Supreme Court Upholds Termination but Sets Aside Blacklisting in Contract Dispute Due to Violation of Natural Justice. The termination was justified based on negligence and non-compliance with design, but blacklisting was invalidated for lack of specific show-cause notice and failure to adhere to audi alteram partem under Rule 10 of Contractor Registration Rules, 2012.

  • 7
Judgement Image
Font size:
Print

Case Note & Summary

The dispute involved a contractor engaged by the Water and Sanitation Department of Jharkhand for constructing an Elevated Service Reservoir. The contract was governed by a Letter of Acceptance issued on 06.03.2023. During the contract, on 01.06.2024, the top dome of the reservoir collapsed, which the contractor attributed to an unexpected cyclone but offered to reconstruct at its own expense. The Department issued a show-cause notice on 04.06.2024, alleging negligence and poor quality work. Following multi-level enquiries, including reports from technical institutes, the Chief Engineer passed a termination cum blacklisting order on 23.08.2024, citing violations of Contractor Registration Rules, 2012. The contractor's appeal and subsequent writ petition were dismissed by the Appellate Authority and High Court, respectively, with the High Court imposing costs. A review petition was also dismissed, leading to appeals before the Supreme Court. The core legal issues revolved around the legality of the termination under Clause 59 of the General Conditions of Contract and the blacklisting under Rule 10 of the Contractor Registration Rules, 2012, particularly regarding compliance with natural justice. The appellant argued that both actions were illegal and arbitrary, emphasizing lack of opportunity in enquiries and the severe impact of blacklisting. The respondent contended that the termination did not require prior notice under Clause 59 and that the show-cause notice sufficed for blacklisting under Rule 10. The court analyzed the contractual and regulatory provisions, applying standards of legality, rationality, and proportionality. It upheld the termination as substantiated by evidence of negligence and non-compliance with design, but set aside the blacklisting due to failures in application of mind and absence of a specific show-cause notice proposing blacklisting, violating natural justice principles. Considering the passage of time, the court moulded the relief by directing that the blacklisting order cease from the judgment date. The decision affirmed the termination while quashing the blacklisting, with no costs imposed.

Headnote

A) Administrative Law - Judicial Review of Administrative Actions - Standards of Legality, Rationality, and Proportionality - Not mentioned - Courts must apply distinct standards of legality, rationality, and proportionality when reviewing administrative actions related to contract termination and blacklisting, as these measures have differing gravity and consequences. This approach ensures proper scrutiny of state actions in contractual matters. (Paras 2-3)

B) Contract Law - Termination of Contract - Substantiation and Justification - General Conditions of Contract, Clause 59 - The termination order was upheld as substantiated and justified based on concurrent reports indicating negligence and failure to adhere to approved design and drawings, despite the contractor's offer to reconstruct at own expense. The court found the termination compliant with contractual provisions. (Paras 3-4, 12-13)

C) Administrative Law - Blacklisting of Contractors - Natural Justice and Show-Cause Notice - Contractor Registration Rules, 2012, Rule 10 - The blacklisting order was set aside due to patent infirmities, including lack of application of mind, disregard for audi alteram partem, and failure to issue a specific show-cause notice proposing blacklisting. Blacklisting, being stigmatic and exclusionary, cannot be imposed mechanistically and must comport with principles of natural justice and reasonableness. (Paras 3-5, 12)

D) Remedies - Moulding of Relief - Cessation of Blacklisting Order - Not mentioned - Due to the passage of time, the court moulded the relief by directing that the blacklisting order, originally for five years, shall cease to operate from the date of the judgment, rather than allowing it to continue for the full term. This adjustment balanced the need for justice with practical considerations. (Para 5)

Issue of Consideration: Whether the termination and blacklisting of the contractor by the State Department were legal and compliant with contractual clauses and rules, particularly regarding natural justice in blacklisting

Final Decision

Uphold termination order, set aside blacklisting order, direct blacklisting to cease from judgment date

2026 LawText (SC) (04) 15

Civil Appeal No(s). of 2026 arising out of SLP (C) No. 23858 of 2025, with Civil Appeal No(s). of 2026 arising out of SLP (C) No. 22669 of 2025

2026-04-02

PAMIDIGHANTAM SRI NARASIMHA J. , ALOK ARADHE J.

2026 INSC 312

Mr. M.S. Ganesh, Mr. Kumar Anurag Singh

M/S A.K.G. Construction and Developers Pvt. Ltd

State of Jharkhand & Ors.

Nature of Litigation: Civil appeal challenging termination and blacklisting of a contractor by the State Department

Remedy Sought

Appellant sought quashing of termination and blacklisting orders

Filing Reason

Appellant aggrieved by termination cum blacklisting order dated 23.08.2024 and subsequent dismissals by Appellate Authority and High Court

Previous Decisions

Appellate Authority dismissed appeal on 05.12.2024, High Court dismissed writ petition on 07.02.2025 and review petition on 04.08.2025

Issues

Legality of termination under Clause 59 of General Conditions of Contract Legality of blacklisting under Rule 10 of Contractor Registration Rules, 2012 regarding natural justice

Submissions/Arguments

Appellant argued termination and blacklisting were illegal and arbitrary, with lack of opportunity in enquiries Respondent argued termination did not require prior notice under Clause 59 and show-cause notice sufficed for blacklisting under Rule 10

Ratio Decidendi

Termination can be upheld if substantiated, but blacklisting must comply with natural justice including a specific show-cause notice; courts apply standards of legality, rationality, and proportionality in judicial review of such administrative actions

Judgment Excerpts

Courts must apply distinct standards of legality, rationality and proportionality Blacklisting, being stigmatic and exclusionary in nature, cannot be imposed mechanistically but must comport with principles of natural justice and reasonableness The assumed logical consequence of blacklisting is neither supported by application of mind nor followed by a clear notice proposing blacklisting

Procedural History

Contract issued on 06.03.2023, dome collapsed on 01.06.2024, show-cause notice on 04.06.2024, termination cum blacklisting order on 23.08.2024, appeal dismissed on 05.12.2024, writ petition dismissed on 07.02.2025, review dismissed on 04.08.2025, appeals filed in Supreme Court

Related Judgement
Supreme Court Supreme Court Upholds Termination but Sets Aside Blacklisting in Contract Dispute Due to Violation of Natural Justice. The termination was justified based on negligence and non-compliance with design, but blacklisting was invalidated for lack of spec...
Related Judgement
High Court Notice of Motion to Quash Undefended Suit Order and Condonation of Delay. A Legal Challenge to Balance Procedural Flexibility and Strict Timelines Under the Commercial Courts Act