Case Note & Summary
The case involves an appeal filed by Messrs. Raghuvir Cotton Ginning & Pressing Pvt. Ltd. (the appellant) under Section 37 of the Arbitration and Conciliation (Amendment) Act, 2015, challenging an order dated 6th October 2016 passed by a learned Single Judge of the Bombay High Court. The Single Judge had rejected the appellant's Chamber Summons seeking amendments to its Arbitration Petition filed under Section 34 of the Arbitration and Conciliation Act, 1996, to challenge an arbitral award. The main petition was pending final adjudication. The respondent raised a preliminary objection that the appeal was not maintainable under Section 37, arguing that only orders specified therein are appealable. The appellant relied on the Supreme Court judgment in State of Maharashtra v. Hindustan Construction Company Limited, which dealt with the aspect of amendment to add additional grounds within the prescribed period in an application under Section 34 or memo of appeal under Section 37. The Court considered the issue of whether incorporation of additional grounds by way of amendment tantamounts to filing a fresh application. The Division Bench, consisting of Justice Anoop V. Mohta and Justice P.R. Bora, held that the appeal is maintainable as the order refusing amendment finally decides the rights of the parties regarding the grounds to be urged. The Court further held that if additional grounds are sought to be added within the limitation period, the amendment should be liberally allowed as it does not introduce a new cause of action. The Court allowed the appeal, set aside the impugned order, and permitted the appellant to carry out the amendments as sought, subject to the condition that the amended petition be filed within two weeks and the respondent be given an opportunity to file a reply.
Headnote
A) Arbitration Law - Amendment of Pleadings - Section 34, Arbitration and Conciliation Act, 1996 - Maintainability of Appeal - The Court held that an appeal under Section 37 of the Act is maintainable against an order refusing amendment of a petition under Section 34, as such an order finally decides the rights of the parties regarding the grounds to be urged. The Court also held that incorporation of additional grounds by way of amendment within the prescribed period does not tantamount to filing a fresh application, relying on State of Maharashtra v. Hindustan Construction Company Limited. (Paras 2-5) B) Arbitration Law - Limitation - Section 34, Arbitration and Conciliation Act, 1996 - Amendment within Limitation - The Court observed that if additional grounds are sought to be added within the limitation period for filing objections under Section 34, the amendment should be liberally allowed, as it does not introduce a new cause of action but merely elaborates existing grounds. (Para 4)
Issue of Consideration
Whether an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 is maintainable against an order refusing amendment of an arbitration petition under Section 34, and whether incorporation of additional grounds by way of amendment in the application under Section 34 tantamounts to filing a fresh application.
Final Decision
The appeal is allowed. The impugned order dated 6th October 2016 is set aside. The Chamber Summons for amendments is allowed. The appellant is permitted to carry out the amendments as sought, subject to the condition that the amended petition be filed within two weeks from today. The respondent is at liberty to file an additional reply, if any, within two weeks thereafter.
Law Points
- Amendment of pleadings in arbitration proceedings
- Section 34 of Arbitration and Conciliation Act
- 1996
- Section 37 of Arbitration and Conciliation Act
- Maintainability of appeal against refusal of amendment
- Liberal approach to amendments
- Limitation period for filing objections




