Bombay High Court Allows Writ Petition Challenging Interim Orders Under Section 9 of Arbitration Act — Orders Set Aside for Non-Compliance with Mandatory Pre-Arbitration Procedure. The court held that the learned Principal District Judge lacked jurisdiction to grant interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, as the applicant failed to comply with the mandatory pre-arbitration conciliation procedure agreed upon in the contract.

High Court: Bombay High Court Bench: GOA In Favour of Accused
  • 73
Judgement Image
Font size:
Print

Case Note & Summary

The petitioners, Mineira Nacional Limitada and others, filed a writ petition challenging two orders dated 13.01.2016 and 29.11.2016 passed by the learned Principal District Judge (PDJ), Panaji, in Civil Miscellaneous Application No. 119/2013 in Arbitration Application No. 36/2012. The PDJ had allowed an application under Section 9 of the Arbitration and Conciliation Act, 1996, filed by the first respondent, Hardesh Ores Private Limited, directing the petitioners to maintain status quo and not to alienate certain properties. The petitioners contended that the application under Section 9 was not maintainable because the first respondent had not complied with the mandatory pre-arbitration procedure agreed upon in the contract between the parties. The contract required that before invoking arbitration, the parties must first attempt to settle the dispute through a named conciliator. The first respondent had directly approached the court under Section 9 without attempting such conciliation. The court examined the arbitration agreement and found that the pre-arbitration procedure was a condition precedent to the invocation of arbitration. The court held that the PDJ had no jurisdiction to entertain the Section 9 application until the pre-arbitration procedure was exhausted. Consequently, the impugned orders were set aside, and the writ petition was allowed. The court also noted that the first respondent was at liberty to invoke arbitration after complying with the pre-arbitration procedure.

Headnote

A) Arbitration - Section 9 of Arbitration and Conciliation Act, 1996 - Interim Measures - Pre-arbitration Procedure - The court held that the learned Principal District Judge erred in entertaining the application under Section 9 without the applicant first exhausting the mandatory pre-arbitration procedure agreed upon in the contract. The dispute resolution mechanism required the parties to first attempt settlement through a named conciliator before invoking arbitration. Since the applicant failed to comply with this condition precedent, the application under Section 9 was not maintainable. (Paras 2-10)

B) Arbitration - Section 9 of Arbitration and Conciliation Act, 1996 - Jurisdiction - Condition Precedent - The court held that the requirement of a pre-arbitration procedure is a condition precedent to the invocation of arbitration and consequently to the jurisdiction of the court under Section 9. The court cannot grant interim relief unless the arbitration agreement has been properly invoked in accordance with its terms. (Paras 11-15)

C) Arbitration - Section 9 of Arbitration and Conciliation Act, 1996 - Interim Orders - Setting Aside - The court set aside the impugned orders dated 13.01.2016 and 29.11.2016 passed by the learned Principal District Judge, Panaji, in Civil Miscellaneous Application No. 119/2013 in Arbitration Application No. 36/2012, as the orders were passed without jurisdiction. (Paras 16-18)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the learned Principal District Judge could entertain and grant interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, without the applicant first complying with the mandatory pre-arbitration procedure agreed upon between the parties.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The writ petition is allowed. The impugned orders dated 13.01.2016 and 29.11.2016 passed by the learned Principal District Judge, Panaji, in Civil Miscellaneous Application No. 119/2013 in Arbitration Application No. 36/2012 are set aside. The first respondent is at liberty to invoke arbitration after complying with the pre-arbitration procedure.

Law Points

  • Arbitration
  • Section 9 of Arbitration and Conciliation Act
  • 1996
  • Pre-arbitration procedure
  • Interim measures
  • Jurisdiction of court
Subscribe to unlock Law Points Subscribe Now

Case Details

2017 LawText (BOM) (06) 127

Writ Petition No. 1180 of 2016

2017-06-06

C. V. Bhadang

2017:BHC-GOA:1409

Ashwin D. Bhobe, Maria C. D'Costa Mashelkar, Shradha Bhobe, Rafiq Dada, S.S. Kantak, Gurudatt Mallaya, Linette da Costa Rodrigues, Preetam Talaulikar, Mahesh Amonkar, Prachita R. Kalangutkar

Mineira Nacional Limitada, Arjun Anil Salgaocar, Anil Vasudeva Salgaocar (Deleted)

Hardesh Ores Private Limited, Regional Controller of Mines, Indian Bureau of Mines, State of Goa

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition challenging orders passed by Principal District Judge under Section 9 of Arbitration and Conciliation Act, 1996.

Remedy Sought

Petitioners sought setting aside of orders dated 13.01.2016 and 29.11.2016 passed by the learned Principal District Judge, Panaji, in Civil Miscellaneous Application No. 119/2013 in Arbitration Application No. 36/2012.

Filing Reason

The petitioners challenged the orders on the ground that the learned Principal District Judge had no jurisdiction to entertain the application under Section 9 of the Arbitration and Conciliation Act, 1996, as the first respondent had not complied with the mandatory pre-arbitration procedure agreed upon in the contract.

Previous Decisions

The learned Principal District Judge had allowed the application under Section 9 filed by the first respondent, directing the petitioners to maintain status quo and not to alienate certain properties.

Issues

Whether the learned Principal District Judge could entertain an application under Section 9 of the Arbitration and Conciliation Act, 1996, without the applicant first complying with the mandatory pre-arbitration procedure agreed upon between the parties.

Submissions/Arguments

Petitioners argued that the first respondent had not complied with the pre-arbitration procedure requiring conciliation before invoking arbitration, and therefore the application under Section 9 was not maintainable. First respondent argued that the pre-arbitration procedure was not a condition precedent and that the court had jurisdiction to grant interim relief under Section 9.

Ratio Decidendi

The requirement of a pre-arbitration procedure is a condition precedent to the invocation of arbitration and consequently to the jurisdiction of the court under Section 9 of the Arbitration and Conciliation Act, 1996. The court cannot grant interim relief unless the arbitration agreement has been properly invoked in accordance with its terms.

Judgment Excerpts

The challenge in this petition is to the orders dated 13.01.2016 and 29.11.2016 passed by the learned Principal District Judge Panaji (PDJ, for short) in Civil Miscellaneous Application No. 119/2013 in Arbitration Application No. 36/2012. The court held that the learned PDJ erred in entertaining the application under Section 9 without the applicant first exhausting the mandatory pre-arbitration procedure agreed upon in the contract.

Procedural History

The first respondent filed an application under Section 9 of the Arbitration and Conciliation Act, 1996, before the Principal District Judge, Panaji, which was allowed by orders dated 13.01.2016 and 29.11.2016. The petitioners challenged these orders by filing the present writ petition. The writ petition was heard and reserved on 16.02.2017 and pronounced on 06.06.2017.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 9
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Compassionate Appointment of Shikshan Sevak Despite Recruitment Ban — Government Resolution dated 2nd May 2012 Not Applicable to Compassionate Appointments. The Court held that the Education Officer cannot refuse approval t...
Related Judgement
Supreme Court Supreme Court Upholds Plaintiffs in Partition Suit: Adoption and Will Not Proved; High Court Erred Under Section 100 CPC. First Wife's Consent Not Obtained for Adoption Under Section 7 of Hindu Adoptions and Maintenance Act, 1956, and Will Not Proved...