Bombay High Court Dismisses Claims for Damages Against Plaintiff for Wrongful Arrest of Cargo in Admiralty Suit — Undertaking Under Rule 941 of Bombay High Court (OS) Rules Not Enforceable After Suit Withdrawal Without Adjudication on Merits.

The Plaintiff, Navbharat International Ltd., filed an admiralty suit and obtained an ex-parte order dated 12th January 2010 for arrest of cargo on boa...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses Petition Challenging Arbitral Award in Pipeline Construction Dispute. Court upholds arbitrator's findings on breach of contract and quantum of damages, rejecting challenge under Section 34 of Arbitration and Conciliation Act, 1996.

The petitioner, Mahanagar Gas Ltd., challenged an arbitral award dated 5th March 2010 passed by a sole arbitrator under Section 34 of the Arbitration ...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses Writ Petition Challenging Land Acquisition for High-Speed Rail Project Due to Lack of Locus Standi. Petitioners, Not Being Recorded Titleholders, Cannot Challenge Acquisition Under Right to Fair Compensation Act, 2013.

The petitioners, Dilip Babubhai Shah and others, filed a writ petition before the Bombay High Court challenging the land acquisition proceedings initi...

© Image Copyrights Juris Services & Technology

High Court of Karnataka Dismisses Appeal Against Arbitral Award in Construction Contract Dispute. Court upholds rejection of claims for additional payment due to lack of evidence and failure to prove that extra work was ordered by the Railways.

The appellant, M/s. N.N. Constructions, a proprietary concern, filed a commercial appeal under Section 37(1)(c) of the Arbitration and Conciliation Ac...