Case Note & Summary
The petitioner, Mahanagar Gas Ltd., challenged an arbitral award dated 5th March 2010 passed by a sole arbitrator under Section 34 of the Arbitration and Conciliation Act, 1996. The respondent, M/s Babulal Uttamchand & Co., had been awarded a contract for project management and construction of a pipeline network for domestic gas supply in Santacruz, Mumbai, by work order dated 12th October 2002, for a value of Rs.3,87,07,260. The contract was for three years. The respondent mobilised resources and invested heavily. The petitioner was responsible for providing gas connections to individuals, while the respondent was to enter into agreements with customers. The petitioner failed to provide gas despite completion of pipeline work, causing a delay of about 18 months. This led to non-payment by customers and consequent non-payment to the respondent. The respondent suffered heavy financial losses due to breach of contract. Additionally, the full work could not be completed in the stipulated period due to defaults by the petitioner, including changes in specifications. The respondent raised claims under the arbitration clause, and the petitioner filed counterclaims. The arbitrator heard the matter, examined witnesses, and passed a reasoned award. The petitioner challenged the award under Section 34. The court noted that on 7th August 2008, the parties agreed on figures for claim No.1 (balance amount for work done) and counter claim No.18 (material reconciliation recoveries). On 5th January 2009, they filed a jointly signed statement. The court held that the arbitrator's findings were based on evidence and not perverse, and the agreed figures were binding. The petition was dismissed with no order as to costs.
Headnote
A) Arbitration Law - Challenge to Arbitral Award - Section 34 of Arbitration and Conciliation Act, 1996 - Scope of Interference - The court considered whether the arbitral award suffered from patent illegality or perversity warranting interference under Section 34. The court held that the arbitrator's findings on breach of contract and quantum of damages were based on evidence and not perverse, and the petition was dismissed. (Paras 1-3) B) Contract Law - Breach of Contract - Delay in Supply of Gas - The dispute arose from a contract for pipeline construction where the petitioner failed to provide gas connections, causing delay and financial loss to the respondent. The arbitrator found the petitioner in breach. The court upheld the finding as based on material on record. (Paras 2-3) C) Arbitration Law - Agreed Figures - Binding Effect - The parties had agreed on certain figures for claim No.1 and counter claim No.18 on 7th August 2008 and 5th January 2009. The court held that such agreed figures are binding and cannot be re-agitated under Section 34. (Para 3)
Issue of Consideration
Whether the arbitral award dated 5th March, 2010 is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on the grounds of patent illegality or perversity.
Final Decision
The petition is dismissed. No order as to costs.
Law Points
- Section 34 of Arbitration and Conciliation Act
- 1996
- scope of interference with arbitral award
- breach of contract
- quantum of damages
- agreed figures between parties
- no review on merits


