Bombay High Court Allows Arbitration Appeal Against Rejection of Section 9 Application for Appointment of Receiver in BOT Road Contract Dispute. The court held that the appellant contractor had a prima facie case and was entitled to appointment of a receiver to collect tolls pending arbitration under Section 9 of the Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: AURANGABAD
  • 76
Judgement Image
Font size:
Print

Case Note & Summary

The appellant, Ashoka Buildcon Ltd., a construction company, entered into a Build-Operate-Transfer (BOT) contract with the State of Maharashtra for improvements to Ahmednagar-Karmala Road. The contract was executed on 19.02.1999, and the appellant was to collect tolls for a concession period. Disputes arose, and the respondent terminated the contract and took over the road. The appellant filed an application under Section 9 of the Arbitration and Conciliation Act, 1996 before the Principal District Judge, Ahmednagar, seeking appointment of a receiver to collect tolls pending arbitration. The District Court rejected the application on 25.7.2013. The appellant appealed to the Bombay High Court. The High Court considered the facts and arguments, noting that the appellant had a prima facie case, balance of convenience in its favor, and would suffer irreparable loss if the receiver was not appointed. The court allowed the appeal, set aside the District Court's order, and appointed a receiver to collect tolls and deposit them in court. The receiver was directed to submit accounts periodically, and the parties were to bear the receiver's fees equally. The court also disposed of the civil application for interim relief.

Headnote

A) Arbitration - Interim Measures - Section 9 of the Arbitration and Conciliation Act, 1996 - Appointment of Receiver - The appellant contractor sought appointment of a receiver to collect tolls from a BOT road project after the respondent State terminated the contract and took over the road. The District Court rejected the application. The High Court held that the appellant had a prima facie case, balance of convenience in its favor, and would suffer irreparable loss if receiver was not appointed. The court allowed the appeal and appointed a receiver to collect tolls and deposit them in court pending arbitration (Paras 1-10).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the District Court erred in rejecting the application under Section 9 of the Arbitration and Conciliation Act, 1996 for appointment of a receiver to collect tolls pending arbitration, and whether the appellant is entitled to interim relief.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The appeal is allowed. The order dated 25.7.2013 passed by the Principal District Judge, Ahmednagar in Arbitration Application No. 1 of 2013 is set aside. The application under Section 9 of the Arbitration and Conciliation Act, 1996 is allowed. A receiver is appointed to collect tolls from the road and deposit them in the District Court. The receiver shall submit accounts every three months. The parties shall bear the receiver's fees equally. Civil Application No. 11305 of 2013 is disposed of.

Law Points

  • Section 9 of the Arbitration and Conciliation Act
  • 1996
  • Appointment of Receiver
  • Interim Measures
  • Prima Facie Case
  • Balance of Convenience
  • Irreparable Loss
Subscribe to unlock Law Points Subscribe Now

Case Details

2013 LawText (BOM) (11) 21

Arbitration Appeal No. 15 of 2013

2013-11-16

S.S. Shinde

Shri R.N. Dhorde, Senior Counsel i/b Smt. S.D. Tambat-Dhumal for appellant; Shri Rajendra S. Deshmukh for respondent

Ashoka Buildcon Ltd.

State of Maharashtra

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Arbitration appeal against rejection of application under Section 9 of the Arbitration and Conciliation Act, 1996 for appointment of receiver.

Remedy Sought

Appointment of receiver to collect tolls from the road project pending arbitration.

Filing Reason

The respondent terminated the BOT contract and took over the road, causing loss to the appellant.

Previous Decisions

The Principal District Judge, Ahmednagar, rejected the application under Section 9 on 25.7.2013.

Issues

Whether the District Court erred in rejecting the Section 9 application for appointment of receiver? Whether the appellant is entitled to interim relief pending arbitration?

Submissions/Arguments

Appellant argued that it had a prima facie case, balance of convenience in its favor, and would suffer irreparable loss if receiver was not appointed. Respondent opposed the application, but the High Court found merit in appellant's contentions.

Ratio Decidendi

In an application under Section 9 of the Arbitration and Conciliation Act, 1996, the court may appoint a receiver if the applicant establishes a prima facie case, balance of convenience in its favor, and likelihood of irreparable loss. The court must protect the subject matter of the arbitration pending final resolution.

Judgment Excerpts

This Arbitration Appeal is arising out of the order, dated 25.7.2013, passed by the learned Principal District Judge, Ahmednagar, in Arbitration Application No. 1 of 2013. The appellant has made out a prima facie case, balance of convenience is in favour of the appellant and if the receiver is not appointed, the appellant would suffer irreparable loss.

Procedural History

The appellant filed Arbitration Application No. 1 of 2013 under Section 9 of the Arbitration and Conciliation Act, 1996 before the Principal District Judge, Ahmednagar, which was rejected on 25.7.2013. The appellant then filed Arbitration Appeal No. 15 of 2013 before the Bombay High Court, along with Civil Application No. 11305 of 2013 for interim relief. The High Court heard the appeal and allowed it on 16.11.2013.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 9
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Winding Up Petition for Time-Barred Debt Under Companies Act, 1956. Claim for Goods Supplied in 2006-2007 Held Barred by Limitation as Petition Filed Beyond Three Years from Last Payment in 2011.
Related Judgement
High Court Bombay High Court Allows Arbitration Appeal Against Rejection of Section 9 Application for Appointment of Receiver in BOT Road Contract Dispute. The court held that the appellant contractor had a prima facie case and was entitled to appointment of a ...