Supreme Court Allows Homebuyers' Appeal and Waives Time Extension Charges Imposed by Development Authority in Corporate Insolvency Resolution Process. Court Holds That Penalty Charges for Project Delay Cannot Be Treated as CIRP Costs or Recovered from Homebuyers and Successful Resolution Applicant When Default Attributable to Corporate Debtor Under Insolvency and Bankruptcy Code, 2016.

In Favour of Accused
  • 0
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose from two leasehold plots in Noida Sector 100 and Sector 110, where a developer, Granite Gate Properties Private Limited, was to construct residential projects Lotus Boulevard and Lotus Panache. The developer was later admitted into corporate insolvency resolution process and declared a Corporate Debtor. The Committee of Creditors comprised homebuyers as a class of financial creditors. A Resolution Plan submitted by M/s SMV Agencies Private Limited was approved by the CoC and the entity became the Successful Resolution Applicant. During CIRP, homebuyers pooled resources under a 'Pool and Build' mechanism to continue construction, but NOIDA sealed three towers of Lotus Panache on 16.10.2024 over time extension charges. The NCLT disposed of various interim applications including the Resolution Professional's application for approval of the Resolution Plan. On appeal, the NCLAT directed that time extension charges under both lease deeds be treated as CIRP costs for maximum three years provided in the lease deed. The Authorised Representative of homebuyers challenged this direction, while NOIDA appealed seeking inclusion of time extension charges beyond three years up to the tenth year under office order dated 18.10.2019. The Supreme Court considered whether time extension charges are CIRP costs under Section 5(13)(c) of the CIRP Regulations and whether NOIDA could claim extended charges. The AR argued that such charges were penal, not incurred by Resolution Professional, and not for continuation of project; only period after insolvency commencement date 10.01.2019 could be considered. NOIDA argued that without payment the project could not continue and that office order dated 18.10.2019 read with 18.06.2015 permitted charges up to tenth year. The SRA adopted AR's arguments and highlighted that the resolution plan capped contingent protection above Rs.3 crores, recoverable from allottees of towers 17/18/19 as super area charge. The Court examined the lease deed and noted that the land was acquired under Land Acquisition Act, 1894 for urban and industrial township development by NOIDA, whose purpose is welfare and revenue generation, not mere profit. It found that the original lease provided time extension charges at 4%, 5%, and 6% for first, second and third years of delay with cancellation thereafter, and that the new policy introduced by office order 18.10.2019 escalated charges up to tenth year. The Court held that the default was of the corporate debtor, not homebuyers or SRA, and imposing penalty would defeat the essential purpose of development. It therefore ordered NOIDA to waive the penalty charges, set aside the direction to treat time extension charges as CIRP costs, rejected NOIDA's appeal for charges beyond three years, allowed Civil Appeal No.3132 of 2026, and dismissed Civil Appeal No.4207 of 2026.

Headnote

A) Insolvency and Bankruptcy - CIRP Costs - Exclusion of Penalty/Time Extension Charges - Insolvency and Bankruptcy Board of India (Insolvency Resolution Process for Corporate Persons) Regulations, 2016, Section 5(13)(c) - The issue was whether time extension charges claimed by NOIDA for delay in completing leasehold projects should be treated as CIRP costs. The Court held that such charges are penal in nature, arise from the default of the corporate debtor, and do not fall under Section 5(13)(c) as they were not incurred by the Resolution Professional and did not concern continuation of the project. The Court directed waiver of penalty charges and set aside the NCLAT direction to treat them as CIRP costs. Held that penalty charges cannot be imposed on homebuyers and SRA for past sins of the corporate debtor (Paras 7-16).

B) Development Authority Law - Lease and Development Charges - Welfare Objective and Penalty Waiver - UP Industrial Area Development Act, 1976; Land Acquisition Act, 1894 - The Court examined NOIDA's role as a local authority acquiring land for urban and industrial township development with a welfare purpose and revenue generation, not mere profit. It held that imposing default charges on homebuyers and SRA would defeat the essential purpose of development and that NOIDA should waive penalty charges in the peculiar facts of the case. The Court rejected NOIDA's appeal for time extension charges beyond three years up to the tenth year under office order dated 18.10.2019 (Paras 11-16).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether time extension charges under lease deeds are to be treated as CIRP costs, and whether NOIDA is entitled to such charges beyond three years up to the tenth year under office order dated 18.10.2019.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Civil Appeal No.3132 of 2026 allowed; Civil Appeal No.4207 of 2026 dismissed. Directions to consider time extension charges as CIRP costs set aside; NOIDA's appeal for charges beyond three years up to tenth year rejected. Pending applications disposed of.

Law Points

  • Time extension charges under lease deed are penal in nature and not CIRP costs under Section 5(13)(c) of CIRP Regulations
  • penalty for delay caused by corporate debtor cannot be imposed on homebuyers or SRA
  • development authority's welfare purpose overrides penal recovery
  • lease governed by UP Industrial Area Development Act
  • 1976
  • office order dated 18.10.2019 cannot extend charges beyond lease term in peculiar facts
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (SC) (09) 12

Civil Appeal No. 3132 of 2026 with Civil Appeal No. 4207 of 2026

2026-09-03

J.B. Pardiwala, K. Vinod Chandran

2026 INSC 952

Mr. Dhruv Mehta, Mr. Rachit Mittal, Mr. Krishnendu Datta

The Authorised Representative for Granite Gate Properties Private Limited, Ms. Rakesh Verma

M/s New Okhla Industrial Development Authority and Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal against NCLAT order directing time extension charges to be treated as CIRP costs in corporate insolvency resolution of a real estate developer.

Remedy Sought

Authorised Representative of homebuyers sought to set aside direction treating time extension charges as CIRP costs; NOIDA sought inclusion of time extension charges beyond three years up to tenth year as CIRP costs.

Filing Reason

NCLAT directed time extension charges for both lease deeds be treated as CIRP costs for maximum three years provided in lease deed; AR aggrieved by inclusion of penalty charges; NOIDA aggrieved by exclusion of further period under office order dated 18.10.2019.

Previous Decisions

NCLT disposed of various IAs and approved Resolution Plan of M/s SMV Agencies Private Limited as SRA; NCLAT directed time extension charges for maximum three years to be treated as CIRP costs.

Issues

Whether time extension charges under lease deeds are to be treated as CIRP costs under Section 5(13)(c) of the CIRP Regulations. Whether NOIDA is entitled to time extension charges beyond the three-year lease period up to the tenth year as per office order dated 18.10.2019.

Submissions/Arguments

AR contended that time extension charges do not fall under Section 5(13)(c) of the CIRP Regulations as they were not incurred by Resolution Professional and did not concern continuation of project. AR submitted that time extension charges are penal in nature and default was of developer, so homebuyers cannot be mulcted with liability; if at all, only period from insolvency commencement date 10.01.2019 should be included. NOIDA asserted that without payment of time extension charges the project cannot be continued and hence must be CIRP costs; lease governed by UP Industrial Area Development Act, 1976 and office order 18.10.2019 read with 18.06.2015 stipulates escalation beyond three years up to tenth year at specified rates, which must be included. SRA adopted AR's arguments and pointed out resolution plan caps contingent protection at overlap period balance above Rs.3 crores, recoverable from allottees of towers 17/18/19 of Lotus Panache as super area charge.

Ratio Decidendi

Penalty charges for delay in completing leasehold projects cannot be treated as CIRP costs or imposed on homebuyers and SRA when default was by corporate debtor; development authority's welfare purpose overrides penal recovery; time extension charges under lease deed and subsequent office order not CIRP costs and are waived in peculiar facts.

Judgment Excerpts

The default was of the developer and homebuyers cannot be mulcted with that liability. In the peculiar circumstances of this case, we are of the opinion that it is only proper that NOIDA waives the penalty charges since it is neither the default of the homebuyers nor the default of the SRA, which led to the delay. We hence, order that in the peculiar facts and circumstances of the case, the penalty as imposed by the NOIDA on delay, now mulcted on the SRA and the homebuyers, cannot be so validly imposed.

Procedural History

Developer M/s Granite Gate Properties Private Limited obtained perpetual lease of two plots from NOIDA for projects Lotus Boulevard and Lotus Panache in Sectors 100 and 110. Developer declared Corporate Debtor; CoC constituted of homebuyers as Financial Creditors. Resolution Plan approved by CoC with M/s SMV Agencies Private Limited as SRA. Various IAs filed before NCLT, including RP's IA to approve Resolution Plan; NCLT disposed of together with directions. AR and NOIDA filed appeals before NCLAT. NCLAT directed time extension charges for both lease deeds to be treated as CIRP costs for maximum three years provided in lease deed. AR and NOIDA filed appeals before Supreme Court; Supreme Court allowed AR's appeal and dismissed NOIDA's appeal.

Acts & Sections

  • Insolvency and Bankruptcy Board of India (Insolvency Resolution Process for Corporate Persons) Regulations, 2016: Section 5(13)(c)
  • UP Industrial Area Development Act, 1976:
  • Land Acquisition Act, 1894:
  • Insolvency and Bankruptcy Code, 2016:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Acquits Accused in Murder Case Due to Lack of Credible Evidence and Unreliable Witnesses. Conviction under Section 302 IPC set aside as prosecution failed to prove guilt beyond reasonable doubt.
Related Judgement
Supreme Court Supreme Court Validates Sub-Classification of Scheduled Castes in Landmark Judgment. Upholding Equality Within Equality: Supreme Court Endorses State's Power to Sub-Classify Scheduled Castes for Targeted Reservation.