Supreme Court Upholds Karnataka Electricity Regulatory Commission's Order Imposing Liquidated Damages and Tariff Reduction in Solar Power Project Dispute. The court held that the Scheduled Commissioning Date was 16.10.2017, and since injection of power into the grid occurred on 17.10.2017, the projects were delayed, justifying penalties under the Power Purchase Agreement.

  • 6
Judgement Image
Font size:
Print

Case Note & Summary

The appeals arose from a judgment of the Appellate Tribunal for Electricity, which reversed an order by the Karnataka Electricity Regulatory Commission (KERC). The dispute involved Bangalore Electricity Supply Company Limited (BESCOM) as the appellant and E.S. Solar Power Pvt. Ltd. and others as respondents, concerning two solar power projects in Bidar and Bagepalli. The projects were awarded on 31.03.2016, with Power Purchase Agreements (PPAs) entered into on 23.05.2016 and approved by KERC on 17.10.2016. Supplementary PPAs were executed on 17.12.2016. BESCOM reduced the tariff from Rs. 6.10/kWh to Rs. 4.36/kWh and imposed damages of Rs. 20,00,000 for alleged delay in commissioning, claiming the Scheduled Commissioning Date (SCOD) was 16.10.2017, but injection of power into the grid occurred only on 17.10.2017. The respondents filed Original Petitions before KERC, which were dismissed, holding that injection into the grid was essential for commissioning and that the SCOD was 16.10.2017. The Appellate Tribunal allowed the respondents' appeals, setting aside KERC's order. The Supreme Court heard arguments from both sides, with the appellant contending that injection into the grid was a prerequisite and the PPA excluded the General Clauses Act, while the respondents argued that the SCOD should be computed excluding the Effective Date and that commissioning occurred on 16.10.2017. The court analyzed the PPA's terms, particularly Article 1.2(l) and (m), which include both start and end dates in period computations, and Article 1.2.4, which excludes the General Clauses Act. It found that the 12-month period from the Effective Date (17.10.2016) ended on 16.10.2017, making that the SCOD. Since injection into the grid occurred on 17.10.2017, the projects were delayed by one day. The court upheld KERC's decision, reversing the Appellate Tribunal's judgment and justifying the imposition of liquidated damages and tariff reduction.

Headnote

A) Electricity Law - Power Purchase Agreements - Scheduled Commissioning Date Computation - Power Purchase Agreement - The dispute centered on whether the Scheduled Commissioning Date (SCOD) for solar power projects was 16.10.2017 or 17.10.2017, with the court examining the PPA's terms for computing the 12-month period from the Effective Date (17.10.2016). Held that the SCOD was 16.10.2017, and the projects were commissioned on 17.10.2017, resulting in a one-day delay, justifying liquidated damages and tariff reduction. (Paras 13-20)

B) Electricity Law - Commissioning of Solar Power Projects - Injection of Power into Grid - Power Purchase Agreement - The court considered whether injection of power into the state grid is essential for declaring a solar power project commissioned. Held that injection of power into the grid is a prerequisite for commissioning, and since injection occurred only on 17.10.2017, the projects were not commissioned by the SCOD of 16.10.2017. (Paras 13-20)

C) Contract Law - Interpretation of Agreements - Exclusion of General Clauses Act - Power Purchase Agreement - The court addressed the applicability of the General Clauses Act, 1897, to the PPA. Held that Article 1.2.4 of the PPA explicitly excludes the General Clauses Act, and thus, its provisions cannot be invoked for interpreting the agreement's terms. (Paras 13-20)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Solar Power Projects were commissioned within the Scheduled Commissioning Date as per the Power Purchase Agreement, and whether the imposition of liquidated damages and tariff reduction by BESCOM was justified

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court allowed the appeals, set aside the judgment of the Appellate Tribunal for Electricity, and upheld the order of the Karnataka Electricity Regulatory Commission imposing liquidated damages and reducing the tariff.

Law Points

  • Interpretation of Power Purchase Agreements
  • Scheduled Commissioning Date computation
  • Commissioning vs Commercial Operation Date distinction
  • Liquidated damages imposition
  • Exclusion of General Clauses Act applicability
Subscribe to unlock Law Points Subscribe Now

Case Details

2021 LawText (SC) (5) 14

Civil Appeal No. 9273 of 2019, Civil Appeal No. 9274 of 2019

2021-05-03

L. Nageswara Rao, J.

Mr. Tushar Mehta, Mr. Balaji Srinivasan, Mr. Basava Prabhu Patil

Bangalore Electricity Supply Company Limited (BESCOM)

E.S. Solar Power Pvt. Ltd. & Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal against the judgment of the Appellate Tribunal for Electricity reversing the order of the Karnataka Electricity Regulatory Commission

Remedy Sought

Appellant seeks to set aside the Appellate Tribunal's judgment and uphold KERC's order imposing liquidated damages and tariff reduction

Filing Reason

Dispute over the Scheduled Commissioning Date of solar power projects and imposition of penalties for delay

Previous Decisions

KERC dismissed Original Petitions, holding SCOD as 16.10.2017 and projects commissioned on 17.10.2017; Appellate Tribunal allowed appeals, setting aside KERC's order

Issues

Whether the Scheduled Commissioning Date of the Solar Power Projects is 16.10.2017 or 17.10.2017 Whether injection of power into the Grid is essential for declaring a Project commissioned Whether Commissioning of the Project and Commercial Operation of the Project are the same or different concepts

Submissions/Arguments

Appellant argued that injection of power into the Grid is a prerequisite for commissioning and the PPA excludes the General Clauses Act Respondents argued that the SCOD should be computed excluding the Effective Date and that commissioning occurred on 16.10.2017

Ratio Decidendi

The Scheduled Commissioning Date is 16.10.2017 as per the PPA terms, injection of power into the grid is essential for commissioning, and the General Clauses Act is excluded by the PPA, justifying penalties for delay.

Judgment Excerpts

The Appellate Tribunal held that the Commissioning Date of both the Solar Plants according to KPTCL is 16.10.2017 Article 1.2.4 Any word or expression used in this Agreement shall, unless otherwise defined or construed in this Agreement, bear its ordinary English meaning and, for these purposes, the General Clauses Act 1897 shall not apply

Procedural History

KERC dismissed Original Petitions; Appellate Tribunal allowed appeals; Supreme Court heard appeals and reversed Appellate Tribunal's judgment

Acts & Sections

  • General Clauses Act, 1897:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Upholds Karnataka Electricity Regulatory Commission's Order Imposing Liquidated Damages and Tariff Reduction in Solar Power Project Dispute. The court held that the Scheduled Commissioning Date was 16.10.2017, and since injection of pow...
Related Judgement
Supreme Court Supreme Court Quashes Adverse Remarks and Costs Against Tax Officer in UP VAT Act Case Due to Violation of Natural Justice. High Court's Findings on Ex Parte Assessment and Service of Notice Upheld, but Ancillary Strictures and Penalties Set Aside fo...