Case Note & Summary
The appellant, M/s. N.N. Constructions, a proprietary concern, filed a commercial appeal under Section 37(1)(c) of the Arbitration and Conciliation Act, 1996 (A&C Act) read with Section 13(1-A) of the Commercial Court Act, 2015, challenging the judgment dated 30.01.2026 passed by the LXXXII Additional City Civil and Sessions Judge, Commercial Court, Bengaluru in Com.A.P.No.113/2025. The Commercial Court had dismissed the appellant's petition under Section 34 of the A&C Act seeking to set aside an arbitral award dated 05.05.2025 delivered by respondent No.4 (Sole Arbitrator) in A.C.No.300/2024. The appellant had invoked the arbitration clause in relation to disputes arising under an agreement dated 27.04.2017 with the Union of India, South Western Railway (respondents 1 to 3). The arbitral tribunal rejected the appellant's claims for additional payment for extra work allegedly performed beyond the contract. The appellant contended that the award was patently illegal and perverse, and that the Commercial Court erred in not setting it aside. The High Court, after hearing the parties, held that the scope of interference under Section 34 of the A&C Act is narrow and does not permit reappreciation of evidence. The court found that the arbitral tribunal had considered the evidence and reached a plausible conclusion that the appellant failed to prove that the extra work was ordered by the Railways or that it was entitled to additional payment. The Commercial Court had correctly applied the limited grounds of challenge. Consequently, the High Court dismissed the appeal, upholding the arbitral award and the Commercial Court's order.
Headnote
A) Arbitration - Arbitral Award - Section 34 of Arbitration and Conciliation Act, 1996 - Scope of Interference - The court examined whether the arbitral award rejecting the appellant's claims for additional payment was liable to be set aside under Section 34 of the A&C Act. The court held that the scope of interference under Section 34 is narrow and does not permit reappreciation of evidence. The award was based on a plausible view of the evidence and did not suffer from patent illegality or perversity. (Paras 1-10) B) Arbitration - Arbitral Award - Section 37 of Arbitration and Conciliation Act, 1996 - Appeal against dismissal of Section 34 petition - The court considered the appeal under Section 37 against the Commercial Court's order dismissing the Section 34 petition. The court held that the Commercial Court had correctly applied the limited grounds of challenge and that no interference was warranted. (Paras 1-10) C) Contract - Construction Contract - Additional Work - Burden of Proof - The appellant claimed additional payment for extra work beyond the contract. The court held that the appellant failed to prove that the extra work was ordered by the Railways or that it was entitled to additional payment. The arbitral tribunal's finding that the claims were not supported by evidence was upheld. (Paras 3-10)
Issue of Consideration
Whether the Commercial Court erred in dismissing the petition under Section 34 of the Arbitration and Conciliation Act, 1996, and whether the arbitral award suffered from patent illegality or perversity warranting interference.
Final Decision
The High Court dismissed the commercial appeal, upholding the judgment of the Commercial Court and the arbitral award.
Law Points
- Arbitration
- Arbitral Award
- Section 34 of Arbitration and Conciliation Act
- 1996
- Section 37 of Arbitration and Conciliation Act
- Commercial Court Act
- 2015
- Scope of interference
- Patent illegality
- Perversity
- Evidence appreciation




