Bombay High Court Adjudicates Challenge to MMRDA's Additional Premium Demand — Interpretation of Articles 2(c), 2(d), 2(e) of Lease Deed and Impact of Supplementary Lease Deed. The Court Examines Whether Delay in Construction Attributable to MMRDA's Approvals and Absence of Time Limit for Additional Built-Up Area Renders Demand Arbitrary.

High Court: Bombay High Court Bench: BOMBAY
  • 3
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose from a demand notice issued by the Mumbai Metropolitan Region Development Authority (MMRDA) to the Indian Newspaper Society (the petitioner) for additional premium/penalty due to alleged late completion of construction on a leased plot at Bandra-Kurla Complex, Mumbai. The petitioner, a non-profit company registered under Section 25 of the Companies Act, 1956, was allotted Plot No. C-63 in 'G' Block, BKC, on 17 November 2005, on an 80-year lease for constructing an office complex, with a lease premium of Rs. 88,52,75,000. A Lease Deed was executed on 9 April 2008, stipulating under Article 2(d) that construction must be completed within four years. Article 2(e) allowed extension of time on payment of additional premium at progressive rates. Possession was handed over on 10 April 2008. The original permissible built-up area (BUA) was 20,830 sq. mtrs. at 2.00 FSI. The petitioner submitted construction plans and obtained excavation permission on 30 May 2008. However, plan approval was delayed, partly due to requirements for environmental NOC, which was submitted on 8 October 2009. Meanwhile, MMRDA enhanced FSI to 4.00 and offered additional BUA. On 22 September 2009, the petitioner applied for additional BUA of 20,830 sq. mtrs., which was allotted on 10 September 2009 against additional premium of Rs. 204,02,98,500, payable in instalments. A Supplementary Lease Deed was executed on 22 April 2013, which stated that there would be no time limit for completing construction using the additional BUA, and the incremental premises would be integral to the original demised premises. The total BUA thus increased to 41,660 sq. mtrs. The petitioner submitted a revised plan for G+14 floors in both wings, which was approved on 26 August 2011. Commencement Certificates (CC) were issued piecemeal, with the final CC for the entire building granted only on 14 November 2013. In the meantime, the four-year period under the original Lease Deed had expired. The petitioner, anticipating the need for extension, wrote on 6 June 2012 and 10 December 2012 seeking two years' extension, citing delays including height clearance from aviation authorities, which was eventually obtained on 2 August 2012. By a letter dated 10 January 2013, the petitioner estimated completion would take six years and requested payment of additional premium in instalments under protest. MMRDA proposed to levy penalty. Despite disagreement, the petitioner, to avoid project delay, offered to pay the additional premium in quarterly instalments under protest. On 30 September 2013, MMRDA granted extension for one year from 9 April 2012 to 8 April 2013, charging additional premium at 10% of lease premium (Rs. 8,85,27,500) plus 14% interest for delayed payment, and agreed to instalment payment. Subsequently, the petitioner challenged a demand notice dated 12 September 2017, contending that the demand was contrary to lease terms, especially since delay was partly due to MMRDA's own delays in approvals and the Supplementary Lease Deed had removed time limits for additional BUA. The writ petition was filed in 2018. The Bombay High Court issued Rule and by consent heard the matter finally, reserving judgment on 22 January 2026 and pronouncing it on 8 April 2026. The available judgment text contains only the factual background up to paragraph 22; the court's analysis, reasoning, and final decision are not included in the provided excerpt.

Issue of Consideration

Whether the demand notice dated 12th September 2017 for penalty/additional premium on account of late completion of construction is contrary to the terms and conditions of the Lease Agreement and therefore arbitrary and illegal.

Subscribe to unlock Issue of Consideration Subscribe Now

Case Details

2026 LawText (BOM) (04) 43

Writ Petition No. 864 of 2018

2026-04-08

Shree Chandrashekhar, CJ, Suman Shyam, J.

Mr. Ankit Lohia, Mr. Firoz Patel, Mr. Prashant Ghelani, Ms. Namrata Vashist, Mr. Darshil Desai, Dr. Birendra Saraf, Senior Advocate, Mr. Nishant Chotani, Mr. Nivit Srivastava, Ms. Sneha Patil, Ms. Aditi Sinha, Mr. Hrishikesh Joshi, Ms. Isha Vyas

Indian Newspaper Society

Mumbai Metropolitan Region Development Authority (MMRDA) & Anr.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition under Article 226 of the Constitution of India challenging MMRDA's demand notice for additional premium/penalty for late completion of construction.

Remedy Sought

Quashing of demand notice dated 12th September 2017 and declaration that the demand is contrary to lease terms and arbitrary.

Filing Reason

MMRDA issued demand notice levying additional premium/penalty for failure to complete construction within four years as per Article 2(d) of Lease Deed dated 9 April 2008, which petitioner contends is illegal due to delays attributable to MMRDA and terms of Supplementary Lease Deed.

Issues

Whether the demand for additional premium/penalty is consistent with the terms of the Lease Deed dated 9 April 2008 and the Supplementary Lease Deed dated 22 April 2013, especially in light of the removal of time limits for additional built-up area and delays caused by MMRDA's own approval processes.

Submissions/Arguments

Petitioner contended that Article 2(c) of the Supplementary Lease Deed eliminated any time limit for completing construction with the additional built-up area, thereby overriding Article 2(d) of the original Lease Deed. Delay in completing the entire project was not attributable to the petitioner alone but was substantially caused by MMRDA's tardy issuance of plan approvals, no-objection certificates, and commencement certificates. Despite the absence of any written demand, the petitioner proactively sought extension of time and offered to pay additional premium under protest to avoid project disruption. The demand notice dated 12 September 2017 was arbitrary, contrary to the lease covenants, and issued without proper consideration of the factual and contractual context.

Judgment Excerpts

Article 2(d) lays down that the construction will be completed within a period of four years from the date of execution of the Lease Deed; Article 2(e) stipulates that failure to comply with Article 2(d) would require extension of time that may be permitted by the Metropolitan Commissioner on payment of additional premium... Article 2(c) of the Supplementary Lease Deed clearly stipulated that there shall be no time-limit, as stipulated in Article 2(d) of the Lease Deed dated 9th April 2008, for completion of the construction of the building by using the additional built-up area. It was also conveyed that as requested by the Petitioner, the Respondent No. 1 was agreeable to the proposal for payment of the additional pre...

Procedural History

Writ Petition No. 864 of 2018 was filed before the Bombay High Court. Rule was issued and by consent of parties, the matter was taken up for final hearing. Judgment was reserved on 22 January 2026 and pronounced on 8 April 2026.

Acts & Sections

  • Companies Act, 1956: Section 25
  • Mumbai Metropolitan Regional Development Authority Act, 1974:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Adjudicates Challenge to MMRDA's Additional Premium Demand — Interpretation of Articles 2(c), 2(d), 2(e) of Lease Deed and Impact of Supplementary Lease Deed. The Court Examines Whether Delay in Construction Attributable to MMRDA'...
Related Judgement
High Court High Court of Bombay at Aurangabad Hears Writ Petitions Against School Tribunal’s Order in Headmaster Promotion Dispute. Challenge to Promotion on Grounds of Jurisdiction, Delay, and Minority School Status.