Case Note & Summary
The applicant, Santsaran Gursaran Advani Alias Papan Advani, filed a suit seeking declaration of ownership and permanent injunction against the respondents, including Nina H. Bhalla and others, concerning a flat in Mumbai. The applicant claimed that he was the owner of the flat by virtue of a registered deed and that the respondents had forged a power of attorney to create third-party rights. The applicant filed an interim application under Order 39 Rules 1 and 2 of the Code of Civil Procedure, 1908 (CPC) seeking to restrain the respondents from alienating or creating any encumbrance over the flat pending disposal of the suit. The court considered the three-fold test for grant of interim injunction: prima facie case, balance of convenience, and irreparable loss. The court found that the applicant had made out a prima facie case based on the registered deed and the alleged forgery. The balance of convenience was in favor of the applicant as the flat was his only residence and any alienation would cause irreparable hardship. The court also rejected the argument under Section 41(h) of the Specific Relief Act, 1963, holding that damages were not an adequate remedy. The court allowed the interim application and restrained Respondent No.1 from creating any third-party rights over the suit flat until the disposal of the suit.
Headnote
A) Civil Procedure - Interim Injunction - Prima Facie Case - The court considered whether the applicant had made out a prima facie case for grant of interim injunction - Held that the applicant's claim of ownership based on a registered deed and the alleged forgery of a power of attorney raised serious triable issues, establishing a prima facie case (Paras 5-10). B) Civil Procedure - Interim Injunction - Balance of Convenience - The court weighed the balance of convenience between the parties - Held that the balance of convenience was in favor of the applicant as the suit flat was his only residence and any alienation would cause irreparable hardship (Paras 11-15). C) Civil Procedure - Interim Injunction - Irreparable Loss - The court assessed whether the applicant would suffer irreparable loss if injunction was not granted - Held that the applicant, being in possession and having a strong claim, would suffer irreparable loss if third-party rights were created (Paras 16-20). D) Specific Relief Act, 1963 - Section 41(h) - Bar to Injunction - The court examined whether the applicant had an alternative efficacious remedy - Held that the remedy of damages was not adequate given the nature of the property dispute, and Section 41(h) did not bar the injunction (Paras 21-25).
Issue of Consideration
Whether the applicant is entitled to an interim injunction restraining the respondents from creating third-party rights over the suit flat pending disposal of the suit.
Final Decision
The court allowed the interim application and restrained Respondent No.1 from creating any third-party rights over the suit flat until the disposal of the suit.
Law Points
- Prima facie case
- balance of convenience
- irreparable loss
- interim injunction
- power of attorney
- forgery
- ownership dispute
- Section 41(h) Specific Relief Act
- 1963
- Order 39 Rules 1 and 2 CPC





