Bombay High Court Adjudicated Arbitration Petition Under Section 34 of the Arbitration and Conciliation Act, 1996 Challenging Arbitral Award in Lease Finance Dispute. The Award Held Lessee Liable for Tax Demands Arising from Disallowance of Depreciation Under Income Tax Act, 1961.

The matter pertains to an arbitration petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 before the High Court of Judicatur...

© Image Copyrights Juris Services & Technology

High Court of Bombay Considers Second Appeals in RERA Delayed Possession Matter. Builder Challenges Appellate Tribunal's Direction to Pay Interest at 10.05% p.a. from February 2014.

These Second Appeals were filed before the High Court of Judicature at Bombay by Runwal Constructions, a registered partnership firm, challenging the ...

© Image Copyrights Juris Services & Technology

High Court of Bombay Dismisses Arbitration Petition in Interest on Security Deposit Dispute. Contractual Bar on Interest and Non-Applicability of Section 31(7)(a) Arbitration Act Renders Claim Unsustainable; Arbitrator’s Finding on Evidence Upheld.

The dispute arose from an agreement dated 30 December 1996 between the petitioner, M/s. Mascon Multiservices & Consultants Pvt. Ltd., and the responde...

© Image Copyrights Juris Services & Technology

Supreme Court Dismisses Appeal by State Undertaking in BOT Arbitration Dispute, Upholds Arbitral Award on Termination Payment. Court Reiterates Limited Scope of Judicial Interference Under Sections 34 and 37 of Arbitration and Conciliation Act, 1996, Emphasizing Finality of Arbitral Awards.

The Supreme Court dismissed the appeal filed by Madhya Pradesh Road Development Corporation Ltd. (MPRDC) against the judgment of the Madhya Pradesh Hi...

© Image Copyrights Juris Services & Technology

Bombay High Court Adjudicates Writ Petition Challenging MMRDA’s Demand for Additional Premium under Lease Deed — Interpretation of Time Extension Clauses and Effect of Interim Court Orders on Construction Deadlines

The Petitioner No.1, a company incorporated under the Companies Act, 1956, successfully bid for a plot in Bandra-Kurla Complex leased by the Mumbai Me...

© Image Copyrights Juris Services & Technology

Supreme Court Allows Appeal in LPG Distributorship Case Due to Delay and Laches — Writ Petition Filed After Four Years Dismissed. Division Bench's Reversal of Single Judge's Dismissal on Locus Standi Set Aside as Writ Petitioner Failed to Explain Inordinate Delay.

The case pertains to a challenge to the grant of LPG distributorship at Jamalpur, District Burdwan, under the GP Category. An advertisement was issued...

© Image Copyrights Juris Services & Technology

Bombay High Court Partially Allows Appeal Against Setting Aside of Arbitral Award in Development Dispute. Court Upholds Damages for Breach but Disallows Compound Interest.

The judgment arises from two arbitration appeals under Section 37 of the Arbitration and Conciliation Act, 1996, challenging a common order dated 25th...