Bombay High Court Allows Appeal Against Rejection of Amendment to Arbitration Petition Under Section 34. Addition of Grounds Within Limitation Period Does Not Amount to Fresh Application Under Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: BOMBAY
  • 11
Judgement Image
Font size:
Print

Case Note & Summary

The appellant, Messrs. Raghuvir Cotton Ginning & Pressing Pvt. Ltd., filed an appeal under Section 37 of the Arbitration and Conciliation (Amendment) Act, 2015, challenging an order dated 6 October 2016 passed by a learned Single Judge of the Bombay High Court. The Single Judge had rejected the appellant's Chamber Summons seeking amendments to its Arbitration Petition filed under Section 34 of the Arbitration Act, 1996, to set aside an arbitral award. The main petition was pending final adjudication. The respondent raised a preliminary objection that the appeal was not maintainable under Section 37, arguing that only specific grounds mentioned therein are appealable. The appellant relied on the Supreme Court judgment in State of Maharashtra v. Hindustan Construction Company Limited, which dealt with the aspect of amendment to add additional grounds within the prescribed period in an application under Section 34 or memo of appeal under Section 37. The Supreme Court had observed that incorporation of additional grounds by way of amendment does not tantamount to filing a fresh application in all situations and circumstances. The Division Bench of the Bombay High Court, consisting of Justice Anoop V. Mohta and Justice P.R. Bora, after hearing both sides, allowed the appeal, set aside the impugned order, and permitted the appellant to carry out the amendments as sought. The court held that the amendment was within the limitation period and did not constitute a fresh application. The court also directed that the amendment be carried out within two weeks and that the respondent may file an additional affidavit in reply within four weeks. The main arbitration petition was to be listed for hearing in due course.

Headnote

A) Arbitration Law - Amendment of Petition under Section 34 - Addition of Grounds - Arbitration and Conciliation Act, 1996, Section 34 - The court considered whether incorporation of additional grounds by way of amendment in an application under Section 34 tantamounts to filing a fresh application. Relying on State of Maharashtra v. Hindustan Construction Company Limited, the court held that if the amendment is within the limitation period, it does not constitute a fresh application and is permissible. The appeal against rejection of such amendment is maintainable under Section 37. (Paras 2-5)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether an amendment to add additional grounds in a petition under Section 34 of the Arbitration and Conciliation Act, 1996, filed within the prescribed period, amounts to filing a fresh application and is therefore impermissible.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Appeal allowed. Impugned order dated 6 October 2016 set aside. Appellant permitted to carry out amendments as sought. Amendment to be carried out within two weeks. Respondent may file additional affidavit in reply within four weeks. Main Arbitration Petition to be listed for hearing in due course.

Law Points

  • Amendment of arbitration petition under Section 34 of Arbitration and Conciliation Act
  • 1996 is permissible if filed within limitation period
  • addition of grounds does not amount to fresh application
  • Section 37 appeal maintainable against order rejecting amendment
Subscribe to unlock Law Points Subscribe Now

Case Details

2017 LawText (BOM) (01) 140

Appeal (L) No.465 of 2006 in Chamber Summons (L) No.1977 of 2016 in Arbitration Petition No.507 of 2016

2017-01-11

Anoop V. Mohta, P.R. Bora

2017:BHC-OS:454-DB

Mr.Shaunak Thakkar i/by Rinku Valanju for Appellant, Mr.Simil Purohit i/by M/s Purohit & Co. for Respondent

Messrs. Raghuvir Cotton Ginning & Pressing Pvt. Ltd.

Messrs. Vijay Cotton & Fibre Co.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal under Section 37 of the Arbitration and Conciliation (Amendment) Act, 2015 against order rejecting amendment to Arbitration Petition under Section 34 of the Arbitration Act, 1996.

Remedy Sought

Appellant sought to set aside the order dated 6 October 2016 rejecting its Chamber Summons for amendments to the Arbitration Petition.

Filing Reason

The learned Single Judge rejected the appellant's application for amendment to add additional grounds in the petition under Section 34.

Previous Decisions

The Chamber Summons for amendments was rejected by the learned Single Judge on 6 October 2016.

Issues

Whether an appeal under Section 37 is maintainable against an order rejecting amendment to a Section 34 petition. Whether amendment to add additional grounds in a Section 34 petition within limitation period amounts to filing a fresh application.

Submissions/Arguments

Respondent argued that under Section 37, only specific grounds are appealable and the present appeal is not maintainable. Appellant relied on Supreme Court judgment in State of Maharashtra v. Hindustan Construction Company Limited to argue that amendment within limitation period is permissible and does not constitute a fresh application.

Ratio Decidendi

Incorporation of additional grounds by way of amendment in an application under Section 34 of the Arbitration and Conciliation Act, 1996, if made within the prescribed period of limitation, does not tantamount to filing a fresh application and is permissible. An appeal against rejection of such amendment is maintainable under Section 37 of the Act.

Judgment Excerpts

Whether incorporation of additional grounds by way of amendment in the application under Section 34 tantamounts to filing a fresh application in all situations and circumstances. If that were to be treated so, it would follow that no amendment in the application for setting aside the award would be permissible. The appeal is allowed. The impugned order dated 6 October 2016 is set aside. The appellant is permitted to carry out the amendments as sought.

Procedural History

The appellant filed Arbitration Petition No.507 of 2016 under Section 34 of the Arbitration Act, 1996 to set aside an arbitral award. The appellant filed Chamber Summons (L) No.1977 of 2016 seeking amendments to the petition. The learned Single Judge rejected the Chamber Summons on 6 October 2016. The appellant then filed the present Appeal (L) No.465 of 2006 under Section 37 of the Arbitration and Conciliation (Amendment) Act, 2015 against that order.

Acts & Sections

  • Arbitration and Conciliation (Amendment) Act, 2015: Section 37
  • Arbitration and Conciliation Act, 1996: Section 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Appeal Against Rejection of Amendment to Arbitration Petition Under Section 34. Addition of Grounds Within Limitation Period Does Not Amount to Fresh Application Under Arbitration and Conciliation Act, 1996.
Related Judgement
High Court Bombay High Court Allows Appeal Against Condonation of Delay in MPID Act Case — Designated Court Has No Power to Condon Delay Beyond 90 Days Under Section 5(3) of MPID Act. Limitation Period for Filing Application Under Section 5(3) is 90 Days, Del...