Case Note & Summary
The litigation arose from the acquisition of 20 guntas of land in Sy. No. 146 of Agara Village for the formation of HSR Layout by the Bengaluru Development Authority (BDA) under the Bangalore Development Authority Act, 1976. The appellant claimed ownership and sought de-notification of the land, alleging that the acquisition had lapsed and that he remained in possession. The BDA issued a preliminary notification on 15.12.1984 under Section 17(1) of the BDA Act, followed by a final notification on 28.12.1986 under Section 19(1). The award was passed on 07.07.1987, and possession was taken on 15.07.1987. Subsequently, the land was included in the fully developed HSR Layout scheme and allotted to third parties. The appellant had filed multiple proceedings over the years all of which were unsuccessful: W.P. No. 18044/2000 was dismissed by a Division Bench of the High Court on 18.08.2000 on the ground that Section 38C(2) of the BDA Act, upon which he relied, had been repealed; Original Suit No. 8279/2000 for declaration of title by adverse possession was dismissed on 15.11.2010; R.F.A. No. 306/2011 arising from the suit was dismissed on 04.10.2012; and S.L.P. No. 8132/2013 before the Supreme Court was dismissed on 10.01.2014, though with liberty to make a representation for de-notification. The appellant made a representation on 29.01.2014, which was rejected by the BDA on 01.06.2015. In the meantime, he filed W.P. No. 17432/2014 seeking a declaration that the acquisition proceedings had lapsed under Section 27 read with Section 36 of the BDA Act and under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, and for quashing the mahazar recording possession. The learned Single Judge dismissed the writ petition on 16.04.2018, leading to the present intra-Court appeal. The core legal issues were whether the acquisition had lapsed under Section 27 of the BDA Act because the scheme was not enforced, and whether the appellant could claim benefit under Section 24(2) of the 2013 Act. The appellant argued that the land was not utilized and remained in his possession, relying on the Supreme Court's decision in Offshore Holdings. The respondents contended that the acquisition was complete, the scheme had been fully implemented as HSR Layout, possession was taken and third-party rights had been created, rendering de-notification impossible. The Court examined the facts and found that the HSR Layout scheme was indeed implemented and a full-fledged layout existed. It held that even if the scheme had lapsed, the acquisition would not lapse as per the law laid down in Offshore Holdings. Regarding the claim under the 2013 Act, the Court noted that the acquisition under the BDA Act was completed with possession taken, and thus Section 24(2) could not be invoked. It also observed that the appellant had repeatedly litigated and failed, and that de-notification could not be granted after third-party rights had been created. The Court concluded there was no merit in the appeal and dismissed it, upholding the decision of the learned Single Judge.
Headnote
A) Land Acquisition - Lapse of Scheme under BDA Act - Section 27 of Bangalore Development Authority Act, 1976 - The appellant contended that the scheme had lapsed as the land was not utilized, but the Court found that the HSR Layout scheme was fully implemented, award was passed, possession taken, and third-party rights created - Held that the scheme did not lapse and even if the scheme had lapsed, the acquisition would not lapse as per Offshore Holdings Private Limited v. Bengaluru Development Authority (Paras 14-16) B) Land Acquisition - Applicability of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - The appellant argued that acquisition under BDA Act is akin to acquisition under Land Acquisition Act, 1894, thus entitling him to lapse under the 2013 Act - The Court reasoned that irrespective of the analogy, the acquisition was complete, possession was taken, and the scheme was implemented, so no benefit under Section 24(2) could be claimed - Held that the appellant could not invoke Section 24(2) to challenge a completed acquisition (Paras 16-17) C) De-notification after Completion of Acquisition - Bangalore Development Authority Act, 1976 - Once possession is taken and third-party rights are created, de-notification becomes impermissible; repeated unsuccessful litigation does not revive the claim - Held that the prayer for de-notification was rightly rejected by the Single Judge (Paras 14-16)
Issue of Consideration
Whether the acquisition of the subject land had lapsed under Section 27 read with Section 36 of the Bangalore Development Authority Act, 1976 and under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.
Final Decision
The appeal was dismissed. The Court held that the acquisition proceedings were complete, the HSR Layout scheme had been fully implemented, possession was taken on 15.07.1987, and third-party rights had been created. There was no merit in the appellant's contentions regarding lapsing of acquisition under Section 27 of the BDA Act or Section 24(2) of the 2013 Act. The order of the learned Single Judge dismissing the writ petition was upheld.
Law Points
- If the scheme under the BDA Act is implemented and possession taken
- the acquisition does not lapse even under Section 27
- Section 24(2) of the 2013 Act cannot be invoked for a completed acquisition under BDA Act where possession taken
- de-notification is impermissible after third-party rights are created




