Bombay High Court Partially Allows Contractor's Petition and Dismisses State's Petitions in BOT Contract Dispute — Extension of Concession Period and Damages for Suspension of Toll Collection Upheld. The court upheld the arbitral tribunal's interpretation of the BOT contract regarding extension of concession period and damages, finding no error apparent on the face of the award under Section 30 of the Arbitration Act, 1940.
12 Feb 2015The judgment concerns three arbitration petitions arising from two arbitral awards under the Arbitration Act, 1940, relating to a Build, Operate and T...