Case Note & Summary
The Petitioner, Ms. Anila Gautam Jain, proprietress of M/s. Badal Agency, was appointed as a dealer by the Respondent, Hindustan Petroleum Corporation Limited (HPCL), under a dealership agreement dated 17th August 2004 for a period of five years from 28th March 2004 to 27th March 2009. The Respondent expressed dissatisfaction with the Petitioner's performance and issued a show cause notice on 23rd January 2008 alleging breaches of clauses 5, 6, 10, 11, 24A, 28A, 28B(g), (h), (i) and (k) of the agreement. After considering the Petitioner's unsatisfactory reply, the Respondent suspended refill supplies on 3rd June 2008, took over possession of the premises, and handed them over to a new dealer. The Petitioner challenged this action by filing a writ petition in the Bombay High Court, which referred the matter to arbitration by order dated 4th September 2008. Subsequently, on 13th September 2008, the Respondent terminated the dealership agreement. The Petitioner claimed that the termination was wrongful and illegal, seeking quashing of the suspension and termination orders, restoration of the dealership and premises, or alternatively, payment of Rs.24,44,076.09 and Rs.12,00,000 for future losses. The Respondent filed a counterclaim for damages. The sole arbitrator rejected the Petitioner's claims and allowed the Respondent's counterclaim, awarding damages and interest. The Petitioner challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996. The court held that the arbitrator's findings on breach were based on evidence and were not patently illegal or perverse. The court noted that the Petitioner had admitted to certain breaches and that the arbitrator's quantification of damages was reasonable. The court also found no error in the award of interest. Consequently, the petition was dismissed.
Headnote
A) Arbitration - Challenge to Arbitral Award - Section 34 of the Arbitration and Conciliation Act, 1996 - Scope of Interference - The court examined whether the arbitral award suffered from patent illegality or perversity. Held that the court cannot re-appreciate evidence or substitute its own view; interference is limited to grounds under Section 34. The arbitrator's findings on breach and damages were plausible and not perverse. (Paras 1, 7-10) B) Contract - Breach of Dealership Agreement - Clauses 5, 6, 10, 11, 24A, 28A, 28B - The arbitrator found that the Petitioner committed breaches of various clauses of the LPG dealership agreement, justifying suspension and termination. The court upheld these findings as based on evidence and not patently illegal. (Paras 2-4, 7-8) C) Damages - Quantification of Loss - Mitigation - The arbitrator awarded damages to the Respondent for losses suffered due to the Petitioner's breaches, including costs of shifting and additional expenses. The court held that the arbitrator's quantification was reasonable and not contrary to law; the Petitioner failed to prove that the Respondent failed to mitigate damages. (Paras 9-10) D) Interest - Award of Interest - Section 31(7) of the Arbitration and Conciliation Act, 1996 - The arbitrator awarded interest at 12% per annum from the date of the award until payment. The court found no error in the award of interest as it was within the arbitrator's discretion. (Para 10)
Issue of Consideration
Whether the arbitral award rejecting the Petitioner's claim and allowing the Respondent's counterclaim suffers from patent illegality or perversity warranting interference under Section 34 of the Arbitration and Conciliation Act, 1996.
Final Decision
The petition is dismissed. The arbitral award is upheld.
Law Points
- Section 34 of the Arbitration and Conciliation Act
- 1996
- scope of interference with arbitral award
- patent illegality
- perversity
- findings of fact not re-appreciable
- damages for breach of contract
- mitigation of damages
- interest pendente lite and future interest



