Bombay High Court Allows MSEDCL's Petitions Challenging CGRF Orders on Recovery of Additional Charges from Consumers. MERC Orders on FAC and AEC Recovery Upheld as Binding on Distribution Licensee.

The Bombay High Court dismissed a group of writ petitions filed by Maharashtra State Electricity Distribution Company Ltd. (MSEDCL) challenging orders...

© Image Copyrights Juris Services & Technology

Supreme Court Allows Appeals by DISCOMs and Generating Companies in Electricity Tariff Dispute — Change in Law Compensation for Coal Shortfall Must Be Computed Based on Actual GCV and SHR as per PPAs.

The judgment involves two civil appeals concerning the determination of compensatory tariff for Change in Law events under long-term Power Purchase Ag...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses Writ of Quo Warranto Against Electricity Ombudsman for Lack of Standing. Petitioner failed to establish that the appointment of respondent no.2 was illegal or that he had a superior right to the post under the Electricity Act, 2003 and MERC Regulations, 2006.

The petitioner, Amol Prabhakar Joshi, a retired Secretary to the Government of Maharashtra, filed a writ petition seeking a writ of quo warranto again...

© Image Copyrights Juris Services & Technology

Supreme Court Dismisses Appeal Against Grant of Transmission Licence Without TBCB in HVDC Project. Section 63 of Electricity Act, 2003 is an alternative route; regulatory commission has discretion to adopt regulated tariff mechanism for transmission projects.

The case involves a challenge by Tata Power Company Limited Transmission (TPC-T) against the grant of a transmission licence by the Maharashtra Electr...

© Image Copyrights Juris Services & Technology

Supreme Court Allows Appeal by MSEDCL in Electricity Tariff Dispute Over Change in Law Due to Wildlife Notification. Held that the notification declaring buffer zone around Tadoba Tiger Reserve constituted a 'Change in Law' under PPAs, entitling APML to compensatory tariff for all four PPAs.

The present appeals arise from a dispute between Maharashtra State Electricity Distribution Company Limited (MSEDCL), the appellant, and Adani Power M...

© Image Copyrights Juris Services & Technology

Bombay High Court Allows MSEDCL Petition Against CGRF Interest Order in Tariff Refund Dispute. Interest on Differential Tariff Amount Not Payable Absent Specific Provision in Regulations or Agreement.

The petitioner, Maharashtra State Electricity Distribution Company Limited (MSEDCL), challenged an order dated 25 January 2018 passed by the Consumer ...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses MCGM's Challenge to MERC Regulation on Compensation for Delayed Electricity Connections. Regulation 4.10 requiring distribution licensees to pay compensation for failure to provide new connections within stipulated period is valid and not ultra vires the Electricity Act, 2003.

The Municipal Corporation of Greater Mumbai (MCGM), through its Brihanmumbai Electric Supply & Transport Undertaking (BES&T), filed a writ petition un...

© Image Copyrights Juris Services & Technology

Bombay High Court Examines Legality of Maharashtra Electricity Regulatory Commission’s Distribution Open Access Regulations. Challenge Concerns Alleged Jurisdictional Overreach Curtailing Consumers’ Right to Access Power Exchange Under the Electricity Act, 2003.

The provided text is an incomplete extract of a judgment from the Bombay High Court in a set of writ petitions (WP Nos. 2694/2014, 2318/2014, 2294/201...