Supreme Court Examines Challenge to NGT Orders Imposing Rs 18 Crore Environmental Compensation for Untreated Effluent Discharge. Appeal Challenges NGT Orders for Violation of Natural Justice and Reliance on Joint Committee Reports Under Water Act 1974 and National Green Tribunal Act 2010.

  • 6
Judgement Image
Font size:
Print

Case Note & Summary

These civil appeals, filed under Section 22 of the National Green Tribunal Act, 2010, challenge two orders dated 15.02.2022 and 16.09.2022 passed by the National Green Tribunal, Principal Bench, New Delhi in Original Application No. 71/2021. The appellant, a public limited company incorporated under the Companies Act, 1956, operates a sugar manufacturing unit at village Sheikhpura, Khatauli, Muzaffarnagar, Uttar Pradesh. In March 2021, respondent No.2 filed a complaint before the NGT alleging that the sugar mill was discharging untreated waste into a drain, contaminating groundwater over an area of about one and a half kilometres and depth up to 50 metres. NGT constituted a joint committee of CPCB, UPPCB and the District Magistrate, Muzaffarnagar on 22.03.2021 to inspect and report. After initial delays due to closure of the mill and covid pandemic, the joint committee inspected the unit on 08.12.2021 and submitted a report dated 11.01.2022. NGT found that the appellant had violated environmental norms, including illegal disposal of untreated effluent, dilution at outlet with fresh water to conceal real status, absence of flow meters, absence of records of oil and grease and absence of ETP logbook. NGT directed the joint committee to assess compensation for past violations. The supplementary report dated 10.08.2022 calculated compensation of Rs 34,20,000 for 114 days of violation at Rs 30,000 per day, which worked out to Rs 18 crores at 2 percent of annual turnover of Rs 900 crores. NGT accepted this and directed the appellant to deposit Rs 18 crores with the District Magistrate, Muzaffarnagar within one month for restoration of environment. Aggrieved, the appellant filed appeals. The Supreme Court by order dated 02.11.2022 condoned delay, issued notice, and stayed the compensation orders. In the appeals, the appellant argued that impugned orders were non est due to violation of principles of natural justice, as the appellant was not made party to NGT proceedings and was not heard. Appellant also challenged the scientific methodology and findings of the joint committee and contended that NGT ignored procedures under Sections 21 and 22 of the Water Act, 1974 and Section 19(1) of the NGT Act. Respondents supported the NGT orders, arguing that untreated effluent discharge contaminated groundwater affecting 10-15 thousand people, joint committee reports were scientific and accepted as expert views, and principles of natural justice need not be applied as straitjacket; appellant had copies of reports but did not contest. The Supreme Court then considered relevant statutory provisions, including definitions under the Water Act. The final decision of the Supreme Court is not available in the extracted portion; the available text ends with reference to statutory definitions.

Headnote

A) Environmental Law - Pollution Control - Discharge of Untreated Effluent - Water (Prevention and Control of Pollution) Act, 1974 Sections 21 and 22; National Green Tribunal Act, 2010 Section 22 - NGT found that sugar mill violated environmental norms by illegal disposal of untreated effluent, dilution at outlet, absence of flow meter and records. NGT directed joint committee to assess past violations and later imposed Rs 18 crore compensation at 2% of annual turnover. (Paras 2, 2.1, 4.7, 4.8)

B) Administrative Law - Natural Justice - Audi Alteram Partem - National Green Tribunal Act, 2010 Section 19(1) - Appellant argued NGT passed adverse orders without making appellant a party or granting hearing, violating principles of natural justice and rendering orders non est. NGT had directed copies of reports to appellant but no formal opportunity to contest. (Paras 6-6.4, 7.2)

C) Environmental Law - Expert Committee Reports - Scientific Methodology - Water (Prevention and Control of Pollution) Act, 1974 Sections 21 and 22 - Joint committee inspected on 08.12.2021 and submitted reports; appellant contended reports were scientifically impossible and contradicted by inspection data. Respondents argued expert committee findings were rightly accepted by NGT. (Paras 4.6-4.7, 6.2-6.3, 7.1)

D) Environmental Law - Compensation - Computation Based on Turnover - National Green Tribunal Act, 2010 Section 22; Water Act, 1974 Sections 21, 22 - NGT accepted joint committee supplementary report computing compensation of Rs 18 crores at 2% of annual turnover of Rs 900 crores for 114 days of violation and directed deposit for restoration. Supreme Court's appeal challenged this order on natural justice and scientific grounds. (Paras 2.1, 4.8)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether impugned NGT orders dated 15.02.2022 and 16.09.2022 are vitiated by violation of natural justice; whether joint committee reports are scientifically valid; whether compensation of Rs 18 crores is justifiable; whether procedures under Water Act, 1974 were followed

Subscribe to unlock Issue of Consideration Subscribe Now

Law Points

  • Principles of natural justice
  • audi alteram partem
  • Section 19(1) National Green Tribunal Act 2010
  • Section 22 National Green Tribunal Act 2010
  • Sections 21 and 22 Water Act 1974
  • environmental compensation
  • joint committee inspection
  • NGT powers
Subscribe to unlock Law Points Subscribe Now

Case Details

2025 LawText (SC) (09) 104

Civil Appeal Nos. 8119-8120 of 2022

Ujjal Bhuyan

2025 INSC 1060

M/s. Triveni Engineering and Industries Ltd.

State of Uttar Pradesh & Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeal before Supreme Court under Section 22 of the National Green Tribunal Act, 2010 challenging NGT orders imposing environmental compensation on sugar mill for effluent discharge.

Remedy Sought

Appellant sought setting aside of NGT orders dated 15.02.2022 and 16.09.2022 and quashing of proceedings in O.A. No. 71/2021 for violation of natural justice.

Filing Reason

NGT found appellant violated environmental norms through untreated effluent discharge and imposed Rs 18 crore compensation without making appellant a party or providing hearing.

Previous Decisions

NGT passed order dated 15.02.2022 holding violations and directing supplementary report, and order dated 16.09.2022 imposing compensation of Rs 18 crore. Supreme Court stayed the operation of these orders on 02.11.2022.

Issues

Whether the NGT orders dated 15.02.2022 and 16.09.2022 are vitiated for violation of principles of natural justice as appellant was not a party and not heard. Whether joint committee reports dated 11.01.2022 and 10.08.2022 are scientifically valid and whether NGT rightly relied on them. Whether compensation of Rs 18 crores at 2% of annual turnover is justified under applicable environmental law.

Submissions/Arguments

Appellant: Impugned NGT orders are non est due to violation of audi alteram partem; appellant was not made party to O.A. No. 71/2021 and not given opportunity of hearing. Appellant: Joint committee reports are scientifically impossible, based on erroneous third-party laboratory data, and contradicted by inspection data; NGT ignored Water Act procedures under Sections 21 and 22. Appellant: NGT failed to follow Section 19(1) of NGT Act requiring it to be guided by natural justice. Respondents: Untreated effluent from sugar mill contaminated groundwater affecting 10-15 thousand people; joint committee conducted scientific inspection and was rightly accepted by NGT. Respondents: Principles of natural justice cannot be straitjacketed; NGT directed copies of reports to appellant, but appellant did not contest them before NGT.

Judgment Excerpts

NGT held that the project proponent (appellant herein) had violated the environmental norms which included illegal disposal of untreated effluent, dilution at outlet with fresh water to conceal real status, absence of flow meter at boiler/mill house to avoid monitoring, absence of record of oil and grease stored and absence of Effluent Treatment Plant (ETP) logbook. No opportunity of hearing, not to speak of any fair opportunity of hearing, was afforded to the appellant before rendering the findings vide the impugned orders dated 15.02.2022 and 16.09.2022.

Procedural History

Original Application No. 71/2021 filed before NGT in March 2021; NGT constituted joint committee on 22.03.2021; joint committee could not inspect due to off-season and covid; NGT directed inspection when operational on 21.09.2021; joint committee inspected on 08.12.2021 and submitted report on 11.01.2022; NGT passed first order on 15.02.2022 finding violations and directing supplementary report; joint committee submitted supplementary report on 10.08.2022; NGT passed second order on 16.09.2022 imposing Rs 18 crore compensation; appeals filed; Supreme Court on 02.11.2022 condoned delay, issued notice and stayed the compensation orders.

Acts & Sections

  • Water (Prevention and Control of Pollution) Act, 1974: Section 2(dd), Section 21, Section 22
  • National Green Tribunal Act, 2010: Section 19(1), Section 22
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Examines Challenge to NGT Orders Imposing Rs 18 Crore Environmental Compensation for Untreated Effluent Discharge. Appeal Challenges NGT Orders for Violation of Natural Justice and Reliance on Joint Committee Reports Under Water Act 197...
Related Judgement
High Court Bombay High Court Dismisses State Appeal Against Acquittal for Murder in Dowry Death Case — Dying Declaration Found Unreliable Due to Lack of Corroboration and Inconsistencies.