Case Note & Summary
The petitioner, K L Ramesh, claiming to be the owner of land measuring 3 acres 9 guntas in Sy.No.44/2 at Yelechenahalli Village, Uttarahalli Hobli, Bangalore South Taluk, filed a writ petition under Articles 226 and 227 of the Constitution of India. The petitioner sought a declaration that the scheme published by the Government of Karnataka by virtue of the preliminary notification dated 6.4.1989 under Section 17(1) of the Land Acquisition Act, 1894 (the Act) and the final declaration dated 18.5.1994 under Section 19(1) of the Act in respect of the said land had lapsed. The respondents were the Bangalore Development Authority, the Government of Karnataka, and the Special Land Acquisition Officer. The petitioner contended that the award was not made within two years from the date of the final declaration, as required under Section 11A of the Act, and therefore the acquisition proceedings had lapsed. The court, after hearing the parties, held that the failure to make an award within the prescribed period of two years from the date of the final declaration under Section 19(1) of the Act results in the lapse of the acquisition proceedings. The court allowed the writ petition and declared that the acquisition proceedings in respect of the petitioner's land had lapsed. The court directed the respondents to issue a notification under Section 48 of the Act withdrawing from the acquisition and to return the land to the petitioner if possession had not been taken, or if possession had been taken, to pay compensation in accordance with law.
Headnote
A) Land Acquisition - Lapse of Acquisition - Section 11A Land Acquisition Act, 1894 - Mandatory Time Limit - The court considered whether the acquisition proceedings had lapsed due to non-compliance with the statutory time limit for making an award. The petitioner claimed that the award was not made within two years from the date of the final declaration under Section 19(1) of the Act. The court held that the failure to make an award within the prescribed period results in the lapse of the acquisition proceedings. (Paras 1-4) B) Land Acquisition - Preliminary Notification - Section 17(1) Land Acquisition Act, 1894 - Validity - The court examined the preliminary notification dated 6.4.1989 issued under Section 17(1) of the Act. The court did not find any infirmity in the notification itself but focused on the subsequent failure to comply with Section 11A. (Paras 1-2) C) Land Acquisition - Final Declaration - Section 19(1) Land Acquisition Act, 1894 - Time Limit - The final declaration was made on 18.5.1994 under Section 19(1) of the Act. The court noted that the award was not made within two years from this date, leading to the lapse of the acquisition. (Paras 1-4)
Issue of Consideration
Whether the land acquisition proceedings in respect of the petitioner's land have lapsed under Section 11A of the Land Acquisition Act, 1894, due to the failure to make an award within two years from the date of the final declaration under Section 19(1) of the Act.
Final Decision
The writ petition is allowed. The acquisition proceedings in respect of the petitioner's land in Sy.No.44/2 measuring 3 acres 9 guntas at Yelechenahalli Village, Uttarahalli Hobli, Bangalore South Taluk are declared to have lapsed. The respondents are directed to issue a notification under Section 48 of the Land Acquisition Act, 1894 withdrawing from the acquisition and to return the land to the petitioner if possession has not been taken, or if possession has been taken, to pay compensation in accordance with law.
Law Points
- Land Acquisition
- Lapse of Acquisition
- Section 11A Land Acquisition Act 1894
- Mandatory Time Limit
- Award Not Made Within Two Years
- Declaration of Lapse




