Case Note & Summary
The petitioner, Smt. Nilima Mahesh Bhole, filed a writ petition before the Bombay High Court (Aurangabad Bench) seeking quashment of land acquisition proceedings initiated by the State of Maharashtra for the Waghur Project, an irrigation project. The acquisition pertained to 20 Ares of her land in Asoda, Jalgaon. The proceedings were initiated under the Land Acquisition Act, 1894. A notification under Section 4 was issued, followed by a declaration under Section 6 published on 18 December 2008. However, the Special Land Acquisition Officer made the award under Section 11 on 28 March 2011, which was beyond the two-year period prescribed under Section 11A of the Act. The petitioner contended that the acquisition proceedings had lapsed due to the failure to make the award within the statutory period. The respondents argued that the delay was due to administrative reasons and that the proceedings should not be quashed. The court examined the provisions of Section 11A, which mandates that the Collector shall make an award within two years from the date of publication of the declaration under Section 6, failing which the entire proceedings lapse. The court held that the provision is mandatory and not directory. Since the award was made after the expiry of two years, the acquisition proceedings stood lapsed. The court allowed the petition, quashed the acquisition proceedings to the extent of the petitioner's land, and directed the respondents to return possession if taken and to pay compensation for any use of the land during the period of possession.
Headnote
A) Land Acquisition - Lapse of Acquisition Proceedings - Section 11A of Land Acquisition Act, 1894 - Failure to make award within two years from declaration under Section 6 - The petitioner challenged acquisition of 20 Ares of her land for Waghur Project. The declaration under Section 6 was published on 18.12.2008, but the award was made on 28.03.2011, beyond the two-year period. The Court held that the provisions of Section 11A are mandatory and the entire acquisition proceedings lapsed due to non-compliance. The Court relied on the principle that the Collector must make an award within two years from the date of publication of the declaration under Section 6, failing which the proceedings lapse. (Paras 2-6) B) Land Acquisition - Mandatory Nature of Section 11A - Land Acquisition Act, 1894 - The Court observed that Section 11A uses the word 'shall' and imposes a time limit of two years for making the award. The failure to adhere to this time limit results in the lapse of the entire acquisition proceedings. The Court rejected the argument that the period could be extended or that the proceedings could be saved by any subsequent action. (Paras 4-6) C) Land Acquisition - Writ Jurisdiction - Quashment of Acquisition Proceedings - The Court exercised its writ jurisdiction under Article 226 of the Constitution to quash the acquisition proceedings as they had lapsed under Section 11A. The Court directed the respondents to return the possession of the land to the petitioner if taken, and to pay compensation for any use of the land during the period of possession. (Paras 6-7)
Issue of Consideration
Whether the acquisition proceedings in respect of the petitioner's land lapsed due to failure to make an award under Section 11 of the Land Acquisition Act, 1894 within two years from the date of declaration under Section 6 of the said Act.
Final Decision
The writ petition is allowed. The acquisition proceedings bearing No. 3 of 2008 to the extent of 20 Ares of the petitioner's land are quashed and set aside. The respondents are directed to return the possession of the land to the petitioner if taken, and to pay compensation for the use of the land during the period of possession, if any.
Law Points
- Land Acquisition Act
- 1894
- Section 11A
- Section 6
- Section 4
- Lapse of acquisition proceedings
- Failure to make award within prescribed period
- Mandatory provision
- Writ jurisdiction





