Bombay High Court Partially Sets Aside Arbitral Award in Construction Contract Dispute — Interest Rate Reduced from 18% to 12% per annum. Arbitrator's Award of Interest at 18% Held to be Excessive and Not in Accordance with Contractual Stipulation of 12% under Section 31(7)(a) of the Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: BOMBAY
  • 48
Judgement Image
Font size:
Print

Case Note & Summary

The case involves an arbitration petition filed by the Municipal Corporation of Greater Mumbai (Petitioner) challenging an arbitral award passed by a sole arbitrator in favor of S.N. Thakkar Construction Company Private Limited (Respondent). The dispute arose out of a construction contract for diversion chambers for sewage diversion at seven locations in Mumbai. The contract was awarded in 2002, with work to commence on 01.10.2003 and be completed by 31.05.2004. The Respondent submitted a bar chart and cash flow statement after the due date. During the work, the Petitioner complained of slow progress and breaches. The contract ended by efflux of time on 31.05.2004. The Respondent applied for extension of time and later raised claims for wrongful termination and other losses. The arbitrator awarded various sums to the Respondent, including interest at 18% per annum on the principal amount from the date of the award until payment. The Petitioner challenged the award primarily on the ground that the interest rate was excessive and contrary to the contract, which stipulated interest at 12% per annum for delayed payments. The court analyzed the contractual provisions and found that the contract clearly provided for interest at 12% per annum on delayed payments. The court held that the arbitrator's award of 18% interest was not in accordance with the contract and amounted to a patent illegality under Section 34 of the Arbitration and Conciliation Act, 1996. The court modified the award by reducing the interest rate to 12% per annum from the date of the award until payment, while upholding the rest of the award. The petition was partly allowed.

Headnote

A) Arbitration - Interest Award - Section 31(7)(a) of the Arbitration and Conciliation Act, 1996 - The arbitrator awarded interest at 18% per annum on the principal amount from the date of the award until payment, despite the contract providing for interest at 12% per annum on delayed payments. The court held that the arbitrator's award of interest at a rate higher than the contractual rate was contrary to the terms of the contract and amounted to a patent illegality. The court reduced the interest rate to 12% per annum, as stipulated in the contract, from the date of the award until payment. (Paras 10-14)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitrator was justified in awarding interest at 18% per annum on the awarded amount when the contract stipulated interest at 12% per annum for delayed payments.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court partly allowed the petition and modified the arbitral award by reducing the interest rate from 18% per annum to 12% per annum from the date of the award until payment. The rest of the award was upheld.

Law Points

  • Interest rate under Section 31(7)(a) of the Arbitration and Conciliation Act
  • 1996 must be in accordance with the contract
  • if contract provides for a rate
  • arbitrator cannot award a higher rate without justification
  • 18% interest per annum on delayed payments is penal and not compensatory.
Subscribe to unlock Law Points Subscribe Now

Case Details

2019 LawText (BOM) (03) 66

Arbitration Petition No.1060 of 2010

2019-02-13

S.C. Gupte, J.

Mr. P.G. Lad, a/w. Mr. R.Y. Sirsikar and Mr. D.S. Shingade, for the Petitioner. Mr. Nikhil Wadikar, a/w. Mr. Pradip Zende, i/b. Mr. S.S. Phadke, for the Respondent.

Municipal Corporation of Greater Mumbai

S.N. Thakkar Construction Company Private Limited

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Arbitration petition challenging an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996.

Remedy Sought

Petitioner sought to set aside the arbitral award, particularly the award of interest at 18% per annum.

Filing Reason

The Petitioner challenged the arbitrator's award of interest at 18% per annum as being contrary to the contract which stipulated 12% per annum.

Previous Decisions

The sole arbitrator passed an award in favor of the Respondent, awarding various sums including interest at 18% per annum from the date of the award until payment.

Issues

Whether the arbitrator's award of interest at 18% per annum is contrary to the contract and amounts to a patent illegality.

Submissions/Arguments

Petitioner argued that the contract provided for interest at 12% per annum on delayed payments, and the arbitrator's award of 18% was excessive and not in accordance with the contract. Respondent argued that the arbitrator had discretion to award interest at a reasonable rate, and 18% was not excessive given the commercial nature of the transaction.

Ratio Decidendi

Under Section 31(7)(a) of the Arbitration and Conciliation Act, 1996, the arbitrator must award interest in accordance with the contract. If the contract stipulates a specific rate of interest for delayed payments, the arbitrator cannot award a higher rate without justification. Awarding interest at a rate higher than the contractual rate amounts to a patent illegality and is liable to be set aside under Section 34.

Judgment Excerpts

The arbitrator has awarded interest at 18% per annum on the principal amount from the date of the award until payment. The contract, however, provides for interest at 12% per annum on delayed payments. The award of interest at a rate higher than the contractual rate is contrary to the terms of the contract and amounts to a patent illegality. The interest rate is reduced to 12% per annum from the date of the award until payment.

Procedural History

The dispute was referred to arbitration. The sole arbitrator passed an award in favor of the Respondent. The Petitioner filed Arbitration Petition No.1060 of 2010 under Section 34 of the Arbitration and Conciliation Act, 1996, challenging the award. The petition was heard and decided on 13 February 2019.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 31(7)(a), Section 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Madras High Court Dismisses Writ Petition as Withdrawn in Transport Permit Dispute — Petitioner Granted Liberty to Approach Authorities for Counter Signature Under Interstate Agreement. The court allowed withdrawal with liberty to seek counter sign...
Related Judgement
High Court Bombay High Court Partially Sets Aside Arbitral Award in Construction Contract Dispute — Interest Rate Reduced from 18% to 12% per annum. Arbitrator's Award of Interest at 18% Held to be Excessive and Not in Accordance with Contractual Stipulation ...