Supreme Court Dismisses Appeal Against Grant of Transmission Licence Without TBCB in HVDC Project. Section 63 of Electricity Act, 2003 is an alternative route; regulatory commission has discretion to adopt regulated tariff mechanism for transmission projects.

  • 3
Judgement Image
Font size:
Print

Case Note & Summary

The case involves a challenge by Tata Power Company Limited Transmission (TPC-T) against the grant of a transmission licence by the Maharashtra Electricity Regulatory Commission (MERC) to Adani Electricity Mumbai Infra Limited (AEMIL) for setting up a 1000 MW HVDC link between Kudus and Aarey in Mumbai. The appellant argued that the licence was granted without following the Tariff Based Competitive Bidding (TBCB) process mandated under Section 63 of the Electricity Act, 2003, and contrary to the National Tariff Policy and a Government Resolution of Maharashtra. The background includes a history of planning for HVDC technology to meet Mumbai's power demand, with earlier involvement of Reliance Infrastructure and later transfer to AEMIL. MERC granted the licence on 21 March 2021, which was upheld by APTEL on 18 February 2022. The Supreme Court framed the legal issues as whether Section 63 is mandatory, the binding nature of the National Tariff Policy, and the value of the Government Resolution. The appellant contended that TBCB is the dominant route and failure to adopt it is against public interest. The respondents argued that Section 63 is an alternative and MERC has discretion. The court analyzed the regulatory framework under the Electricity Act, 2003, and held that Section 63 is not mandatory but an alternative route; the National Tariff Policy is a material consideration but not binding; and the Government Resolution is not binding on MERC. The court emphasized the general regulatory power of the appropriate commission under Sections 61 and 62. It concluded that MERC's decision to grant the licence without TBCB was valid, and dismissed the appeal. The decision upholds the discretion of regulatory commissions in tariff determination and clarifies the interplay between specific provisions and general regulatory powers.

Headnote

A) Electricity Law - Transmission Licence - Grant without TBCB - Section 63 Electricity Act, 2003 - The issue was whether MERC could grant a transmission licence to AEMIL without a TBCB process. The court held that Section 63 is an alternative route and not mandatory; the appropriate commission has discretion to adopt other methods for tariff determination under Sections 61 and 62. (Paras 48-55)

B) Electricity Law - National Tariff Policy - Binding Nature - The court held that the National Tariff Policy is a material consideration but not binding on the regulatory commission; the commission can deviate from it for valid reasons. (Paras 61-71)

C) Electricity Law - Government Resolution - Value - The court held that a Government Resolution of the State Government is not binding on the regulatory commission; it is only a policy directive and cannot override the statutory framework. (Paras 72-88)

D) Electricity Law - Regulatory Power - General vs Specific - Sections 61, 62, 63 Electricity Act, 2003 - The court held that the general regulatory power under Sections 61 and 62 is not ousted by Section 63; the commission can adopt a regulated tariff mechanism if justified. (Paras 56-60)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the grant of a transmission licence by MERC without following the Tariff Based Competitive Bidding (TBCB) process under Section 63 of the Electricity Act, 2003 is valid, and whether the National Tariff Policy and Government Resolution of Maharashtra are binding on the regulatory commission.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court dismissed the appeal, upholding MERC's order granting transmission licence to AEMIL without TBCB process. The court held that Section 63 is not mandatory, and MERC's decision was valid.

Law Points

  • Section 63 of Electricity Act
  • 2003 is an alternative route for tariff determination
  • not mandatory
  • National Tariff Policy is a material consideration but not binding
  • Government Resolution of State Government is not binding on regulatory commission
  • Regulatory commission has general regulatory power under Section 61 and 62 of Electricity Act
  • 2003
  • Tariff Based Competitive Bidding Guidelines are not mandatory for all transmission projects.
Subscribe to unlock Law Points Subscribe Now

Case Details

2022 LawText (SC) (11) 17

Civil Appeal No. 1933 of 2022

2022-02-18

Dr Dhananjaya Y Chandrachud, CJI

The TATA Power Company Limited Transmission

Maharashtra Electricity Regulatory Commission & Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Statutory appeal under Section 125 of the Electricity Act, 2003 against APTEL's judgment dismissing appeal against MERC's order granting transmission licence.

Remedy Sought

Appellant sought setting aside of MERC's order granting transmission licence to AEMIL and direction to follow TBCB process.

Filing Reason

Appellant challenged grant of transmission licence without TBCB process, alleging violation of Section 63 and public interest.

Previous Decisions

MERC granted licence on 21 March 2021; APTEL dismissed appeal on 18 February 2022.

Issues

Whether Section 63 of the Electricity Act, 2003 mandates Tariff Based Competitive Bidding for all transmission projects. Whether the National Tariff Policy is binding on the appropriate commission. Whether a Government Resolution of the State Government is binding on the regulatory commission. Whether MERC's decision to grant licence without TBCB was valid.

Submissions/Arguments

Appellant: Section 63 is the dominant route; TBCB is mandatory; failure to adopt it is contrary to public interest and statutory mandate. Respondents: Section 63 is an alternative route; MERC has discretion to adopt other methods; the decision was based on technical and policy considerations.

Ratio Decidendi

Section 63 of the Electricity Act, 2003 is an alternative route for tariff determination and not mandatory. The appropriate commission has general regulatory power under Sections 61 and 62 to adopt other methods. The National Tariff Policy is a material consideration but not binding. A Government Resolution is not binding on the regulatory commission.

Judgment Excerpts

Section 63 is an alternative route and not mandatory. The National Tariff Policy is a material consideration but not binding. A Government Resolution is not binding on the regulatory commission.

Procedural History

MERC granted transmission licence to AEMIL on 21 March 2021. Appellant appealed to APTEL under Section 111 of the Act. APTEL dismissed appeal on 18 February 2022. Appellant then appealed to Supreme Court under Section 125 of the Act.

Acts & Sections

  • Electricity Act, 2003: 14, 15, 61, 62, 63, 111, 125
  • Maharashtra Electricity Regulatory Commission (Multi Year Tariff) Regulations 2019:
  • Maharashtra Electricity Regulatory Commission (Multi Year Tariff) (First Amendment) Regulations 2022:
  • MERC (State Grid Code) Regulations 2006: 8
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Dismisses Appeal Against Grant of Transmission Licence Without TBCB in HVDC Project. Section 63 of Electricity Act, 2003 is an alternative route; regulatory commission has discretion to adopt regulated tariff mechanism for transmission ...
Related Judgement
High Court High Court of Bombay Set Aside Patent Application Rejection Due to Procedural Lapses and Non-Consideration of Material Evidence. Detailed Scrutiny Ordered for Patent Application with Direction for Reassignment to a Different Officer.