Bombay High Court Dismisses Promoter's Appeal in RERA Delayed Possession Case, Upholds Allottees' Right to Interest. Section 18 of RERA Overrides Section 55 of Contract Act; Acceptance of Delayed Possession Does Not Waive Right to Compensation.

The case involves a Second Appeal filed by CCI Projects Private Limited (the promoter) against the judgment of the Maharashtra Real Estate Appellate T...

© Image Copyrights Juris Services & Technology

Bombay High Court Allows Promoter's Appeal in RERA Case, Holding That Acceptance of Delayed Possession Without Protest Does Not Waive Right to Interest Under Section 18 of RERA. Statutory Right to Interest Under RERA Cannot Be Waived by Mere Acceptance of Possession Without a Clear Agreement.

The case involves a Second Appeal filed by CCI Projects Private Limited (the promoter) against an order of the Maharashtra Real Estate Appellate Tribu...

© Image Copyrights Juris Services & Technology

Bombay High Court Directs Statewide Integration of Building Plan Management System with MahaRERA to Prevent Fraudulent Real Estate Registrations. Court Emphasizes Need for Coordinated Verification of Commencement and Occupation Certificates Under RERA Act.

The petitioner, Sandeep Pandurang Patil, filed a Public Interest Litigation under Article 226 of the Constitution of India before the Bombay High Cour...

© Image Copyrights Juris Services & Technology

Bombay High Court Quashes Charity Commissioner's Order Allowing Intervention in Trust's Section 36 Application. Right to be Heard Under Maharashtra Public Trust Act, 1951 Limited to Persons with Direct Interest in Trust Property.

The petitioner, Shree Khambhati Modh Vanik Samaj, is a public charitable trust registered under the Maharashtra Public Trust Act, 1950. It owns a prop...

© Image Copyrights Juris Services & Technology

Bombay High Court Partly Allows Promoter's Appeal in RERA Interest Case. Appellate Tribunal's Suo Motu Adjudication on Termination of Agreement Set Aside as Without Jurisdiction.

The case involves an appeal under Section 58 of the Real Estate (Regulation and Development) Act, 2016 (RERA Act) filed by Satyam Developers, the prom...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses Appeals Against RERA Orders on Pre-2017 Agreements, Upholding Retrospective Application of MahaRERA. Court holds that Section 3(1) of RERA applies to ongoing projects even if agreements were executed before the Act came into force.

The judgment concerns three connected second appeals filed before the Bombay High Court under the Civil Appellate Jurisdiction. The appeals were filed...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses Second Appeals by Developer in Possession Suits — Concurrent Findings of Fact Cannot Be Reopened Under Section 100 CPC. Suits for possession based on title and prior possession were decreed; no substantial question of law arose.

The appellant, M/s. Samruddhi Developers, a partnership firm, filed four second appeals under Section 100 of the Code of Civil Procedure, 1908, challe...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses Writ Petition Challenging Part Occupation Certificate for Building Height Violation. Flat Purchasers Cannot Seek Revocation of Occupation Certificate as They Have Alternative Remedy Under RERA and No Vested Right to Challenge Planning Permissions.

The petitioners, Sanjay Phulwaria and others, filed a writ petition under Article 226 of the Constitution of India before the Bombay High Court challe...