Case Note & Summary
The Supreme Court dealt with a Special Leave Petition arising from an interim order of the High Court of Jharkhand in a Public Interest Litigation concerning alleged unauthorized supply of electricity from a captive power plant. The first petitioner, a steel and power company, had entered into a Captive Power Plant agreement with Jharkhand Bijli Vitran Nigam Ltd. on 17 May 2012, renewed in 2017 and 2023, for supply of surplus power to the second petitioner. The first respondent, Energy Watchdog, a PIL petitioner, complained on 15 April 2024 that the second petitioner was using power without valid captive user status under Rule 3 of the Electricity Rules, 2005 and sought action under Section 135 of the Electricity Act, 2003. The complaint led to a fact-finding inquiry by the State Government and JBVNL on 28 June 2024. Energy Watchdog filed a PIL seeking declaration that the supply was illegal and direction for investigation and recovery of losses. On 26 August 2025, JBVNL issued show cause notices and demand notices for cross subsidy surcharge of Rs.176.74 crores against petitioner no.1 and Rs.108.17 crores against petitioner no.2. Petitioner no.1 filed an interlocutory application objecting to maintainability; the High Court by order dated 5 February 2026 rejected the objection and directed that Energy Watchdog be heard along with the petitioners in the JBVNL proceedings. The petitioners challenged this interim order before the Supreme Court. The petitioners argued that Energy Watchdog was a stranger without legal injury and lacked locus standi; the Electricity Act was an exhaustive code and the High Court could not introduce a tripartite process; and after completion, if aggrieved, respondent no.1 could pursue remedies. They relied on precedents including Ayaaubkhan Noorkhan Pathan, D.N. Jeevaraj and Kunga Nima Lepcha. The respondent contended that petitioners had not paid cross subsidy surcharge, complaints prompted inquiry, and demand was under Jharkhand Open Access Rules, so no interference was needed. The Court noted the constitutional bench ruling in PTC India Ltd. that the Electricity Act is exhaustive code; no unallocated regulatory residue left; Sections 79, 86 and 94 delineate functions of regulatory commissions, including transparency and power to authorize consumer representation. The High Court had to consider this regime at final hearing. On the interim order, the Supreme Court observed that the facts presented by Energy Watchdog gave the High Court an impression that all was not well in the inquiry; despite long-standing complaint action was not taken. The High Court found it compelling to adopt an interim measure to bring full facts to JBVNL through a party other than petitioners. The Supreme Court held that this interim measure was not perverse and did not warrant interference under Article 136. The Court clarified that JBVNL should treat the direction for oral hearing only as a means to collect information, not as a court or tribunal, and should decide independently. It expressed no opinion on merits and left all aspects including scope of third-party intervention to be considered by the High Court at final hearing. The Special Leave Petition was disposed of; pending applications disposed of.
Headnote
A) Electricity Law - Exhaustive Code - Regulatory Framework - Electricity Act, 2003, Sections 79, 86, 94 - The Supreme Court reiterated that the Electricity Act, 2003 is an exhaustive code for all matters concerning electricity and after unbundling and constitution of Central and State Regulatory Commissions, there is no unallocated regulatory residue left outside the regulatory bodies. The High Court was required to consider this regulatory regime, including the functions of the Central Commission under Section 79, the State Commission under Section 86, and the powers of the Appropriate Commission under Section 94, before passing the final order (Paras 9-10). B) Public Interest Litigation - Locus Standi and Third-Party Intervention - Maintainability of PIL and Scope of Intervention - Electricity Act, 2003, Section 94(3); Constitution of India, Article 226 - The High Court rejected the preliminary objection to maintainability of the PIL and directed that respondent no.1 Energy Watchdog be heard along with the petitioners in proceedings pending before JBVNL, despite respondent no.1 not being privy to the CPP Agreement. The Supreme Court held that in the peculiar facts, the High Court's interim measure to bring full facts to JBVNL through a party other than the petitioners could not be termed perverse and warranted no interference under Article 136; JBVNL should treat the oral hearing only as a means to collect information and not as a court or tribunal (Paras 6, 11-13). C) Supreme Court Jurisdiction - Article 136 Interference with Interim Orders - Limited Scope of Interference - Constitution of India, Article 136 - The Special Leave Petition challenged an interim order of the High Court pending disposal of a writ petition under Article 226. The Supreme Court declined to interfere, holding that the interim direction was not perverse and observed that no opinion was expressed on merits; the High Court at final hearing would consider all aspects including scope and ambit of third-party intervention in proceedings under the Electricity Act (Paras 10, 14-15). D) Electricity Law - Functions of Regulatory Commissions - Adjudication and Transparency - Electricity Act, 2003, Sections 79(3), 86(1)(f), 86(3), 94(3) - The judgment noted that Section 86(1)(f) mandates the State Commission to adjudicate disputes between licensees and generating companies and refer disputes to arbitration; Sections 79(3) and 86(3) require transparency; Section 94(3) empowers the Commission to authorize any person to represent consumer interests. Held that these provisions form part of the exhaustive code and must guide the High Court's final determination (Para 9).
Issue of Consideration
Whether the High Court's interim order rejecting the petitioners' objection to maintainability of the Public Interest Litigation and permitting respondent no.1 Energy Watchdog to participate in proceedings initiated by JBVNL was legally valid, and whether the Supreme Court should interfere under Article 136 of the Constitution.
Final Decision
The Supreme Court declined to interfere with the impugned interim order of the High Court dated 05.02.2026 and disposed of the Special Leave Petition. The Court clarified that it had not expressed any opinion on the merits of the matter and directed that at the time of final hearing, the High Court would consider all aspects, including the scope and ambit of third-party intervention in proceedings arising under the Electricity Act, 2003. Pending applications were disposed of.
Law Points
- Electricity Act
- 2003 is an exhaustive code for all matters concerning electricity
- no unallocated regulatory residue remains after unbundling and constitution of regulatory commissions
- State Commission must adjudicate disputes between licensees and generating companies
- Section 94(3) permits Commission to authorize any person to represent consumer interests
- High Court must consider regulatory regime before final order
- interim direction permitting third-party participation as information gathering not court or tribunal is not perverse
- Article 136 interference not warranted.


