Bombay High Court Allows Rebate Claim for Toll Contractor in Flood-Related Traffic Reduction - Contractual Force Majeure Clause Interpreted. Clause 7 of the contract entitles rebate for closure due to natural calamities, and Clause 8 does not bar such claim; order rejecting claim without hearing set aside.

High Court: Bombay High Court Bench: NAGPUR In Favour of Accused
  • 85
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Prakash Khampariya, a toll contractor, entered into a contract with the Executive Engineer, National Highway, Nagpur, for collection of toll on a bridge. Due to heavy rains and floods between 13/07/1994 and 24/07/1994, the flow of traffic on the bridge was reduced to a large extent, resulting in less collection of toll. The petitioner claimed rebate under Clause 7 of the contract, which provides for rebate on prorata basis for closure due to act of God or natural calamities. The respondent No.1 rejected the claim and imposed penalty by order dated 21/11/1997 without giving any personal hearing or opportunity to the petitioner. The petitioner challenged this order by way of writ petition. The court examined Clause 7 and Clause 8 of the contract. Clause 7 entitles the agent to rebate for closure due to natural calamities, while Clause 8 restricts any compensation for change in traffic pattern. The court noted that the S.D. Engineer's communication confirmed that traffic was closed due to floods. The court held that the reduction in traffic due to floods amounts to closure under Clause 7, and Clause 8 does not bar the claim. The impugned order was set aside as it violated principles of natural justice. The court directed the respondent No.1 to decide the petitioner's claim afresh after giving an opportunity of hearing, within three months. The petition was allowed.

Headnote

A) Contract Law - Force Majeure - Rebate for Natural Calamity - Clause 7 of Contract - The petitioner, a toll contractor, claimed rebate for 13 days when heavy rains and floods reduced traffic on the bridge. Clause 7 provides rebate on prorata basis for closure due to act of God or natural calamities. The court held that the reduction in traffic due to floods amounts to closure within the meaning of Clause 7, and the petitioner is entitled to rebate. The impugned order rejecting the claim without giving opportunity of hearing was set aside. (Paras 2-5)

B) Administrative Law - Natural Justice - Opportunity of Hearing - The respondent No.1 passed the impugned order dated 21/11/1997 without giving any personal hearing or opportunity to the petitioner to justify the claim. The court held that such order violates principles of natural justice and is liable to be set aside. (Para 3)

C) Contract Law - Interpretation of Clauses 7 and 8 - Clause 8 restricts rebate for change in traffic pattern, but Clause 7 specifically covers closure due to natural calamities. The court held that Clause 8 does not override Clause 7, and the petitioner's claim falls under Clause 7. (Paras 3-4)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the petitioner is entitled to rebate under Clause 7 of the contract for reduction in toll collection due to heavy rains and floods, and whether the impugned order rejecting the claim without hearing is sustainable.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The petition is allowed. The impugned order dated 21/11/1997 is quashed and set aside. The respondent No.1 is directed to decide the petitioner's claim for rebate afresh after giving an opportunity of hearing to the petitioner, within three months from the date of the order.

Law Points

  • Contract interpretation
  • force majeure
  • rebate
  • natural calamity
  • toll collection
  • opportunity of hearing
Subscribe to unlock Law Points Subscribe Now

Case Details

2015 LawText (BOM) (01) 70

Writ Petition No. 3265 of 1999

2015-01-08

Anoop V. Mohta, A. R. Joshi

Mr. Anjan De for petitioner; Ms N.P. Mehta for respondents

Prakash Khampariya

Executive Engineer, National Highway, Divn.No.K, Nagpur; Collector, Jabalpur; State of Maharashtra

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition challenging the order of the Executive Engineer rejecting the claim of rebate and imposing penalty.

Remedy Sought

Petitioner sought quashing of the impugned order dated 21/11/1997 and direction to grant rebate for 13 days due to floods.

Filing Reason

The respondent No.1 rejected the petitioner's claim for rebate under Clause 7 of the contract for reduction in toll collection due to heavy rains and floods, and imposed penalty without giving opportunity of hearing.

Previous Decisions

The respondent No.1 passed the impugned order dated 21/11/1997 rejecting the claim and directing deposit of balance amount within seven days.

Issues

Whether the petitioner is entitled to rebate under Clause 7 of the contract for reduction in toll collection due to heavy rains and floods? Whether the impugned order rejecting the claim without giving opportunity of hearing is sustainable?

Submissions/Arguments

Petitioner argued that due to heavy rains and floods between 13/07/1994 to 24/07/1994, traffic on the bridge was reduced, and he is entitled to rebate under Clause 7 of the contract. Respondents argued that Clause 8 of the contract restricts any compensation for change in traffic pattern, and the claim was rightly rejected.

Ratio Decidendi

Clause 7 of the contract provides for rebate on prorata basis for closure due to act of God or natural calamities. The reduction in traffic due to floods amounts to closure within the meaning of Clause 7. Clause 8 does not override Clause 7. The impugned order rejecting the claim without giving opportunity of hearing violates principles of natural justice.

Judgment Excerpts

Clause 7 of the contract condition is produced as under – 7. Upon the temporary closure of the said bridge for any reason whatsoever; the Agent shall be entitled to claim rebate on prorato basis... Clause 8, however, restricts any compensation rebate or reduction in amount on account of the change or variation in traffic pattern and volume or intensity for any reason whatsoever. There is concerned S.D.Engineer’s communication to the Executive Engineer whereby it is specifically mentioned that between 13/07/1994 to 24/07/1994 because of floods, the traffic was closed and, therefore, toll could not be collected.

Procedural History

The petitioner filed a claim for rebate which was rejected by the respondent No.1 by order dated 21/11/1997. The petitioner issued a legal notice on 24/02/1997. Thereafter, the petitioner filed the present writ petition in 1999. The matter was heard finally on 08.01.2015.

Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Accused's Application for Production of Document Showing Authority of Complainant in PCPNDT Act Case. Right to Fair Trial Includes Right to Challenge Complainant's Authority at Pre-Charge Stage Under Section 2(a) of Pre-Conce...
Related Judgement
Supreme Court Supreme Court Allows Land Owner in Company Winding Up Matter to Appeal Sale Order Despite Not Being Party Before Company Judge. Natural Justice and Rule 103 of Companies (Court) Rules, 1959 Require Notice to Persons Prejudicially Affected Before Sale...