Case Note & Summary
The petitioner, M/s.Muthu Construction, a proprietary concern, entered into a contract with the respondent, Union of India represented by the Southern Railway, for repairs to existing dilapidated fittings over points and crossings, etc. The contract was awarded pursuant to a tender, and the letter of acceptance was issued on 28.11.2018 for a value of Rs.1,55,15,697/-. The contract agreement was SA/279 dated 06.02.2019. Disputes arose regarding the measurement and payment for work done. The petitioner claimed that the respondent had measured the work in 'track metre' but paid only for 'metre', resulting in a short payment. The matter was referred to arbitration. The Arbitral Tribunal passed an award dated 22.01.2022, rejecting the petitioner's claim. The petitioner filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, to set aside the award. The court heard arguments from both sides. The petitioner argued that the Tribunal misinterpreted the contract, as the contract specified the unit of measurement as 'per metre' but the actual work was measured in 'track metre', which is a different unit. The respondent contended that the award was based on a plausible interpretation and should not be interfered with. The court analyzed the contract and found that the Tribunal had erroneously held that the contract was for 'per track metre' when it was actually for 'per metre'. This misinterpretation led to the rejection of the claim. The court held that this constituted a patent illegality under Section 34 of the Act. Consequently, the court set aside the award to the extent it rejected the claim and remanded the matter to the Arbitral Tribunal for fresh consideration of the claim in accordance with the correct interpretation of the contract. The court directed the Tribunal to pass a fresh award within four months from the date of receipt of the order. The petition was partly allowed.
Headnote
A) Arbitration Law - Section 34 Petition - Patent Illegality - The court examined whether the Arbitral Tribunal's interpretation of the contract's measurement unit 'track metre' was patently illegal. The Tribunal had rejected the claim for difference in payment based on a mistaken understanding that the contract was for 'per track metre' whereas the contract specified 'per metre'. The court found this to be a patent illegality as the Tribunal misconstrued the contract terms. (Paras 1-22) B) Arbitration Law - Remand - Section 34 of the Arbitration and Conciliation Act, 1996 - The court held that where an arbitral award suffers from patent illegality, the court can set aside the award and remand the matter to the Arbitral Tribunal for fresh consideration. The court directed the Tribunal to reconsider the claim afresh in light of the correct interpretation of the contract. (Paras 20-22)
Issue of Consideration
Whether the Arbitral Tribunal's rejection of the petitioner's claim for payment based on the unit of measurement 'track metre' suffers from patent illegality warranting interference under Section 34 of the Arbitration and Conciliation Act, 1996.
Final Decision
The court partly allowed the petition, set aside the arbitral award to the extent it rejected the claim, and remanded the matter to the Arbitral Tribunal for fresh consideration of the claim in accordance with the correct interpretation of the contract. The Tribunal was directed to pass a fresh award within four months.
Law Points
- Section 34 of the Arbitration and Conciliation Act
- 1996
- Patent illegality
- Arbitral award
- Remand
- Measurement unit
- Track metre
- Contract interpretation




