Case Note & Summary
The dispute arose from a civil works contract between the North Eastern Electric Power Corporation Limited (NEEPCO) and Astra Construction Private Limited, concerning the Gas Turbine Power Project in Tripura. The contract, executed on 23.05.1996, had an estimated value of Rs. 17,09,26,913 and stipulated completion by 26.03.1997. Following disputes, the matter was referred to arbitration, where the Arbitral Tribunal awarded Rs. 3.30 crores to the respondent along with pre-reference interest at 12% per annum. The appellant challenged this award in the Commercial Court, which modified the award by disallowing pre-reference interest based on Clause 54 of the General Conditions of Contract (GCC). The respondent appealed under Section 37 of the Arbitration and Conciliation Act, 1996, leading to the High Court restoring the Arbitral Tribunal's award. The Supreme Court examined the interpretation of Clause 54, which barred claims for interest or damages related to delayed payments and disputes. The Court distinguished this clause from similar clauses in previous judgments, concluding that it explicitly prohibited interest claims for delayed payments, thus affirming the Commercial Court's decision. The appeal was allowed, and the High Court's judgment was set aside, with no order as to costs. (Paras 1-24).
Headnote
A) Arbitration Law - Grant of Interest - Clause 54 of General Conditions of Contract - Clause 54 bars claims for interest for pre-reference period - The Supreme Court held that the wording of Clause 54 explicitly prohibits interest claims arising from delayed payments, distinguishing it from similar clauses in prior case law. The High Court's interpretation equating it with Harish Chandra was erroneous, leading to the restoration of the Arbitral Tribunal's award being set aside. (Paras 23-24).
Issue of Consideration
Whether Clause 54 of the General Conditions of Contract bars the grant of pre-reference interest.
Final Decision
The Supreme Court allowed the appeal, set aside the High Court's judgment restoring the grant of pre-reference interest, and upheld the Commercial Court's decision that Clause 54 of the GCC bars such interest.
Law Points
- Arbitration
- Interest
- Public Works Contracts
- Clause Interpretation
- Jurisdiction of Arbitral Tribunal


