Supreme Court Sets Aside Grant of Pre-Reference Interest in Arbitration Case Due to Clause Interpretation. Clause 54 of General Conditions of Contract Explicitly Bars Interest Claims for Delayed Payments.

In Favour of Accused
  • 0
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose from a civil works contract between the North Eastern Electric Power Corporation Limited (NEEPCO) and Astra Construction Private Limited, concerning the Gas Turbine Power Project in Tripura. The contract, executed on 23.05.1996, had an estimated value of Rs. 17,09,26,913 and stipulated completion by 26.03.1997. Following disputes, the matter was referred to arbitration, where the Arbitral Tribunal awarded Rs. 3.30 crores to the respondent along with pre-reference interest at 12% per annum. The appellant challenged this award in the Commercial Court, which modified the award by disallowing pre-reference interest based on Clause 54 of the General Conditions of Contract (GCC). The respondent appealed under Section 37 of the Arbitration and Conciliation Act, 1996, leading to the High Court restoring the Arbitral Tribunal's award. The Supreme Court examined the interpretation of Clause 54, which barred claims for interest or damages related to delayed payments and disputes. The Court distinguished this clause from similar clauses in previous judgments, concluding that it explicitly prohibited interest claims for delayed payments, thus affirming the Commercial Court's decision. The appeal was allowed, and the High Court's judgment was set aside, with no order as to costs. (Paras 1-24).

Headnote

A) Arbitration Law - Grant of Interest - Clause 54 of General Conditions of Contract - Clause 54 bars claims for interest for pre-reference period - The Supreme Court held that the wording of Clause 54 explicitly prohibits interest claims arising from delayed payments, distinguishing it from similar clauses in prior case law. The High Court's interpretation equating it with Harish Chandra was erroneous, leading to the restoration of the Arbitral Tribunal's award being set aside. (Paras 23-24).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether Clause 54 of the General Conditions of Contract bars the grant of pre-reference interest.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court allowed the appeal, set aside the High Court's judgment restoring the grant of pre-reference interest, and upheld the Commercial Court's decision that Clause 54 of the GCC bars such interest.

Law Points

  • Arbitration
  • Interest
  • Public Works Contracts
  • Clause Interpretation
  • Jurisdiction of Arbitral Tribunal
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (SC) (09) 79

Civil Appeal No. of 2026 (@ Special Leave Petition (Civil) No. 24803 of 2025)

2026-09-22

Alok Aradhe, Pamidighantam Sri Narasimha

Tushar Mehta, Raghavendra P. Shankar, Ritin Rai, C.S. Vaidyanathan

North Eastern Electric Power Corporation Limited

Astra Construction Private Limited

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Dispute arising from a public works contract regarding interest claims.

Remedy Sought

Restoration of the Arbitral Tribunal's award including pre-reference interest.

Filing Reason

Disputes over the execution of the contract and interest claims.

Previous Decisions

Commercial Court modified the Arbitral Tribunal's award, disallowing pre-reference interest.

Issues

Interpretation of Clause 54 of the General Conditions of Contract regarding interest claims. Whether the High Court erred in restoring the Arbitral Tribunal's award.

Submissions/Arguments

Appellant argued that Clause 54 bars interest claims and that the High Court erred in its interpretation. Respondent contended that the appellant waived its right to invoke Clause 54 by not raising it before the Arbitral Tribunal.

Ratio Decidendi

Clause 54 of the General Conditions of Contract explicitly bars claims for interest arising from delayed payments, distinguishing it from similar clauses in prior case law.

Judgment Excerpts

The controversy... bears materially upon public works contracts generally. The issue is no longer res integra, clauses of materially similar tenor having received the considered attention of this Court. Clause 54 of the GCC bars the grant of interest for the pre-reference period. The High Court erred in equating Clause 54 with the clause considered in Harish Chandra (supra).

Procedural History

The matter was referred to arbitration, the Arbitral Tribunal awarded interest, the Commercial Court modified the award disallowing interest, and the High Court restored the award leading to the appeal.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 31(7), Section 37
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Delivers Judgment on Writ Petitions Challenging CIDCO's Refusal to Regularize Building Irregularities under MRTP Act. The Court examined the validity of orders passed under Sections 45 and 53 of the Maharashtra Regional and Town Pla...
Related Judgement
High Court High Court of Bombay at Goa Allows Writ Petition Challenging Administrative Tribunal Order in Mundkar Dispute — Tribunal Exceeded Revisionary Jurisdiction Under Section 26 of Goa, Daman and Diu Mundkars (Protection from Eviction) Act, 1975. Concurr...