Bombay High Court Allows Landlord's Petition in Rent Control Dispute — Remand Order Set Aside for Lack of Jurisdiction. Landlord's Application for Permission Under Clause 13(3)(vi) of C.P. and Berar Letting of Premises and Rent Control Order, 1949 Held Maintainable Despite Earlier Proceedings Under Other Sub-Clauses....

The petitioner, Purushottam Ramlal Shukla, is the landlord of premises at Dharampeth, Nagpur, comprising two rooms admeasuring 22 ft. X 33 ft. let out to the respondents for business purposes. On 18.0...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses Writ Petition Challenging Disciplinary Orders in Insurance Company Service Matter — Limited Scope of Judicial Review Under Article 226 for Private Sector Domestic Enquiries. The court declined to interfere with concurrent findings of improper supervision by a Branch Manager, as there was no perversity or breach of substantive provisions....

The petitioner, Hemraj s/o Budha Raut, a Branch Manager of National Insurance Company Ltd., challenged the concurrent disciplinary orders passed by the Assistant General Manager (Disciplinary Authorit...

© Image Copyrights Juris Services & Technology

High Court Dismisses Cooperative Society's Challenge to Allotment Order — Transfer of Plot Directed to Disputant Member. Concurrent findings of fact by Cooperative Court and Appellate Court upheld under Maharashtra Cooperative Societies Act, 1960....

The petitioner, Vishwabharti Gruha Nirman Sahakari Sanstha Limited, a cooperative housing society, challenged the judgments and orders of the Cooperative Court and the Cooperative Appellate Court. The...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses Landlord's Petition Challenging Remand Order in Rent Control Matter. Landlord Held Ineligible for Permission Under Clause 13(3)(vi) of C.P. and Berar Letting of Premises and Rent Control Order, 1949 Due to Availability of Other Suitable Accommodation....

The petitioner, Purushottam Ramlal Shukla, is the landlord of premises at Dharampeth, Nagpur, comprising two rooms admeasuring 22 ft. x 33 ft. let out to the respondents for business purposes. On 18.0...

© Image Copyrights Juris Services & Technology

Bombay High Court Acquits Accused in Abetment of Suicide Case Due to Lack of Instigation. Mere questioning about illicit relationship does not constitute abetment under Section 306 IPC as there was no direct or indirect act of instigation or intentional aid to commit suicide....

The case involves an appeal against the conviction of two accused persons, Premila w/o Bandu Dahat and Bandu Gadi Dahat, under Section 306 of the Indian Penal Code for abetment of suicide. The decease...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses Writ Petition Challenging Retender Notice in Foodgrain Transportation Contract. State Authority's Decision to Reject Highest Bid and Issue Fresh Tender Upheld as Not Arbitrary or Malafide....

The petitioner, Shri Ganesh Carriers, a registered government contractor, participated in a tender process for transportation of foodgrains in Nagpur district for the period 2013-2016. The petitioner'...

© Image Copyrights Juris Services & Technology

Bombay High Court Protects Service of Employee Despite Invalidated Caste Certificate Based on Full Bench Judgment in Arun Vishwanath. Mere invalidation of caste claim does not entail withdrawal of benefits or discharge from employment that became final prior to Milind's case....

The petitioner, Chandrapal Ratansingh Rajput, filed a writ petition challenging the order dated 31.03.2006 of the Divisional Caste Scrutiny Committee, Amravati, which invalidated his caste certificate...

© Image Copyrights Juris Services & Technology

Bombay High Court Disposes of Writ Petition Challenging Industrial Court's Reversal of Labour Court Order, Holding Employer May Terminate Service in Accordance with Labour Laws. The Court declined to examine merits as the employee was already reinstated and working, but clarified that any future termination must comply with labour laws....

The petitioner, an employee, filed a complaint alleging unfair labour practice. The Labour Court in Complaint ULP No. 30 of 1991 held that the employer was engaged in unfair labour practice under Item...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses MSRTC Petition Challenging Industrial Court Order to Allow Friday Prayer Concession for Muslim Employees. Unfair Labour Practice Under MRTU and PULP Act Upheld for Discontinuation of Customary Concession....

The Maharashtra State Road Transport Corporation (MSRTC) filed a writ petition challenging the judgment and order of the Industrial Court dated 4th September 2004 in Complaint (ULPN) No. 373 of 1996. ...

© Image Copyrights Juris Services & Technology

Bombay High Court Allows Rebate Claim for Toll Contractor in Flood-Related Traffic Reduction - Contractual Force Majeure Clause Interpreted. Clause 7 of the contract entitles rebate for closure due to natural calamities, and Clause 8 does not bar such claim; order rejecting claim without hearing set aside....

The petitioner, Prakash Khampariya, a toll contractor, entered into a contract with the Executive Engineer, National Highway, Nagpur, for collection of toll on a bridge. Due to heavy rains and floods ...