Madras High Court Closes Contempt Petition After Compliance with Writ Order — Encroachments Removed and Bridge Constructed. Court finds that the order dated 11.02.2022 in W.P.No.21784 of 2021 has been complied with, and closes the contempt petition with liberty to file a fresh complaint if any grievance persists.

High Court: Madras High Court
  • 49
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, P.D.Muthusamy, filed a contempt petition (CONT P No. 1811 of 2022) before the Madras High Court seeking to punish the respondents for allegedly disobeying the order passed by the court on 11.02.2022 in W.P.No.21784 of 2021. The respondents included the District Collector, the President of Panchayat/Executive Officer, the Block Development Officer, the Assistant Director for Village Panchayat, and one N.Ramalingam (impleaded later). The court, comprising Justice S.M.Subramaniam and Justice C.Kumarappan, considered the matter. During the hearing, the Block Development Officer submitted written instructions indicating that the encroachments had been removed and a small bridge had been constructed. The court found that the order had been complied with and that no further action was warranted in the contempt proceedings. However, the court granted liberty to the petitioner to file a fresh complaint if any grievance still existed. Consequently, the contempt petition was closed. The judgment was delivered on 18.02.2026 and uploaded on 20.02.2026.

Headnote

A) Contempt of Court - Compliance with Order - Closure of Proceedings - The contempt petition was filed alleging disobedience of the order dated 11.02.2022 in W.P.No.21784 of 2021 - The court noted that written instructions from the Block Development Officer showed that encroachments had been removed and a small bridge constructed - Held that the order had been complied with, and the contempt petition was closed with liberty to the petitioner to file a fresh complaint if any grievance persists (Paras 1-3).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the respondents had willfully disobeyed the order dated 11.02.2022 in W.P.No.21784 of 2021, and whether contempt proceedings should be continued.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The contempt petition stands closed. The petitioner is at liberty to file a fresh complaint if any grievance exists.

Law Points

  • Contempt of court
  • compliance with court orders
  • closure of contempt proceedings upon satisfaction
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (MAD) (02) 258

CONT P No. 1811 of 2022

2026-02-18

S. M. Subramaniam, C. Kumarappan

2026:MHC:694

Mr.P.Valliappan, Senior Counsel for M/S.Pv Law Associates for petitioner; Mr.T.Arun Kumar, AGO for R1 to R4; Mr.C.Prabakran for R5

P.D.Muthusamy

Mrs.P.Sri Venkada Priya, The District Collector; Muthusamy, The President of Panchayat / Executive Officer; Muralidharan, The Block Development Officer; N.Ganabathy, The Assistant Director for Village Panchayat; N.Ramalingam (impleaded as per order dt.18.02.2026)

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Contempt petition alleging willful disobedience of court order dated 11.02.2022 in W.P.No.21784 of 2021.

Remedy Sought

Petitioner sought to punish the respondents for disobeying the order passed by the court on 11.02.2022 in W.P.No.21784 of 2021.

Filing Reason

Alleged non-compliance with the order dated 11.02.2022 in W.P.No.21784 of 2021.

Previous Decisions

Order dated 11.02.2022 in W.P.No.21784 of 2021.

Issues

Whether the respondents had willfully disobeyed the order dated 11.02.2022 in W.P.No.21784 of 2021.

Submissions/Arguments

Written instructions submitted by the Block Development Officer showed that encroachments had been removed and a small bridge constructed.

Ratio Decidendi

Once the court is satisfied that the order has been complied with, contempt proceedings may be closed. The petitioner retains the right to approach the court if any grievance persists.

Judgment Excerpts

Written instructions submitted by the Block Development Officer, Alathur Village, would show that the encroachments have been removed and a small bridge has been constructed. If any grievance exists to the petitioner, he is at liberty to file a fresh complaint. Accordingly, the Contempt Petition stands closed.

Procedural History

The petitioner filed W.P.No.21784 of 2021, which was disposed of on 11.02.2022. Subsequently, the petitioner filed CONT P No. 1811 of 2022 alleging disobedience of that order. On 18.02.2026, the court heard the contempt petition and closed it after noting compliance.

Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Appeal for Specific Performance of Share Sale Agreement — Plaintiff Failed to Prove Readiness and Willingness to Perform Contract. MOU for Sale of Shares Held Not Enforceable as Plaintiff Did Not Show Financial Capacity ...
Related Judgement
Supreme Court Supreme Court Upholds Dismissal of Retired Junior Commissioned Officer Under Army Act, 1950. Dismissal After Superannuation Is Valid Under Section 123 as Offence Was Committed While in Service, and Dismissed Officer Is Ineligible for Pension Under Re...