a third party. The respondents argued that Sections 18(1)(a), 19(4) and 19(10) must be harmoniously construed, and that possession must be in terms of the agreement; they alleged defective title and contended that the allottee has an unqualified right to seek refund without any time limit. The Amicus Curiae assisted the court by taking it through various provisions and citing Imperia Structures Ltd. v. Anil Pant & Anr. The court considered Sections 2(q), 2(zf), 4(2)(l), 12, 18 and 19(10) of the Act. The extracted portion of the judgment ends before the final operative order, so the final decision of the High Court is not available in the provided text.

Headnote

A) Real Estate Regulation - Withdrawal from Project - Allottee's Right to Refund under Section 18 - Real Estate (Regulation and Development) Act, 2016, Sections 18, 19(10) - The appeals raised substantial question whether allottee has an unqualified right to withdraw from the project at any time after possession with Occupation Certificate was offered, even after the agreed date. The High Court noted that OC was obtained on 11.07.2018, possession was offered on 21.12.2018 and 01.09.2019, but the allottees demanded refund on 18.02.2020 citing defective title. The court admitted the appeals on this question and heard parties finally. Held that the question is a substantial question of law requiring interpretation of Sections 18 and 19(10) (Paras 3-9).

B) Real Estate Regulation - Possession under Section 19(10) - Whether Possession Offered with OC Must Be Litigation-Free - Real Estate (Regulation and Development) Act, 2016, Section 19(10) - The court framed second question whether possession offered by the developer along with Occupation Certificate can only be possession without any litigation over the subject property, considering allottees' allegation of defective title due to third-party litigation and ex-parte injunction. The court noted the factual background of litigation and communications to allottees, and the Appellate Tribunal's direction to refund. Held that this issue also raises a substantial question of law for adjudication (Paras 3-4, 8-9).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

(A) Whether the allottee, under section 18 of Real Estate (Regulation And Development) Act, 2016, has an unqualified right to withdraw from the project to mean that he can choose to decide withdrawal from project after whatever time he decides at his own will, when possession of a flat/apartment/plot/building with Occupation Certificate is already offered? (B) Also it needs to be considered whether the possession being offered by the developer alongwith Occupation Certificate (with reference to section 19(10) of the said Act) can only be possession without any litigation over the subject property?

Subscribe to unlock Issue of Consideration Subscribe Now

Law Points

  • Section 18 of RERA makes promoter liable on demand to allottee if promoter fails to complete or is unable to give possession in accordance with agreement by date specified
  • Section 19(10) requires allottee to take possession within two months of issue of occupancy certificate
  • Section 12 allows allottee to withdraw and get entire investment with interest if any false statement in advertisement or prospectus
  • promoter must declare legal title and encumbrances under Section 4(2)(l)
  • completion certificate and occupancy certificate are defined under Sections 2(q) and 2(zf)
Subscribe to unlock Law Points Subscribe Now

Case Details

2025 LawText (BOM) (07) 112

Second Appeal Nos. 391 of 2025, 392 of 2025, 393 of 2025 and 394 of 2025 with Interim Application Nos. 10454 of 2024, 3601 of 2024, 12371 of 2024 and 13186 of 2024

2025-07-18

M. M. Sathaye, J.

2025:BHC-AS:30212

Mr. G. S. Godbole, Senior Advocate a/w Mr. Sarthak Diwan and Mr. Avesh A. Ghadge for the Appellant in all Second Appeals; Mr. Yogesh Patki a/w Mr. A. S. Ramesan for the Respondents in all Second Appeals; Mr. Pradeep J. Thorat, Amicus Curiae appointed by Court assisted by Ms. Aditi Naikare and Mr. Aniesh S. Jadhav

Linker Shelter Pvt. Ltd.

Charmaine Chougule, Arvind D. Chougule, Annie E. Pinto, Edwin M. Pinto, Ramdas S. Gadiyar, Veena R. Gadiyar, Sanny M. Pinto, Nina S. Pinto

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Second appeals before the Bombay High Court arising from a common judgment and order of the Maharashtra Real Estate Appellate Tribunal which directed a developer to refund amounts to allottees under the Real Estate (Regulation and Development) Act, 2016.

Remedy Sought

The appellant developer sought to challenge the Appellate Tribunal order directing refund with interest and to obtain a favourable interpretation of Sections 18 and 19(10) of RERA; the respondent allottees sought to sustain the refund order.

Filing Reason

The appellant was aggrieved by the Appellate Tribunal order dated 30/01/2024 which set aside the MahaRERA order and directed refund of all amounts with interest to the allottees.

Previous Decisions

MahaRERA by common order dated 17/02/2022 rejected the allottees' complaints refusing refund but kept open compensation under Sections 18(2) and 18(3) of RERA. The Maharashtra Real Estate Appellate Tribunal by common judgment and order dated 30/01/2024 allowed the appeals, set aside the MahaRERA order, and directed the developer to refund all amounts including taxes and registration fees with interest from the date of receipt. The Bombay High Court by order dated 19/06/2025 framed two substantial questions of law and admitted the appeals.

Issues

Whether the allottee, under section 18 of Real Estate (Regulation And Development) Act, 2016, has an unqualified right to withdraw from the project to mean that he can choose to decide withdrawal from project after whatever time he decides at his own will, when possession of a flat/apartment/plot/building with Occupation Certificate is already offered? Whether the possession being offered by the developer alongwith Occupation Certificate (with reference to section 19(10) of the said Act) can only be possession without any litigation over the subject property?

Submissions/Arguments

Appellant submitted that there cannot be a strait-jacket formula for all contingencies, but that in the present case the agreed delivery date was 31.12.2017, OC was obtained on 11.07.2018, possession was offered on 21.12.2018 and 01.09.2019, and the allottees waited until 18.02.2020 to demand refund; it is not permissible to wait indefinitely at the sweet will of the allottee when it is his/her duty to take possession within two months from receipt of OC under Section 19(10); during the period of indecision, market prices may rise and the developer cannot sell the flat to any third party. Respondents submitted that Sections 18(1)(a), 19(4) and 19(10) of RERA must be harmoniously construed and possession has to be in terms of the agreement for Section 19(10) to apply; they alleged that the title of the land was defective and therefore the possession offered was not as per the agreement; allottees have an unqualified right to seek refund and it cannot be bound by any time period. Amicus Curiae assisted the court by taking it through various provisions of RERA and cited the earlier judgment of Imperia Structures Ltd. v. Anil Pant & Anr., (2020) 10 SCC 783.

Judgment Excerpts

Whether the allottee, under section 18 of Real Estate (Regulation And Development) Act, 2016, has an unqualified right to withdraw from the project to mean that he can choose to decide withdrawal from project after whatever time he decides at his own will, when possession of a flat/apartment/plot/building with Occupation Certificate is already offered? Also it needs to be considered whether the possession being offered by the developer alongwith Occupation Certificate (with reference to section 19(10) of the said Act) can only be possession without any litigation over the subject property? By the said impugned Order, the common order dated 17/02/2022 passed in 4 complaints filed by Respondent allottees, was set aside and the Appellant/promoter was directed to refund to the Respondents all the amounts including amounts paid for taxes, registration fees etc. with interest from the date of receipt of the amount.

Procedural History

Agreements for sale of four flats were executed in January and October 2013 with promised possession date 31/12/2017. In 2013, an ex-parte injunction was passed by the High Court in third-party litigation and served on the developer. Occupation Certificate was obtained on 11/07/2018. Developer issued possession letters on 21/12/2018 and 01/09/2019. Allottees demanded refund on 18/02/2020 citing defective title. Allottees filed complaints before MahaRERA on 23/03/2020. MahaRERA rejected the complaints on 17/02/2022 but kept open compensation. Allottees appealed to Maharashtra Real Estate Appellate Tribunal, which allowed the appeals on 30/01/2024 and directed refund with interest. Developer filed four second appeals before Bombay High Court. By order dated 19/06/2025, the High Court framed two substantial questions of law. On 18/07/2025, the appeals were admitted on those questions and heard finally by consent.

Acts & Sections

  • Real Estate (Regulation and Development) Act, 2016: 2(q), 2(zf), 4(2)(l), 12, 18(1)(a), 18(2), 18(3), 19(4), 19(10)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Quashed Istegashas Issued Under Section 110(e) CrPC for Lack of Breach of Peace and Granted Token Compensation for Wrongful Detention. The Court Found That the Notices Did Not Disclose Any Element of Habitual Offences Involving Brea...
Related Judgement
High Court Bombay High Court Examines Revenue's Appeal Against ITAT Order Upholding Deduction Under Section 80IB(10) and Quashing Assessment Due to Search Warrant in Name of Non-Existent Entity. The appeal pertained to whether flower bed areas, service areas, a...