Case Note & Summary
The petitioner, Board of Trustees for Jawaharlal Nehru Port, a body corporate under the Major Port Trusts Act, 1963, entered into a licence agreement with the respondent, Gateway Terminals India Pvt. Ltd., on 10 August 2004 for redevelopment of a bulk terminal into a container terminal on a built, operate and transfer (BOT) basis. The project was to be completed within 24 months. The respondent sought extensions of time due to force majeure events like heavy rains, and the petitioner granted extensions totaling 56 days, setting the completion date as 24 October 2006. The respondent completed the project on 30 October 2006, resulting in a delay of six days. The petitioner demanded liquidated damages of Rs. 3 crores at Rs. 50 lakhs per day under clause 7.9 of the licence agreement. The dispute was referred to arbitration, and the arbitral tribunal rejected the claim, holding that the petitioner had not proved any actual loss. The petitioner challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996 before the Bombay High Court. The court considered whether the award was patently illegal or against public policy. The court noted that the arbitrator had considered the evidence and found that the petitioner failed to prove actual loss. The court held that the arbitrator's interpretation of clause 7.9 and Section 74 of the Indian Contract Act, 1872 was plausible and not perverse. The court dismissed the petition, upholding the arbitral award.
Headnote
A) Arbitration Act - Section 34 - Challenge to Arbitral Award - Patent Illegality - The court considered whether the arbitral award rejecting liquidated damages for delay in project completion was patently illegal. The court held that the arbitrator's finding that no actual loss was proved is a plausible view and not perverse, thus no interference under Section 34 (Paras 1-10). B) Contract Act - Section 74 - Liquidated Damages - Proof of Actual Loss - The court examined the requirement of proof of actual loss for claiming liquidated damages. The court held that under Section 74 of the Indian Contract Act, 1872, the claimant must prove actual loss suffered; mere delay does not entitle automatic damages (Paras 5-8). C) Licence Agreement - Clause 7.9 - Liquidated Damages - Interpretation - The court considered the interpretation of clause 7.9 of the licence agreement. The court held that the arbitrator's interpretation that liquidated damages are not payable without proof of actual loss is a possible interpretation and not open to challenge under Section 34 (Paras 6-9).
Issue of Consideration
Whether the arbitral tribunal's rejection of the petitioner's claim for liquidated damages under clause 7.9 of the licence agreement, on the ground that no actual loss was proved, is patently illegal or against public policy warranting interference under Section 34 of the Arbitration and Conciliation Act, 1996.
Final Decision
The Bombay High Court dismissed the arbitration petition, upholding the arbitral award dated 28 June 2012.
Law Points
- Liquidated damages under Section 74 of Indian Contract Act
- 1872 require proof of actual loss
- Section 34 of Arbitration and Conciliation Act
- 1996 limits interference to patent illegality or public policy
- Arbitrator's interpretation of contract clauses is final unless perverse




