Bombay High Court Dismisses Writ Petition Challenging SRA Termination of Developer in Slum Rehabilitation Scheme. Developer Failed to Complete Project Within Stipulated Time and Did Not Comply with Development Agreement and SRA Conditions.

The Petitioner, Shailesh Mulchand Savla, sole proprietor of M/s. Kunal Builders & Developers, filed a Writ Petition challenging the termination of his...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses Petitioner's Claim for Shortfall Land Due to Delay and Laches. Claim for balance land under Maharashtra Project Affected Persons Rehabilitation Act, 1999 rejected as application made 37 years after acquisition award and 20 years after enactment without explanation.

The petitioner, legal heir of Tatoba Rama Chavan, filed a writ petition under Article 226 of the Constitution of India seeking a direction to the resp...

© Image Copyrights Juris Services & Technology

Bombay High Court Allows Writ Petition for Project Affected Certificate and Compassionate Employment Under Maharashtra Project Affected Persons Rehabilitation Act, 1999. Collector Directed to Issue Certificate and Power Company to Consider Compassionate Appointment.

The petitioner, Hanuman Ramaji Chikankar, filed a writ petition before the Bombay High Court at Nagpur seeking quashing of the order dated 30/07/2020 ...

© Image Copyrights Juris Services & Technology

Bombay High Court Allows Writ Petition for Issuance of Project Affected Person Certificate to Senior Citizen. Petitioner's land acquired for irrigation project in 1970s; court directs respondent to decide representation within 8 weeks.

The petitioner, Subhash S/o Eknath Nafade, a 73-year-old senior citizen, filed a writ petition before the Bombay High Court at Aurangabad seeking a wr...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses Petitioners' Challenge to Land Acquisition for MIHAN Project — Upholds Validity of Notifications Under Land Acquisition Act, 1894. Court holds that substantial compliance with Section 4(1) and Section 6 is sufficient and challenge after award is barred by delay and laches.

The petitioners, Bhawarlal Shankarlal Sarda and Lasmikant Shankarlal Sarda, filed two writ petitions challenging the land acquisition proceedings init...