Rajasthan High Court Reviews Commercial Court's Dismissal of Section 34 Application; Arbitral Award Upheld in Favour of Contractor for Work Order Withdrawal. Court Examines Whether Arbitral Tribunal's Failure to Frame Issues and Record Evidence Renders Award Contrary to Public Policy Under Section 34(2)(b)(ii) of Arbitration and Conciliation Act, 1996.

High Court: Rajasthan High Court Bench: Jodhpur
  • 0
Judgement Image
Font size:
Print

Case Note & Summary

The High Court of Judicature for Rajasthan at Jodhpur heard a civil miscellaneous appeal under the Arbitration and Conciliation Act, 1996 arising from a contractual dispute between the Public Work Department and a contractor. The appellant, Executive Engineer, Public Work Department, Kuchaman City, challenged the judgment dated 3.6.2023 of the Commercial Court, Ajmer, which had dismissed the appellant's application under Section 34 of the Arbitration and Conciliation Act, 1996 and upheld the arbitral award dated 11.3.2016 in favour of the respondent contractor. The work order was issued on 15 May 2013 for Rs. 6,35,43,815, but progress was halted due to resistance from local villagers, leading to withdrawal of the work order. The respondent filed claims before the Arbitral Tribunal for idling of men, machinery, and other heads, including a claim of Rs. 12,49,665 for idling of labour and staff from 03.06.13 to 10.10.13 and Rs. 19,56,000 for idle machinery. The appellant filed a written reply denying the claims and contending that no permanent or temporary labour was engaged. The Arbitral Tribunal passed an award in favour of the respondent without framing contested questions of fact or recording evidence. The appellant challenged the award under Section 34 before the Commercial Court, which dismissed the application. On appeal, the appellant argued that the award was against public policy because the Arbitral Tribunal failed to frame issues and examine oral and documentary evidence. The respondent defended the award, stating that the appellant admitted work could not commence due to villagers' resistance and that the appeal lacked merit. The court noted the undisputed fact that the Arbitral Tribunal decided the case without framing issues or recording evidence and without seeking admission or denial of documents. The court examined Section 34(2)(b)(ii) and Explanations 1 and 2, emphasizing that public policy covers contravention of the fundamental policy of Indian law and basic notions of morality or justice, but does not entail merits review. The court referred to ONGC Ltd. v. Saw Pipes Ltd. for the wider meaning of public policy and to Bharat Coking Coal Ltd. v. L.K. Ahuja for the requirement of adequate evidence for loss of profit claims. The provided text of the judgment ends during the court's analysis and does not contain the final operative order or directions. Therefore, the final decision and relief granted are not mentioned in the available text.

Headnote

A) Arbitration - Setting aside arbitral award - Public policy ground - Arbitration and Conciliation Act, 1996, Section 34(2)(b)(ii) - The court examined whether the award was in conflict with public policy; Explanation 1 restricts public policy to fraud, corruption, violation of Sections 75/81, contravention of fundamental policy of Indian law, or conflict with basic notions of morality or justice; Explanation 2 clarifies that no merits review is permitted - The appellant argued that the award was against public policy because the Arbitral Tribunal failed to frame issues despite serious and complex allegations; the court observed that the award must be tested against the statutory public policy standards - Held that an award patently in violation of statutory provisions cannot be in public interest (Paras 10-12).

B) Arbitration - Procedural fairness - Framing of issues and recording of evidence - Arbitration and Conciliation Act, 1996, Section 34 - It was undisputed that the Arbitral Tribunal decided the case in favour of the respondent without framing any contested questions of fact or recording any evidence; the tribunal also did not seek admission or denial of the claimant's documents - The court noted that these deficiencies were relevant to determining whether the award conflicted with the fundamental policy of Indian law and natural justice - Held that failure to frame issues and record evidence may render the award contrary to public policy (Paras 3, 9).

C) Arbitration - Claims for idling charges and loss of profit - Proof and evidence - Arbitration and Conciliation Act, 1996, Section 31(7); Interest Act, Section 34 - The claimant sought idling charges for labour and machinery and interest; the appellant denied engaging permanent or temporary labour at site and contested the claims - The court referred to Bharat Coking Coal Ltd. v. L.K. Ahuja, which requires adequate evidence for loss of profit claims - Held that a claim for loss of profit must be supported by adequate evidence and cannot be allowed unless the plea and proof of alternative use of funds are established (Paras 7-8, 13).

D) Arbitration - Judicial review under Section 34 - Scope of interference - Arbitration and Conciliation Act, 1996, Section 34(2)(b) - The court emphasized that Section 34(2)(b) contains two sub-clauses: subject matter not capable of arbitration and conflict with public policy; Explanation 2 prohibits merits review - The court relied on ONGC Ltd. v. Saw Pipes Ltd. for wider meaning of public policy - Held that an award which is patently in violation of statutory provisions cannot be said to be in public interest and may be set aside (Paras 10-12).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Commercial Court erred in dismissing the appellant's application under Section 34 of the Arbitration and Conciliation Act, 1996, and whether the arbitral award dated 11.3.2016 is liable to be set aside as being in conflict with public policy of India due to the Arbitral Tribunal's failure to frame issues and record evidence.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Not mentioned in the provided text; the judgment ends during the court's analysis before any final operative order or direction is stated

Law Points

  • Arbitral award may be set aside under Section 34(2)(b)(ii) if in conflict with public policy
  • Explanation 1 narrows public policy to fraud
  • corruption
  • violation of Sections 75/81
  • contravention of fundamental policy of Indian law
  • or conflict with basic notions of morality or justice
  • Explanation 2 excludes merits review
  • Arbitral Tribunal must frame contested questions of fact and record oral and documentary evidence
  • failure to frame issues and record evidence may amount to violation of fundamental policy and natural justice
  • claim for loss of profit must be supported by adequate evidence
  • public policy of India given wider meaning to include matters of public good and public interest.
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (RAJ) (08) 2

D.B. Civil Miscellaneous Appeal No. 1905/2023

2026-08-25

Dr. Justice Pushpendra Singh Bhati, Mr. Justice Praveer Bhatnagar

Mr. Ayush Gehlot, Mr. Kuldeep Kumar Shah

The Executive Engineer, Public Work Department, Kuchaman City, Parbatsar, Dist. Nagaur, Rajasthan

M/s Trimurti Construction, Through Partner Pankaj Gupta S/o Shri Dharmendra Gupta, 12/163 Gurudayal Marg, Hathibhata, Ajmer; R P Modirataa, Sole Arbitrator, Retired Commandant, Brtf, C/o Shri Arun Mathur, R/o 468 Krishna Niwas, 7Th B Road, Sardarpura, Jodhpur

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil miscellaneous appeal under Arbitration and Conciliation Act, 1996 against dismissal of Section 34 application by Commercial Court

Remedy Sought

Appellant sought setting aside of the arbitral award dated 11.3.2016 and overturning of the Commercial Court's judgment dated 3.6.2023 dismissing the Section 34 application

Filing Reason

Appellant alleged that the arbitral award was against public policy because the Arbitral Tribunal failed to frame issues and record evidence despite serious and complex allegations

Previous Decisions

Arbitral Tribunal passed award dated 11.3.2016 in favour of respondent; Commercial Court Ajmer dismissed appellant's Section 34 application on 3.6.2023

Issues

Whether the arbitral award is liable to be set aside under Section 34(2)(b)(ii) of Arbitration and Conciliation Act, 1996 as being in conflict with public policy of India due to non-framing of issues and absence of evidence Whether the claims for idling charges, idle machinery, and loss of profit were proved before the Arbitral Tribunal without proper evidence and admission/denial of documents

Submissions/Arguments

Appellant argued that the arbitral award was against public policy and the Arbitral Tribunal failed to frame issues despite serious and complex allegations, requiring examination of oral testimony and documentary evidence Respondent argued that the appellant admitted in written statement that work could not commence due to persistent resistance from local villagers and that respondent's materials were stolen leading to an FIR Respondent contended that the Tribunal delivered a detailed, well-reasoned order after fair hearing and that the appeal lacked merit Respondent cited multiple Supreme Court and High Court judgments supporting non-interference with arbitral awards

Ratio Decidendi

An arbitral award may be set aside under Section 34(2)(b)(ii) of the Arbitration and Conciliation Act, 1996 only if it conflicts with public policy as defined in Explanations 1 and 2, including contravention of the fundamental policy of Indian law or basic notions of morality or justice; an Arbitral Tribunal must frame contested questions of fact and record oral and documentary evidence, and failure to do so may amount to violation of natural justice and public policy; claims for loss of profit must be supported by adequate evidence and specific pleading of alternative use of funds.

Judgment Excerpts

It is also undisputed that the Arbitral Tribunal decided the case in favour of the respondent without framing any contested questions of fact or recording any evidence regarding the parties' disagreements. the phrase 'public policy of India' used in Section 34 in context is required to be given a wider meaning. It can be stated that the concept of public policy connotes some matter which concerns public good and the public interest. the award which is, on the face of it, patently in violation of statutory provisions cannot be said to be in public interest. It is not unusual for the contractors to claim loss of profit arising out of diminution in turnover on account of delay in the matter of completion of the work. What he should establish in such a situation is that had he received the amount due under the contract, he could have utilised the same for some other business in which he could have earned profit.

Procedural History

Work order dated 15 May 2013 issued for Rs. 6,35,43,815; work halted due to villagers' resistance and withdrawn; respondent filed claims before Arbitral Tribunal; Arbitral Tribunal passed award dated 11.3.2016 in favour of respondent; appellant filed Section 34 application before Commercial Court Ajmer (Civil Misc Case No. 45/19); Commercial Court dismissed application on 3.6.2023; appellant filed present D.B. Civil Miscellaneous Appeal No. 1905/2023; arguments concluded on 20.08.2026; judgment pronounced on 25.08.2026

Acts & Sections

  • Arbitration and Conciliation Act, 1996: 34, 34(2)(b), 34(2)(b)(i), 34(2)(b)(ii), 31(7), 75, 81
  • Interest Act: 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Grants Interim Injunction Restraining BCCI from Terminating IPL Franchise Agreement with Deccan Chronicle Holdings Limited. Court Holds Termination Notice Invalid for Not Providing 30-Day Cure Period Under Clause 11.1 of Franchise A...
Related Judgement
High Court Bombay High Court Dismisses Appeal Against Section 9 Interim Relief Order in Arbitration Dispute Over Media Rights. Court Upholds Security Deposit of Rs. 390 Crores Directed by Single Judge to Protect BCCI's Claim Pending Arbitration.