Supreme Court Heard Civil Appeal Concerning Zero Period Policy Benefit; Entitlement Turned on Non-Availability of 45-Metre Front Road and NGT Stay Orders Under UP Statutes. The case involved NOIDA's rejection of zero period benefit despite Tehsildar report confirming encroached and unacquired access road, and UPRERA's finding that the 45-metre road remained unconstructed.

  • 0
Judgement Image
Font size:
Print

Case Note & Summary

These civil appeals arose from the final judgment and order dated 19.07.2024 passed by the Allahabad High Court in Writ-C Nos. 9348 and 21276 of 2023, and 7223 of 2024. The dispute concerned the entitlement of a commercial plot developer to the benefit of NOIDA's Zero Period Policy, which provides for rescheduling of instalments and waiver of penal interest when construction is stalled due to specified reasons including encroachment, lack of access roads, and court stay orders. NOIDA, the appellant authority, had allotted Plot No. 5-A, Sector 94, Noida to the respondent developer under a lease deed dated 11.01.2012 for development of a commercial complex. The developer could not proceed with full construction initially because of an interim order of the National Green Tribunal restraining construction within 10 km of the Okhla Bird Sanctuary; the restraint operated from 17.09.2013 to 19.08.2015. After the restraint was lifted, the developer alleged that the 45-metre front road remained encroached and unacquired, and the 24-metre side road was unpaved and non-motorable. The developer made representations and, on 15.10.2016, first claimed Zero Period Policy benefit on grounds of the NGT restraint and lack of access roads. NOIDA granted benefit for the NGT period from 14.08.2013 to 28.10.2013 and penal interest exemption from 29.10.2013 to 19.08.2015, but referred the access road issue to the Tehsildar for verification. The Tehsildar's report dated 14.02.2019 recorded that the 45-metre road land was 'Abadi' land, never acquired, and encroached, and that the access road was blocked. Despite this, NOIDA's committee rejected the access-road claim and the CEO passed an order dated 14.02.2020 rejecting the benefit, holding that alternative access existed via the 24-metre road and partly the 45-metre road. The developer filed a revision before the State Government under Section 41(3) of the Uttar Pradesh Urban Planning and Development Act, 1973 read with Section 12 of the Uttar Pradesh Industrial Area Development Act, 1976. The developer also filed a complaint before UPRERA seeking possession free from encumbrances, compensation, and construction of roads. During UPRERA proceedings, NOIDA completed the 24-metre side road on 18.02.2020. UPRERA by order dated 22.10.2020 rejected the complaint as not maintainable and directed the developer to pursue statutory remedies under the 1973 and 1976 Acts, but noted from its technical inspection report that the 45-metre road had not been constructed and existing habitation remained. The Allahabad High Court's judgment in the writ petitions is impugned in these civil appeals. The provided text does not include the Supreme Court's final reasoning, findings or operative directions.

Headnote

A) Urban Planning - Zero Period Policy - Policy Conditions for Benefit - NOIDA Zero Period Policy provides for rescheduling of instalments and waiver of penal interest where construction is stalled due to lack of access road, encroachment, or court stay - Uttar Pradesh Urban Planning and Development Act, 1973 and Uttar Pradesh Industrial Area Development Act, 1976 - The Developer sought benefit for NGT restraint period and lack of 45m/24m roads; NOIDA granted partial benefit for NGT period but rejected access-road ground despite Tehsildar report confirming 45m road encroached and unacquired. The court examined whether rejection aligned with policy conditions (Paras 5-9).

B) Statutory Remedies - Revisional Jurisdiction - Section 41(3) Uttar Pradesh Urban Planning and Development Act, 1973 read with Section 12 Uttar Pradesh Industrial Area Development Act, 1976 - Against CEO order rejecting zero period benefit, Developer filed revision before State Government; this statutory remedy was pending when UPRERA complaint was rejected as not maintainable with direction to pursue alternative remedies (Paras 10-12).

C) Real Estate Regulation - UPRERA Jurisdiction - Maintainability of Complaints - UPRERA rejected complaint as not maintainable when alternative statutory remedies existed but recorded factual findings on road non-construction - UPRERA's technical inspection confirmed 45m road not constructed and existing habitation remained (Paras 11-12).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Developer was entitled to Zero Period Policy benefit on account of NGT restraint order and non-availability of access roads; and whether the High Court's interference with the rejection was justified.

Subscribe to unlock Issue of Consideration Subscribe Now

Law Points

  • Zero Period Policy entitles allottees to rescheduling of instalments and waiver of penal interest where construction is impossible due to encroachment
  • lack of access roads
  • or court stay orders
  • authority must verify access road claims through field reports
  • UPRERA may reject a complaint as not maintainable when alternative statutory remedies exist under the Uttar Pradesh Urban Planning and Development Act
  • 1973 and the Uttar Pradesh Industrial Area Development Act
  • 1976
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (SC) (09) 32

Civil Appeal No(s). 10900-10902 of 2025

2026 INSC 975

New Okhla Industrial Development Authority and Ors.

M/s Sunshine Trade Tower Private Limited and Anr.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeals challenging Allahabad High Court judgment in writ petitions concerning entitlement to Zero Period Policy benefit under NOIDA policy for stalled commercial plot development due to NGT restraint and lack of access roads.

Remedy Sought

Developer sought zero period benefit rescheduling of instalments and waiver of penal interest for periods affected by NGT restraint and non-availability of access roads; NOIDA appealed against High Court order.

Filing Reason

Aggrieved by the Allahabad High Court's final judgment and order dated 19.07.2024 in Writ-C Nos. 9348 and 21276 of 2023, and 7223 of 2024.

Previous Decisions

NOIDA CEO order dated 14.02.2020 rejected zero period benefit for access road ground; UPRERA order dated 22.10.2020 rejected complaint as not maintainable with direction to pursue statutory remedies; Allahabad High Court passed impugned judgment on 19.07.2024.

Issues

Whether the Developer is entitled to Zero Period Policy benefit due to NGT restraint order and non-availability of access roads to the allotted plot. Whether the rejection of zero period benefit by NOIDA CEO was justified despite Tehsildar report confirming 45-metre front road encroached and unacquired. Whether UPRERA complaint was maintainable when alternative statutory remedies under the 1973 and 1976 Acts were available.

Submissions/Arguments

Developer contended that construction could not proceed due to NGT restraint and lack of access roads, and sought zero period benefit for those periods. NOIDA contended that alternative access existed via 24-metre road and partially 45-metre road, and rejected benefit for access road ground. UPRERA held the complaint not maintainable and directed pursuit of alternative statutory remedies under the 1973 and 1976 Acts.

Judgment Excerpts

After due consideration on the supplementary item no. 2 of the 188th meeting of the Board of Directors of Noida Authority, the following instructions/procedure regarding Zero Hour are issued in continuation of the instructions given by the Board of Directors of Noida Authority on 14.03.2016. A 45.00-meter-wide road is located on one side and a 24.00-meter-wide road is on the other side of Commercial Plot No. 05A. The construction of the 45.00-meter-wide road in front of this plot could not be completed due to encroachment by farmers. It is clear from the inspection report that the 24.00-meter road construction work was completed by NOIDA in 2020. ... It has been informed that the 45.00-meter road has not been constructed, and there is an existing habitation at that place.

Procedural History

On 22.09.2011 NOIDA launched scheme for allotment of commercial plots; lease deed executed on 11.01.2012; NGT interim order restrained construction on 17.09.2013; restraint lifted on 19.08.2015; NOIDA promulgated Zero Period Policy on 28.03.2016; developer made representations on 12.04.2016, 29.09.2016, and 15.10.2016; NOIDA granted partial benefit on 05.06.2017 but referred access road issue to Tehsildar; Tehsildar report dated 14.02.2019 confirmed encroachment; NOIDA committee rejected access-road claim on 09.01.2020; CEO order dated 14.02.2020 rejected benefit; developer filed revision before State Government under Section 41(3) of 1973 Act read with Section 12 of 1976 Act; developer filed UPRERA complaint; UPRERA passed order dated 22.10.2020 rejecting complaint as not maintainable; Allahabad High Court passed impugned judgment dated 19.07.2024; civil appeals filed before Supreme Court.

Acts & Sections

  • Uttar Pradesh Urban Planning and Development Act, 1973: Section 41(3)
  • Uttar Pradesh Industrial Area Development Act, 1976: Section 12
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Union's Challenge to Dearness Allowance Scheme Modification in Wage Reference. Court Upholds Industrial Tribunal's Decision to Remove Linkage Between Dearness Allowance and Basic Pay Under Section 9A of Industrial Disputes...
Related Judgement
Supreme Court Supreme Court Upholds Reversion of Deputationist in Service Law Dispute Regarding Promotion Rights. Lien in Parent Department Prevails Over Temporary Appointment in Borrowing Department Under General Service Jurisprudence.