Case Note & Summary
The State of Tamil Nadu and the Tamil Nadu Slum Clearance Board filed an intra-court appeal under Clause 15 of the Letters Patent against a single judge's order dated 04.04.2022 in W.P.No.34682 of 2019. The respondent, M/s P.S.T. Engineering Construction, had filed the writ petition seeking a direction not to apply G.O.Ms.296 Finance (Salaries) Department dated 09.10.2017 to the work agreement dated 06.12.2017 entered into with the Tamil Nadu Slum Clearance Board. The respondent also sought to quash resolutions dated 10.08.2018, 07.06.2019, and 19.11.2019. The State argued that the dispute was purely contractual and that the writ court under Article 226 could not resolve disputed facts involving contractual obligations. The contract contained Clause 6.6 stating that all duties, taxes, cess, and levies payable by the contractor as per State/Central Government rules shall be included in the contract value. Special conditions annexed to the contract specifically mentioned the applicability of G.O.Ms.264 Finance (Salaries) Department dated 15.09.2017 and subsequent amendments. The court noted that the respondent had agreed to these terms and could not later challenge the applicability of G.O.Ms.296. The court held that the writ petition was not maintainable as the dispute involved contractual obligations and factual disputes that could only be resolved through arbitration or civil suit. The appeal was allowed, the impugned order was set aside, and the writ petition was dismissed. The court clarified that the respondent was at liberty to pursue other remedies available under law.
Headnote
A) Constitutional Law - Writ Jurisdiction - Contractual Disputes - Article 226 of the Constitution of India - The High Court held that disputed questions of fact arising from contractual obligations cannot be resolved in writ proceedings under Article 226. The remedy lies in invoking arbitration clauses or approaching civil courts. The writ petition seeking to prevent application of G.O.Ms.296 was not maintainable. (Paras 4, 8) B) Contract Law - Interpretation of Contract - Binding Effect of Agreed Terms - Articles of Agreement dated 06.12.2017 - The respondent contractor had agreed to Clause 6.6 and special conditions incorporating G.O.Ms.264 Finance (Salaries) Department dated 15.09.2017. Having accepted the terms, the contractor could not later challenge the applicability of subsequent government orders. (Paras 5-7)
Issue of Consideration
Whether a writ petition under Article 226 is maintainable to challenge the application of a government order in a contractual dispute
Final Decision
The appeal is allowed. The order dated 04.04.2022 passed in W.P.No.34682 of 2019 is set aside. The writ petition is dismissed. No costs. Consequently, connected miscellaneous petitions are closed. The respondent is at liberty to pursue other remedies available under law.
Law Points
- Writ jurisdiction under Article 226 not available for contractual disputes
- Contractual obligations must be resolved through arbitration or civil suit
- Parties bound by agreed terms including applicability of government orders



