Bombay High Court Dismisses MCGM's Challenge to MERC Regulation on Compensation for Delayed Electricity Connections. Regulation 4.10 requiring distribution licensees to pay compensation for failure to provide new connections within stipulated period is valid and not ultra vires the Electricity Act, 2003.
2 Mar 2016The Municipal Corporation of Greater Mumbai (MCGM), through its Brihanmumbai Electric Supply & Transport Undertaking (BES&T), filed a writ petition un...