Bombay High Court Quashed Termination Notice Due to Unfair and Arbitrary Action
25 Feb 2025Contract Law – Judicial Review – Public Law Element – Principles of Fairness and Reasonableness – Article 14 of the Constitution of India The...
200 result(s) found
Contract Law – Judicial Review – Public Law Element – Principles of Fairness and Reasonableness – Article 14 of the Constitution of India The...
Section 11 Petition Under Arbitration and Conciliation Act, 1996 — Jurisdiction Limited to Examining Existence of Arbitration Agreement — Scope of...
Interpretation of Arbitration Agreement’s Validity Post Expiration of the Principal Contract — Section 37(2)(a) of the Arbitration and Conciliatio...
Court Emphasizes Ethical Standards, Accountability, and the Need for Robust Guidelines to Uphold Integrity in the Legal Profession The court recalle...
Technical Plea on Incorrect Citation of Arbitration and Conciliation Act, 1996 – Rejected – Arbitration Proceedings to Commence Without De...
The Supreme Court dismissed the appeal, upholding the High Court’s finding that the claim of ₹68.15 lakhs was speculative and beyond the contract...
The Supreme Court allowed the appeal, setting aside the High Court’s order and reinstating the arbitral award in its entirety. The Court held that:a...
The Court held that the Learned Sole Arbitrator did not attract any ineligibility conditions under the Seventh Schedule. The Court emphasized that onl...
Contractual Terms and Damages – Clause 49.5 of the General Conditions of Contract (GCC) barred claims for damages due to employer delays. The Arbitr...
Arbitral Award And DRB Findings – Division Bench erred in setting aside a plausible arbitral interpretation – (Para 28) Clause 51.1 Interpretation...