Case Note & Summary
The petitioners, Advani Builders Pvt. Ltd. and its director Chirag P. Jain, filed a writ petition challenging the decision of the Slum Rehabilitation Authority (SRA) to cancel the Letter of Intent (LOI) issued to them for a slum rehabilitation project in Bhim Nagar, Goregaon (East), Mumbai. The SRA had initially issued an LOI to the petitioners on 15th July 2008 for the rehabilitation of slum dwellers. However, the petitioners failed to obtain the consent of the slum dwellers and did not complete the project within the stipulated time. Consequently, the SRA cancelled the LOI on 24th March 2011 and appointed Respondent No.4, Sunshine Housing & Infrastructure Pvt. Ltd., as the new developer. The petitioners challenged this cancellation before the High Power Committee, which upheld the SRA's decision. The petitioners then approached the Bombay High Court. The court examined the provisions of the Maharashtra Slum Areas (I.C. & R.) Act, 1971, and the SRA's regulations. It held that the SRA had the power to cancel the LOI for non-compliance and that the decision was not arbitrary. The court also rejected the petitioners' argument of legitimate expectation, stating that no such expectation arose when the petitioners had failed to perform their obligations. The court further held that the High Power Committee's decision was not vitiated by any error of law or procedure. The petition was dismissed, and the SRA's decision to cancel the LOI and appoint a new developer was upheld.
Headnote
A) Slum Rehabilitation - Cancellation of Letter of Intent - Power of SRA - Maharashtra Slum Areas (I.C. & R.) Act, 1971 - The Slum Rehabilitation Authority has the power to cancel a Letter of Intent issued to a developer if the developer fails to comply with the terms and conditions, including obtaining consent of the slum dwellers and completing the project within the stipulated time. The court held that the SRA's decision to cancel the LOI and appoint a new developer was not arbitrary and was based on the failure of the petitioner to fulfill its obligations. (Paras 10-25) B) Legitimate Expectation - Doctrine - Applicability - The doctrine of legitimate expectation does not apply when there is no clear representation or promise made by the authority. The court held that the petitioner could not claim legitimate expectation to continue with the project when it had failed to perform its part of the contract. (Paras 26-30) C) High Power Committee - Judicial Review - Scope - The decision of the High Power Committee, constituted by the Government of Maharashtra, is subject to judicial review if it is found to be arbitrary or in violation of principles of natural justice. However, in this case, the court found no such violation. (Paras 31-35) D) Writ Petition - Maintainability - Alternative Remedy - A writ petition under Article 226 of the Constitution of India is not maintainable when an alternative efficacious remedy is available. The court observed that the petitioner could have approached the civil court or sought arbitration, but since the matter was heard on merits, the petition was dismissed. (Paras 36-40)
Issue of Consideration
Whether the Slum Rehabilitation Authority (SRA) was justified in cancelling the Letter of Intent (LOI) issued to the petitioner and appointing a new developer for the slum rehabilitation project, and whether the High Power Committee's decision to uphold such cancellation was valid.
Final Decision
The Bombay High Court dismissed the writ petition, upholding the SRA's decision to cancel the Letter of Intent and appoint a new developer. The court held that the SRA acted within its powers and that the petitioners failed to comply with the terms of the LOI.
Law Points
- Slum Rehabilitation Authority has power to cancel Letter of Intent for non-compliance
- Doctrine of legitimate expectation does not apply when there is no representation
- High Power Committee's decision is subject to judicial review
- Writ petition not maintainable when alternative remedy available





