High Court of Judicature at Bombay Quashes Consumer Grievance Redressal Forum Order for Lack of Jurisdiction in Open Access Dispute. Electricity Distribution Company's Writ Petition Challenges CGRF's Retrospective Direction to Reduce Open Access and Enhance Contract Demand, Holding Dispute Falls Under MERC (Distribution Open Access) Regulations, 2016.

High Court: Bombay High Court Bench: BOMBAY
  • 1
Judgement Image
Font size:
Print

Case Note & Summary

By way of a writ petition under Article 226 of the Constitution of India, the Maharashtra State Electricity Distribution Company Limited (MSEDCL) challenged an order dated 29.08.2018 passed by the Consumer Grievance Redressal Forum (CGRF) in favour of M/s. Viraj Profile Ltd., an electricity consumer. The dispute concerned revision of Contract Demand and reduction in Open Access capacity. The respondent, engaged in manufacturing stainless steel with open access capacity 4550 KVA and MSEDCL contract demand 500 KVA, had earlier obtained Medium Term Open Access permission in 2014-15. On 30.12.2014, the respondent applied for MTOA permission for quantum of 4550 KVA and reduction in Contract Demand from 5000 KVA to 500 KVA. The Chief Engineer (Commercial), MSEDCL approved the application on 20.05.2015, sanctioning Open Access of 4500 KVA and retention of Contract Demand of 500 KVA. Subsequently, on 21.09.2016, the respondent applied to the Superintendent Engineer, MSEDCL, Palghar for revision of Contract Demand from 500 KVA to 2000 KVA and reduction of Open Access capacity from 4500 KVA to 3000 KVA, with a copy endorsed to the Chief Engineer (Commercial). The Superintendent Engineer sanctioned the enhancement of contract demand to 2000 KVA and consequent reduction in Open Access on 21.10.2016. Later, on 07.02.2017, the respondent applied to the Chief Engineer (Commercial) for revision in Contract Demand and reduction in Open Access capacity as sanctioned by the Superintendent Engineer. On 11.05.2017, the Chief Engineer (Commercial) allowed revision of Contract Demand from 4000 KVA to 3000 KVA, but made it effective only from May 2017, though the revision was already effected from 21.10.2016. Aggrieved by the prospective effect, the respondent filed a grievance before the Internal Grievance Redressal Cell (IGRC), which was dismissed on 28.06.2018. The respondent then approached the CGRF, which allowed the complaint on 29.08.2018, directing MSEDCL to implement the reduction/revision of open access and enhancement/revision of contract demand retrospectively with effect from the billing month of November 2016 and to refund the excess amount recovered along with interest at the RBI rate. MSEDCL contended that the CGRF lacked jurisdiction over the subject matter because disputes relating to reduction in Open Access capacity exclusively vest in the Maharashtra Electricity Regulatory Commission (MERC) under the MERC (Distribution Open Access) Regulations, 2016, particularly Regulation 32. According to MSEDCL, the Standards of Performance of Distribution Licensees (Period for Giving Supply and Determination of Compensation) Regulations, 2014 only provide timelines for reduction or sanction of load under Regulation 4.14, not substantive adjudication of Open Access quantum disputes. MSEDCL further argued that the nodal agency for seeking reduction in Open Access capacity is the Chief Engineer (Commercial), and the respondent's application to the Superintendent Engineer was contrary to the prescribed procedure under Regulation 8 of the 2016 Regulations. The petitioner also relied on the Supreme Court decision in Maharashtra Electricity Regulatory Commission v. Reliance Energy Ltd. and Ors. to support that all consumer-licensee disputes must go to MERC. The excerpted judgment text sets out these contentions but ends before any final reasoning or operative direction. Therefore, the Court's analysis and final decision cannot be ascertained from the provided material; the case was reserved on 03.01.2023 and pronounced on 28.11.2023.

Headnote

A) Electricity Law - Jurisdiction of Consumer Grievance Redressal Forum - Disputes concerning reduction in Open Access capacity - MERC (Distribution Open Access) Regulations, 2016, Regulation 32 - Petitioner contended that the CGRF lacked jurisdiction because Regulation 32 provides that any dispute under these Regulations shall be adjudicated upon by the Commission, i.e., MERC, and therefore the CGRF order dated 29.08.2018 was without jurisdiction - The dispute pertained to retrospective reduction of Open Access capacity and enhancement of Contract Demand, which falls under the 2016 Regulations and not under the Consumer Grievance Redressal Forum Regulations, 2006 (Paras 6, 7(ii)).

B) Electricity Law - Application to Nodal Agency - Requirement for MTOA applications - MERC (Distribution Open Access) Regulations, 2016, Regulation 8 - Petitioner argued that the nodal agency for seeking reduction in Open Access capacity is the Chief Engineer (Commercial), as notified by MSEDCL, and not the Superintending Engineer (Palghar) to whom the respondent made the application - Regulation 8 requires that an application for Open Access shall be made in the prescribed form to the Nodal Agency, which is the Distribution Licensee specifying the Nodal Officer; the respondent's application to the Superintending Engineer was therefore invalid and outside the prescribed procedure (Paras 6, 6.1(vi), 7(iii)).

C) Electricity Law - Standards of Performance - Applicability to revision of Contract Demand - MERC (Standards of Performance of Distribution Licensees (Period for Giving Supply and Determination of Compensation)) Regulations, 2014, Regulation 4.14 - Petitioner submitted that Regulation 4.14 only prescribes the timeline for reduction or sanction of load and does not govern disputes over Open Access quantum or capacity; the 2016 Distribution Open Access Regulations exclusively apply to such disputes - The CGRF's reliance on the 2014 SoP Regulations was misplaced because the substantive adjudication of Open Access capacity reduction lies with MERC (Paras 6, 7(ii)).

D) Electricity Law - Definition of Grievance under Consumer Grievance Redressal Regulations - Consumer Grievance Redressal Forum's purview - MERC (Consumer Grievance Redressal Forum and Electricity Ombudsman) Regulations, 2006, Regulation 2.1(c) - Petitioner contended that a grievance under Regulation 2.1(c) covers only faults or inadequacies in quality, nature and manner of performance by the Distribution Licensee in pursuance of licence, contract, agreement, Electricity Supply Code, or Standards of Performance, and does not include disputes about Open Access capacity reduction - Since the respondent's complaint did not fit this definition, the IGRC and CGRF proceedings were impermissible in law (Paras 6.1(i), 7(iv)).

E) Electricity Law - Precedent on Regulatory Commission Jurisdiction - All consumer-licensee disputes referred to MERC - Electricity Act, 2003, Section 2(47) - Petitioner relied on the Supreme Court decision in Maharashtra Electricity Regulatory Commission v. Reliance Energy Ltd. and Ors. to argue that all disputes between a consumer and Distribution Licensee must be referred to the Commission, i.e., MERC, which has all powers to determine disputes and ensure compliance with rules and regulations - This was advanced to support the argument that the CGRF's order must be quashed for want of jurisdiction (Paras 7(vi), 7(vii)).

F) Electricity Law - Applicability of Subsequent Amendment - MERC (Distribution Open Access) (First Amendment) Regulations, 2019 - Petitioner submitted that the procedure notified for Distribution of Open Access capacity relied upon by the respondent was issued after the 2019 Amendment, and thus not applicable to the respondent's application made in 2016 - The 2016 Regulations were the applicable legal framework for the application and dispute (Para 7(v)).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Consumer Grievance Redressal Forum had jurisdiction to adjudicate a dispute regarding reduction in Open Access capacity and retrospective revision of Contract Demand, or whether such dispute fell exclusively within the jurisdiction of the Maharashtra Electricity Regulatory Commission under the MERC (Distribution Open Access) Regulations, 2016.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The final decision and operative directions are not included in the provided excerpt; the text ends with petitioner's submissions referencing a prior High Court judgment.

Law Points

  • Disputes relating to reduction in Open Access capacity are within MERC's jurisdiction under MERC (Distribution Open Access) Regulations
  • 2016 Regulation 32
  • Consumer Grievance Redressal Forum lacks jurisdiction over Open Access capacity disputes
  • MTOA applications must be made to Nodal Agency as per Regulation 8
  • Standards of Performance Regulations
  • 2014 only prescribe timelines
  • not substantive adjudication
  • Supreme Court in MERC v. Reliance Energy held all consumer-licensee disputes must go to MERC
Subscribe to unlock Law Points Subscribe Now

Case Details

2023 LawText (BOM) (11) 69

Writ Petition No. 3708 of 2019

2023-11-28

Milind N. Jadhav, J.

2023:BHC-AS:35185

Mr. Kiran Gandhi a/w Mr. Aakash Kothari i/by Little & Co. for Petitioner; Mr. Shardul Singh a/w Kezer Kharawala i/by Lex Juris for Respondent

Maharashtra State Electricity Distribution Company Limited (MSEDCL)

M/s. Viraj Profile Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition under Article 226 of the Constitution of India challenging an order of the Consumer Grievance Redressal Forum passed in a consumer complaint regarding Open Access capacity and Contract Demand revision.

Remedy Sought

Petitioner MSEDCL sought a writ of certiorari to quash the CGRF order dated 29.08.2018, to stay its operation, and alternatively to remand the matter for fresh de novo adjudication.

Filing Reason

Petitioner contended that the CGRF lacked jurisdiction over disputes pertaining to reduction in Open Access capacity, which exclusively vests in the Maharashtra Electricity Regulatory Commission under MERC (Distribution Open Access) Regulations, 2016.

Previous Decisions

Internal Grievance Redressal Cell (IGRC) dismissed the respondent's grievance on 28.06.2018; Consumer Grievance Redressal Forum (CGRF) allowed the complaint on 29.08.2018, directing retrospective implementation and refund.

Issues

Whether the Consumer Grievance Redressal Forum had jurisdiction to adjudicate a dispute regarding reduction in Open Access capacity and retrospective revision of Contract Demand, or whether such dispute fell exclusively within the jurisdiction of the Maharashtra Electricity Regulatory Commission under MERC (Distribution Open Access) Regulations, 2016. Whether the MERC (Standards of Performance of Distribution Licensees) Regulations, 2014 applied to the dispute, or only the MERC (Distribution Open Access) Regulations, 2016 governed the subject matter. Whether the respondent's application to the Superintending Engineer instead of the nodal agency (Chief Engineer Commercial) was valid under Regulation 8 of the MERC (Distribution Open Access) Regulations, 2016.

Submissions/Arguments

Petitioner contended that the CGRF order was without jurisdiction because disputes pertaining to reduction in Open Access capacity lie within the domain of MERC only under Regulation 32 of MERC (Distribution Open Access) Regulations, 2016. Petitioner submitted that matters relating to reduction of Contract Demand in MTOA are governed by Standards of Performance Regulations, 2014 only for deciding timelines, and any other dispute is mandatorily governed by MERC (Distribution Open Access) Regulations, 2016. Petitioner argued that the nodal agency for seeking reduction in Open Access capacity is the Chief Engineer (Commercial), and not the Superintending Engineer (Palghar) to whom the respondent made the application; thus the application was invalid. Petitioner contended that the respondent, being an existing Open Access consumer, was aware of the procedure and should have applied to the Nodal Officer, who is required to verify technical feasibility of the grid. Petitioner relied on the Supreme Court decision in Maharashtra Electricity Regulatory Commission v. Reliance Energy Ltd. and Ors. to argue that all disputes between consumer and distribution licensee must be referred to MERC. Petitioner submitted that the procedure relied upon by the respondent was notified after the MERC (Distribution Open Access) (First Amendment) Regulations, 2019, and therefore not applicable to the respondent's 2016 application.

Judgment Excerpts

dispute pertaining to reduction in Open Access capacity lies within the domain of the Maharashtra Electricity Regulatory Commission (MERC) only. Regulation 32 provide that any dispute under the Regulations shall be adjudicated upon by the Commission the nodal agency for seeking reduction in Open Access capacity is the Chief Engineer (Commercial) and not the Superintending Engineer (Palghar) to whom the Application was made by Respondent

Procedural History

On 30.12.2014, the respondent applied for MTOA permission for quantum of 4550 KVA and reduction in Contract Demand from 5000 KVA to 500 KVA. On 20.05.2015, the Chief Engineer (Commercial) approved and sanctioned Open Access of 4500 KVA and retention of Contract Demand of 500 KVA. On 21.09.2016, the respondent applied to the Superintendent Engineer, MSEDCL, Palghar for revision of Contract Demand from 500 KVA to 2000 KVA and reduction of Open Access from 4500 KVA to 3000 KVA; the application was also endorsed to the Chief Engineer (Commercial). On 21.10.2016, the Superintendent Engineer sanctioned enhancement of contract demand from 500 KVA to 2000 KVA and consequent reduction in Open Access quantum/capacity. On 07.02.2017, the respondent applied to the Chief Engineer (Commercial) for revision in Contract Demand and reduction in Open Access capacity as sanctioned by the Superintendent Engineer. On 11.05.2017, the Chief Engineer (Commercial) allowed revision of Contract Demand from 4000 KVA to 3000 KVA, effective only from May 2017, though revision was already effected from 21.10.2016. The respondent filed a grievance before the IGRC, which was dismissed on 28.06.2018. The respondent then filed a complaint before the CGRF, which was allowed on 29.08.2018, directing petitioner to implement the revision retrospectively from the billing month of November 2016 and to refund excess amount with interest at RBI rate. The petitioner filed the present writ petition challenging the CGRF order.

Acts & Sections

  • Electricity Act, 2003: Section 2(47)
  • MERC (Consumer Grievance Redressal Forum and Electricity Ombudsman) Regulations, 2006: Regulation 2.1(c), Regulation 2.1(g)
  • MERC (Standards of Performance of Distribution Licensees (Period for Giving Supply and Determination of Compensation)) Regulations, 2014: Regulation 4.14, Regulation 4
  • MERC (Distribution Open Access) Regulations, 2016: Regulation 8, Regulation 8.5, Regulation 32, Regulation 38.4
  • MERC (Distribution Open Access) (First Amendment) Regulations, 2019:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Judicature at Bombay, Nagpur Bench Hears Second Appeals Challenging Public Auction Order in Partition Suit. Court Frames Substantial Questions on Validity of Sale Before Final Decree Under Order 21 CPC and Section 2 of Partition Act, 18...
Related Judgement
High Court Bombay High Court Dismisses Petition Challenging AICTE's Refusal to Grant Approval for MBA Course Due to Non-Compliance with Infrastructure Norms. AICTE's decision based on expert committee report and lack of essential facilities was upheld as reason...