Bombay High Court Dismisses Appeal Against Rejection of Section 9 Petition Seeking Injunction on Bank Guarantee Invocation. Performance Bank Guarantee Invocation Upheld as No Fraud or Irretrievable Injustice Established Under Contract Clause 4.2.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 1
Judgement Image
Font size:
Print

Case Note & Summary

The appellant, Tata Projects Limited, was awarded a turnkey contract by respondent No.1, Hazel International FZE, for constructing a Chemical Storage Terminal in Sharjah, UAE. The contract was executed on 02/06/2014, and the appellant furnished a Performance Bank Guarantee issued by respondent Nos.2 and 3 (Bank of Baroda) on 11/08/2014. The work was to be completed within two years, but was not completed within that period, and an extension of two years was granted. The appellant claimed delays were due to reasons beyond its control and attributable to the respondent-employer. On 17/11/2018, respondent No.1 invoked the bank guarantee. The appellant filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking an injunction against the invocation. The learned Single Judge rejected the petition. The appellant appealed. The Division Bench held that the law regarding bank guarantees is well settled: courts should not interfere unless there is established fraud or irretrievable injustice. The appellant argued that Clause 4.2 of the contract required an amount due before invocation, but the court found that the bank guarantee is an independent contract and its invocation cannot be restrained based on contractual disputes. The appellant failed to establish fraud or irretrievable injustice. The appeal was dismissed.

Headnote

A) Arbitration - Interim Relief - Section 9 Arbitration and Conciliation Act, 1996 - Injunction against Bank Guarantee - The court considered whether an injunction could be granted against invocation of a performance bank guarantee. Held that unless there is established fraud or irretrievable injustice, the court should not interfere with the invocation of a bank guarantee. The appellant failed to establish either condition. (Paras 1-14)

B) Contract Law - Interpretation of Clause 4.2 - Performance Bank Guarantee - The appellant argued that Clause 4.2 of the contract required an amount due before invocation. The court held that the bank guarantee is an independent contract and its invocation cannot be restrained based on contractual disputes unless fraud or irretrievable injustice is shown. (Paras 4-14)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the appellant is entitled to an injunction restraining the invocation of the Performance Bank Guarantee in the absence of established fraud or irretrievable injustice.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Appeal dismissed. The order of the learned Single Judge rejecting the Section 9 petition is upheld.

Law Points

  • Bank Guarantee
  • Injunction
  • Fraud
  • Irretrievable Injustice
  • Section 9 Arbitration and Conciliation Act
  • 1996
  • Contract Interpretation
Subscribe to unlock Law Points Subscribe Now

Case Details

2018:BHC-OS:17349-DB

Commercial Appeal No.514 of 2018 with Commercial Notice of Motion No.1226 of 2018 in Commercial Arbitration Petition (L) No.1465 of 2018

2018-11-24

B. R. Gavai, A. S. Chandurkar

2018:BHC-OS:17349-DB

Shri Gaurav Joshi, Senior Advocate with Shri Rohan Cama, Advocate, Kaustav Talukdar, Kazan Shroff, Advocate, Shri Vikash Kumar, Advocate and Shri Bipin Mehta Advocate I/b M/s Lex Legal and Partners for appellant/applicant. Shri Venkatesh Dhond, Senior Advocate with Shri Amey Patil, Advocate, Ms Hetal Jobanputra, Advocate, Shri Vivek Sharma, Advocate, Ms Bhairavi Waravdekar, Advocate I/b M/s Vivek Kantawala & Co. for respondent No.1.

Tata Projects Limited

Hazel International FZE, Bank of Baroda Sharjah Branch, Bank of Baroda Hyderabad

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal against rejection of petition under Section 9 of the Arbitration and Conciliation Act, 1996 seeking injunction against invocation of Performance Bank Guarantee.

Remedy Sought

Appellant sought injunction restraining respondent No.1 from invoking the Performance Bank Guarantee.

Filing Reason

Respondent No.1 invoked the Performance Bank Guarantee on 17/11/2018, and appellant sought interim relief under Section 9.

Previous Decisions

Learned Single Judge rejected the petition under Section 9.

Issues

Whether the appellant is entitled to an injunction restraining the invocation of the Performance Bank Guarantee in the absence of established fraud or irretrievable injustice.

Submissions/Arguments

Appellant argued that Clause 4.2 of the contract required an amount due before invocation, and thus the invocation was premature. Respondent argued that the bank guarantee is an independent contract and its invocation cannot be restrained unless fraud or irretrievable injustice is shown.

Ratio Decidendi

The court held that unless there is established fraud or irretrievable injustice, the court should not interfere with the invocation of a bank guarantee. The appellant failed to establish either condition.

Judgment Excerpts

This appeal challenges an order passed by the learned Single Judge in Commercial Arbitration Petition (Lodging) No.1465 of 2018 thereby rejecting the petition filed by the present appellant under Section 9 of the Arbitration and Conciliation Act, 1996. Undisputedly the present appellant was awarded a contract for constructing Chemical Storage Terminal at Hamriyah Free Zone, Sharjah U.A.E. by the respondent No.1 on 20/02/2014. Vide communication dated 17/11/2018 addressed by the respondent No.1 to the respondent Nos.2 and 3, respondent No.1 invoked the Bank Guarantee.

Procedural History

Appellant filed Commercial Arbitration Petition (L) No.1465 of 2018 under Section 9 of the Arbitration and Conciliation Act, 1996 before the learned Single Judge. The petition was rejected. Appellant then filed Commercial Appeal No.514 of 2018 before the Division Bench.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 9
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Appeal Against Rejection of Section 9 Petition Seeking Injunction on Bank Guarantee Invocation. Performance Bank Guarantee Invocation Upheld as No Fraud or Irretrievable Injustice Established Under Contract Clause 4.2.
Related Judgement
Supreme Court Supreme Court Allows Secured Creditor's Appeal in Co-operative Bank Liquidation Case, Holding Priority Over Workmen's Dues Under SARFAESI Act. Section 26E of the Securitisation and Reconstruction of Financial Assets and Enforcement of Security Intere...