Bombay High Court Grants Ex-Parte Decree for Recovery of Excess Payment in Sub-Contract Dispute — Plaintiff Entitled to Recover Rs.12,55,965.21 with Interest at 6% p.a. Plaintiff proved that defendant fabricated bills and was paid in excess of work done, leading to decree under Order 8 Rule 10 CPC.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 2
Judgement Image
Font size:
Print

Case Note & Summary

The plaintiff, M/s. Offshore Industrial Construction Pvt. Ltd., filed a suit for recovery of Rs.12,55,965.21 with interest at 18% p.a. against the defendant, Rosma Engineering Construction. The plaintiff had entered into an agreement with Karnataka Water Supply and Drainage Board for laying a water pipeline from Taranagar to Sandur, and sub-contracted the labour work to the defendant. The defendant submitted seven estimated bills totaling Rs.59,00,650, which the plaintiff certified for Rs.46,64,371. The plaintiff paid Rs.39,86,116 to the defendant. However, the defendant failed to complete the work and left the site, forcing the plaintiff to engage another agency at extra cost. The plaintiff alleged that only Rs.27,30,151 was payable for the work done, and the excess payment of Rs.12,55,965.21 was made due to fabricated bills. The defendant did not appear in the suit, and it was transferred to the undefended list. The plaintiff adduced evidence through its Account Officer, Mr. G.B. Mallikarjunaiah, who deposed in support of the claim and produced six documents. The court found that the plaintiff had proved its case on a preponderance of probabilities and was entitled to recover the excess amount. However, the court reduced the interest rate from 18% to 6% per annum from the date of suit till realization, exercising discretion under Section 34 of the Code of Civil Procedure, 1908. The suit was decreed ex-parte with costs.

Headnote

A) Civil Procedure - Ex-parte Decree - Undefended Suit - Order 8 Rule 10 CPC - Suit transferred to undefended list after defendant failed to appear - Court permitted plaintiff to lead evidence and passed ex-parte decree - Held that plaintiff must prove its case even in ex-parte proceedings (Paras 7-9).

B) Contract Law - Recovery of Excess Payment - Sub-Contract - Plaintiff claimed defendant fabricated bills and was paid in excess - Plaintiff's witness deposed that only Rs.27,30,151/- was payable but Rs.39,86,116/- was paid - Court found plaintiff proved its case on preponderance of probabilities - Held that plaintiff is entitled to recover the excess amount (Paras 8-9).

C) Interest - Discretionary Power - Section 34 CPC - Plaintiff claimed 18% p.a. interest - Court reduced to 6% p.a. from date of suit till realization - Held that interest rate must be reasonable and not usurious (Para 9).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the plaintiff is entitled to a decree for recovery of the alleged excess payment made to the defendant in the absence of the defendant's appearance and evidence.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Suit decreed ex-parte. Defendant ordered to pay plaintiff Rs.12,55,965.21 with interest at 6% p.a. from date of suit till realization, with costs.

Law Points

  • Ex-parte decree
  • recovery of excess payment
  • burden of proof on plaintiff
  • fabrication of bills
  • interest rate discretion
Subscribe to unlock Law Points Subscribe Now

Case Details

2010 LawText (BOM) (01) 259

SUIT NO.1266 OF 2003

2010-01-06

A.S. Oka, J.

Mr. Heeralal Chaturvedi i/by Chaturvedi & Chaturvedi for plaintiff

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil suit for recovery of money

Remedy Sought

Plaintiff seeks decree for recovery of Rs.12,55,965.21 with interest at 18% p.a. from date of suit till realization

Filing Reason

Plaintiff alleges defendant fabricated bills and was paid in excess of work done under a sub-contract

Previous Decisions

Suit transferred to undefended list on 2nd November 2007; on 12th November 2009 shown as undefended suit for ex-parte decree

Issues

Whether the plaintiff is entitled to a decree for recovery of the alleged excess payment made to the defendant in the absence of the defendant's appearance and evidence.

Submissions/Arguments

Plaintiff submitted that defendant fabricated bills and was paid Rs.39,86,116 whereas only Rs.27,30,151 was payable, resulting in excess payment of Rs.12,55,965.21.

Ratio Decidendi

In an undefended suit, the plaintiff must still prove its case on a preponderance of probabilities. Here, the plaintiff's evidence established that the defendant was paid in excess of the work done, and the defendant failed to appear or contest. Therefore, the plaintiff is entitled to recovery of the excess amount with reasonable interest.

Judgment Excerpts

The plaintiffs have filed the present suit for recovery of a sum of Rs.12,55,965=21 Ps. with further interest thereon @ 18% p.a. from the date of institution of the suit till realization. On 2nd November 2007 the suit was ordered to be transferred to the list of 'undefended suits'. The plaintiffs have proved the case on preponderance of probabilities. The plaintiffs are entitled to a decree for recovery of the said amount of Rs.12,55,965=21 Ps. with interest at the rate of 6% p.a. from the date of the suit till realization.

Procedural History

Suit filed in 2003. On 2nd November 2007, suit transferred to undefended list. On 12th November 2009, suit shown as undefended suit for ex-parte decree. Plaintiff permitted to adduce evidence. Judgment reserved on 4th December 2009 and pronounced on 6th January 2010.

Acts & Sections

  • Code of Civil Procedure, 1908 (CPC): Section 34, Order 8 Rule 10
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Appeal Against Refusal to Set Aside Ex-Parte Decree in Suit for Declaration and Injunction — Appellant Failed to Show Sufficient Cause for Non-Appearance Under Order IX Rule 13 CPC.
Related Judgement
High Court Bombay High Court Grants Ex-Parte Decree for Recovery of Excess Payment in Sub-Contract Dispute — Plaintiff Entitled to Recover Rs.12,55,965.21 with Interest at 6% p.a. Plaintiff proved that defendant fabricated bills and was paid in excess of work...