Case Note & Summary
The appeals arose from a judgment of the Appellate Tribunal for Electricity, which reversed an order by the Karnataka Electricity Regulatory Commission (KERC). The dispute involved Bangalore Electricity Supply Company Limited (BESCOM) as the appellant and E.S. Solar Power Pvt. Ltd. and others as respondents, concerning two solar power projects in Bidar and Bagepalli. The projects were awarded on 31.03.2016, with Power Purchase Agreements (PPAs) entered into on 23.05.2016 and approved by KERC on 17.10.2016. Supplementary PPAs were executed on 17.12.2016. BESCOM reduced the tariff from Rs. 6.10/kWh to Rs. 4.36/kWh and imposed damages of Rs. 20,00,000 for alleged delay in commissioning, claiming the Scheduled Commissioning Date (SCOD) was 16.10.2017, but injection of power into the grid occurred only on 17.10.2017. The respondents filed Original Petitions before KERC, which were dismissed, holding that injection into the grid was essential for commissioning and that the SCOD was 16.10.2017. The Appellate Tribunal allowed the respondents' appeals, setting aside KERC's order. The Supreme Court heard arguments from both sides, with the appellant contending that injection into the grid was a prerequisite and the PPA excluded the General Clauses Act, while the respondents argued that the SCOD should be computed excluding the Effective Date and that commissioning occurred on 16.10.2017. The court analyzed the PPA's terms, particularly Article 1.2(l) and (m), which include both start and end dates in period computations, and Article 1.2.4, which excludes the General Clauses Act. It found that the 12-month period from the Effective Date (17.10.2016) ended on 16.10.2017, making that the SCOD. Since injection into the grid occurred on 17.10.2017, the projects were delayed by one day. The court upheld KERC's decision, reversing the Appellate Tribunal's judgment and justifying the imposition of liquidated damages and tariff reduction.
Headnote
A) Electricity Law - Power Purchase Agreements - Scheduled Commissioning Date Computation - Power Purchase Agreement - The dispute centered on whether the Scheduled Commissioning Date (SCOD) for solar power projects was 16.10.2017 or 17.10.2017, with the court examining the PPA's terms for computing the 12-month period from the Effective Date (17.10.2016). Held that the SCOD was 16.10.2017, and the projects were commissioned on 17.10.2017, resulting in a one-day delay, justifying liquidated damages and tariff reduction. (Paras 13-20) B) Electricity Law - Commissioning of Solar Power Projects - Injection of Power into Grid - Power Purchase Agreement - The court considered whether injection of power into the state grid is essential for declaring a solar power project commissioned. Held that injection of power into the grid is a prerequisite for commissioning, and since injection occurred only on 17.10.2017, the projects were not commissioned by the SCOD of 16.10.2017. (Paras 13-20) C) Contract Law - Interpretation of Agreements - Exclusion of General Clauses Act - Power Purchase Agreement - The court addressed the applicability of the General Clauses Act, 1897, to the PPA. Held that Article 1.2.4 of the PPA explicitly excludes the General Clauses Act, and thus, its provisions cannot be invoked for interpreting the agreement's terms. (Paras 13-20)
Issue of Consideration
Whether the Solar Power Projects were commissioned within the Scheduled Commissioning Date as per the Power Purchase Agreement, and whether the imposition of liquidated damages and tariff reduction by BESCOM was justified
Final Decision
The Supreme Court allowed the appeals, set aside the judgment of the Appellate Tribunal for Electricity, and upheld the order of the Karnataka Electricity Regulatory Commission imposing liquidated damages and reducing the tariff.
Law Points
- Interpretation of Power Purchase Agreements
- Scheduled Commissioning Date computation
- Commissioning vs Commercial Operation Date distinction
- Liquidated damages imposition
- Exclusion of General Clauses Act applicability



