Case Note & Summary
The petitioner, Deccan Chronicle Holdings Limited (DCHL), filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking to restrain the respondent, Board of Control for Cricket in India (BCCI), from terminating the Franchise Agreement dated 10th April 2008, which granted DCHL the Hyderabad franchise for the Indian Premier League (IPL). The dispute arose when BCCI issued a notice on 14th September 2012 alleging that DCHL had committed a material breach by failing to pay the franchise fee and other amounts, and purporting to terminate the agreement. DCHL contended that the notice did not comply with Clause 11.1 of the Franchise Agreement, which required a 30-day period to remedy the breach before termination. The court examined the terms of the agreement and found that the notice was defective as it did not give the requisite 30 days' time to cure the breach. The court held that DCHL had made out a prima facie case for interim relief, and the balance of convenience was in favor of granting an injunction to maintain the status quo pending arbitration. The court restrained BCCI from terminating the Franchise Agreement until the disposal of the arbitration proceedings, subject to DCHL depositing a sum of Rs. 10 crores within four weeks. The court also directed that the arbitration be concluded within six months.
Headnote
A) Arbitration - Interim Relief - Section 9 of the Arbitration and Conciliation Act, 1996 - Prima Facie Case - The court examined whether the petitioner made out a prima facie case for grant of interim injunction restraining termination of the Franchise Agreement. The court held that the petitioner had a strong prima facie case as the respondent's termination notice did not comply with the contractual requirement of providing 30 days' notice to remedy the breach. (Paras 1-10) B) Contract Law - Termination of Contract - Material Breach - Clause 11.1 of Franchise Agreement - The court interpreted Clause 11.1 which requires a notice specifying the breach and giving 30 days to remedy it. The court found that the respondent's notice dated 14th September 2012 did not give 30 days' time and was therefore invalid. (Paras 5-8) C) Arbitration - Interim Measures - Balance of Convenience and Irreparable Injury - Section 9 of the Arbitration and Conciliation Act, 1996 - The court held that the balance of convenience was in favor of the petitioner as termination would cause irreparable harm to the petitioner's business and the franchise, whereas the respondent could be compensated by money damages. (Paras 9-10)
Issue of Consideration
Whether the petitioner is entitled to interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, restraining the respondent from terminating the Franchise Agreement pending arbitration, and whether the respondent's notice of termination was valid and complied with the contractual requirements.
Final Decision
The court allowed the petition and restrained the respondent from terminating the Franchise Agreement until the disposal of the arbitration proceedings, subject to the petitioner depositing a sum of Rs. 10 crores within four weeks. The court also directed that the arbitration be concluded within six months.
Law Points
- Section 9 of the Arbitration and Conciliation Act
- 1996
- interim measures
- prima facie case
- balance of convenience
- irreparable injury
- termination of contract
- material breach
- notice period
- remedy of breach





