Bombay High Court Allows Cooperative Housing Societies in Section 9 Arbitration Petitions Against Federation and Developer. Termination of Bipartite MoU and Cancellation of MHADA Layout NOC Eroded Foundation of Tripartite Development Agreement, Meriting Interim Protection from Interference.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 1
Judgement Image
Font size:
Print

Case Note & Summary

These were two commercial arbitration petitions filed under Section 9 of the Arbitration and Conciliation Act, 1996, by Borivali Shree Ganesh Nateshwar Cooperative Housing Society Ltd and Borivali Madhusudan Cooperative Housing Society Ltd against the Gorai Road MHB Cooperative Housing Society Association and SBM Realtors Pvt. Ltd. The petitioners sought interim protection to prevent the respondents from interfering with their independent redevelopment of their respective buildings. The lead petition, Commercial Arbitration Petition No. 452 of 2024, was treated as determinative of the companion petition by consent. The dispute arose from a redevelopment arrangement for a layout involving multiple cooperative societies that were members of the Gorai federation. On 27 October 2007, Gorai and SBM executed a Memorandum of Understanding, followed by a Deed of Confirmation on 17 February 2010. These bipartite agreements underpinned a tripartite Development Agreement dated 15 April 2011 among Borivali, Gorai and SBM, later supplemented by a Supplemental Development Agreement dated 9 December 2017. The layout development involved only 16 of the 26 member societies. Differences emerged over non-performance, and MHADA issued a show cause notice to SBM on 18 February 2022. Gorai resolved to terminate its relationship with SBM on 31 July 2022; MHADA cancelled the no objection certificate on 1 August 2022; and Gorai communicated termination on 2 August 2022. SBM invoked arbitration against Gorai on 23 August 2022, leading to constitution of an arbitral tribunal on 14 June 2023. Borivali terminated the Development Agreement on 22 January 2023 and withdrew from Gorai membership on 9 February 2023. Five other constituent societies had been allowed by separate High Court orders to redevelop independently, and one had completed redevelopment and obtained an occupancy certificate. The present Section 9 petition was filed on 30 October 2023. The main legal issues were whether the petitioners were entitled to interim protection under Section 9, whether the dispute was arbitrable given Section 91 of the Maharashtra Co-operative Societies Act, 1960, whether the member society was bound by the federation's decisions, and whether the tripartite Development Agreement remained enforceable after termination of the foundational bipartite agreements and cancellation of the layout plan. The petitioners argued that the limited prayer for non-interference should be granted because SBM did not contest, Gorai itself had terminated the bipartite relationship with SBM, MHADA had cancelled the layout NOC, and several societies had already redeveloped independently. The respondent Gorai contended that disputes between a society and its members were not arbitrable under Section 91 of the Societies Act, that Borivali could not walk away from the federation, that the MHADA cancellation was sub judice in a pending writ petition, and that Borivali should be treated as a veritable party to the existing bipartite arbitration. The Court, observing that its findings were prima facie, held that the bipartite MoU and Confirmation Deed were the foundation of the tripartite Development Agreement, and that foundation had been eroded by termination and MHADA's cancellation of the layout plan. It found no contractual instrument survived to restrain Borivali's independent redevelopment. The Court further noted that five societies had redeveloped independently with judicial approval and one had obtained an occupancy certificate, rendering the original layout plan infeasible. The Court concluded that the petition deserved to be allowed and that Borivali must be protected from any interference, intermeddling or obstruction by Gorai or SBM.

Headnote

A) Arbitration - Interim Measures - Prima Facie Case - Arbitration and Conciliation Act, 1996, Section 9 - In a Section 9 petition, the court examined whether any contractual instrument survived that could restrain the petitioner society's independent redevelopment. The court held that termination of the bipartite MoU and Confirmation Deed, which were the foundation of the tripartite Development Agreement, and MHADA's cancellation of the layout development plan destroyed the contractual basis, making out a prima facie case for interim protection against interference, intermeddling and obstruction (Paras 16-19).

B) Contract Law - Frustration and Impossibility - Termination and Cancellation of Approvals - Arbitration and Conciliation Act, 1996, Section 9 - The court held that where the foundational bipartite agreements are terminated and the statutory No Objection Certificate for layout redevelopment is cancelled, performance under the tripartite Development Agreement becomes impossible, and no contractual provision survives to restrain the petitioner; the respondent federation could not rely on the terminated arrangement to prevent independent redevelopment (Paras 17-19).

C) Cooperative Societies - Federation and Member Society - Independent Redevelopment - Maharashtra Co-operative Societies Act, 1960, Section 91 - The respondent federation contended that disputes with member societies were non-arbitrable and that member societies lost individual identity; the court, without finally deciding arbitrability, noted that five other constituent societies had been permitted to redevelop independently by court orders and one had obtained a full Occupancy Certificate, indicating the original layout plan was no longer feasible and the petitioner could not be compelled to remain within the failed plan (Paras 8, 20).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the petitioners were entitled to interim protection under Section 9 of the Arbitration and Conciliation Act, 1996 against interference by the respondents in their independent redevelopment; whether the dispute between a cooperative housing federation and its member society was arbitrable or ousted by Section 91 of the Maharashtra Co-operative Societies Act, 1960; whether the member society was bound by the federation's decisions and could not seek independent arbitral remedies; whether the tripartite Development Agreement remained enforceable after termination of the foundational bipartite agreements and cancellation of the MHADA layout NOC

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Court held that the petitioners had made out a prima facie case and were entitled to interim protection under Section 9 of the Arbitration and Conciliation Act, 1996. It found that the termination of the MoU and Confirmation Deed and the MHADA cancellation of the layout development plan destroyed the foundation of the tripartite Development Agreement, leaving no surviving contractual instrument to restrain the petitioners' independent redevelopment. The Court concluded that the petition deserved to be allowed and that Borivali must be protected from any interference, intermeddling, or obstruction by Gorai or SBM.

Law Points

  • Section 9 of the Arbitration and Conciliation Act
  • 1996 provides interim measures
  • prima facie findings may support relief where contractual foundation is eroded
  • termination of bipartite MoU and Confirmation Deed destroys basis of tripartite Development Agreement
  • rendering performance impossible
  • MHADA cancellation of layout development NOC leaves no contractual instrument to restrain independent redevelopment
  • Section 91 of the Maharashtra Co-operative Societies Act
  • 1960 raises arbitrability issues between society and member
  • but interim relief can be granted on merits where no surviving contract exists
  • member societies may redevelop independently when federation's plan fails and other societies have done so with judicial approval
Subscribe to unlock Law Points Subscribe Now

Case Details

2025 LawText (BOM) (08) 41

Commercial Arbitration Petition No. 452 of 2024 along with Arbitration Petition No. 562 of 2024

2025-08-01

Somasekhar Sundaresan, J.

2025:BHC-OS:12693

Mr. Aseem Naphade, Omar Khaiyam Shaikh, Sahil Salvi for Petitioners; Mr. Mayur Khandeparkar, Jagdish Aradwad Reddy, Deepti Thorat for Respondent No.1; no appearance for Respondent No.2

Borivali Shree Ganesh Nateshwar Cooperative Housing Society Ltd (in ARBP No. 452 of 2024) and Borivali Madhusudan Cooperative Housing Society Ltd (in ARBP No. 562 of 2024)

The Gorai Road MHB Cooperative Housing Society Association and Anr (Respondent No.2: SBM Realtors Pvt. Ltd.)

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Petitions under Section 9 of Arbitration and Conciliation Act, 1996 seeking interlocutory relief against interference in redevelopment of cooperative housing society buildings.

Remedy Sought

Petitioners (Borivali Shree Ganesh Nateshwar Cooperative Housing Society Ltd and Borivali Madhusudan Cooperative Housing Society Ltd) sought protection against respondents Gorai Road MHB Cooperative Housing Society Association and SBM Realtors Pvt. Ltd. from interfering, intermeddling, or obstructing their independent redevelopment of their respective buildings.

Filing Reason

Borivali terminated the Development Agreement after Gorai terminated the bipartite MoU with SBM and MHADA cancelled the layout development NOC, leaving no valid basis to prevent independent redevelopment; five other constituent societies had been allowed to redevelop independently.

Previous Decisions

Arbitral tribunal constituted on June 14, 2023 between Gorai and SBM in SBM's arbitration invocation of August 23, 2022; MHADA cancellation challenged in Writ Petition (L) No.700 of 2023 pending; five writ petitions by other societies resulted in orders permitting independent redevelopment; one society obtained full Occupancy Certificate.

Issues

Whether petitioners were entitled to interim protection under Section 9 of the Arbitration and Conciliation Act, 1996 against interference by respondents in their independent redevelopment. Whether disputes between a cooperative housing federation and its member society were arbitrable or ousted by Section 91 of the Maharashtra Co-operative Societies Act, 1960. Whether the member society was bound by the federation's decisions and could not seek independent arbitral remedies or Section 9 relief. Whether the tripartite Development Agreement remained enforceable after termination of the foundational bipartite agreements and cancellation of the MHADA layout NOC.

Submissions/Arguments

Petitioner: Limited prayer for non-interference should be granted; SBM not contesting; some constituents of Gorai not part of layout development with SBM; five societies allowed independent redevelopment, one completed with OC; Borivali terminated Development Agreement on January 22, 2023; Gorai itself terminated bipartite relationship with SBM; MHADA cancelled NOC; nothing survives; deserves protection from interference, intermeddling and obstruction. Respondent Gorai: Disputes between society and members not arbitrable; Section 91 of Maharashtra Co-operative Societies Act, 1960 ousts jurisdiction; Margaret Almeida applies; Gorai protected Borivali by terminating SBM; Borivali cannot walk away from federation; MHADA cancellation subject to pending WPL 700; Section 9 petition filed after tribunal constituted; separate arbitration would create chaos; Borivali must be regarded as veritable party and intervene in bipartite arbitration; member has lost individual identity.

Ratio Decidendi

Interim relief under Section 9 of the Arbitration and Conciliation Act, 1996 may be granted on a prima facie basis where the foundational bipartite agreement underpinning a tripartite development arrangement has been terminated and the statutory layout approval has been cancelled, rendering further contractual performance impossible; a member society is not bound by a federation's failed development plan when the federation itself terminated the developer and other member societies have been permitted to redevelop independently.

Judgment Excerpts

All observations made in this judgement are prima facie in nature, bearing in mind the jurisdiction in which these Petitions have been considered. the bipartite MoU and the Confirmation Deed constitute the very foundation of the tripartite Development Agreement and Supplemental DA. The existence of the bipartite relationship is the basis of the tripartite relationship. That very foundation stands totally eroded and undermined by the termination of the MoU and the Confirmation Deed. MHADA has cancelled approvals for the very layout redevelopment by its decision dated March 22, 2024. nothing can be done in furtherance of the layout development as envisaged by Gorai, with or without SBM. Therefore, there is no instrument containing any contractual provision that would survive with any reasonable basis to hold up Borivali’s interests in redevelopment of the Building standing on the Subject Land. If Gorai itself has sought to terminate the relationship with SBM that authored the layout development plan and MHADA has ensured that the very same plan has been cancelled, there is no scope for any performance under the tripartite Development Agreement. five societies have gone on to develop their premises entirely on their own, and one of them has even obtained a final Occupancy Certificate after complete redevelopment.

Procedural History

On 27 October 2007, Gorai and SBM executed a Memorandum of Understanding. On 17 February 2010, a Deed of Confirmation was executed. On 15 April 2011, a tripartite Development Agreement was executed among Borivali, Gorai and SBM. On 9 December 2017, a Supplemental Development Agreement was executed. On 18 February 2022, MHADA issued a show cause notice to SBM; SBM replied on 3 March 2022. On 31 July 2022, Gorai resolved to terminate the relationship with SBM. On 1 August 2022, MHADA cancelled the No Objection Certificate for layout development. On 2 August 2022, Gorai communicated termination of the MoU and Confirmation Deed. On 23 August 2022, SBM invoked arbitration against Gorai under the bipartite agreement. On 22 January 2023, Borivali terminated the Development Agreement. On 9 February 2023, Borivali withdrew from Gorai membership. Orders in five writ petitions permitted other constituent societies to proceed with independent redevelopment. On 14 June 2023, an arbitral tribunal was constituted in the Gorai-SBM arbitration. On 30 October 2023, Borivali filed the present Section 9 Petition. On 22 March 2024, MHADA cancelled the layout approvals. The MHADA cancellation was challenged in Writ Petition (L) No.700 of 2023, which was pending. The matter was heard finally on 18 July 2025 and judgment was delivered on 1 August 2025.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 9
  • Maharashtra Co-operative Societies Act, 1960: Section 91
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Dismisses Appeal by Insurance Company, Holds Mediclaim Amount Not Deductible from Motor Accident Compensation. Contractual Insurance Benefit Is Independent of Statutory Compensation Under Motor Vehicles Act, 1988, and Cannot Be Deducted...
Related Judgement
High Court High Court of Bombay at Goa Considers Whether Supreme Court Observations in Dismissed SLP Set Aside Executing Court's Rejection of Objections Under Section 47 CPC. Petition Challenges Order Dated 24.04.2024 Rejecting Application Under Section 47 Read...