Case Note & Summary
The appellant, Karabhai Hardasbhai, was the original claimant in a land acquisition matter. The State of Gujarat acquired his land bearing survey no.237/1 and 418/2 situated at Mouje: Karshanpur, Taluka: Jamjodhpur, District Jamnagar for the Kabarka Irrigation Project. A notification under Section 4 of the Land Acquisition Act, 1894 was published on 09.04.2005, followed by a Section 6 notification on 24.09.2005. The Land Acquisition Officer passed an award under Section 11 on 17.11.2005, granting compensation at Rs.4.50 per sq.mtr. Dissatisfied, the claimant sought a reference under Section 18, which was decided by the learned Principal Senior Civil Judge, Lalpur at Jamnagar in Land Reference Case No.161 of 2006 vide judgment and award dated 10.05.2018. The Reference Court enhanced the compensation to Rs.7 per sq.mtr. but did not award the statutory benefits under Section 23(1A) (12% additional amount) and Section 23(2) (30% solatium). The claimant filed the present first appeal under Section 54 of the Land Acquisition Act read with Section 96 of the CPC, challenging the Reference Court's award to the extent it denied these benefits. The High Court allowed the appeal, holding that the claimant is entitled to the additional amount under Section 23(1A) from the date of Section 4 notification to the date of award or possession, and solatium under Section 23(2) at 30% on the enhanced market value. The Court directed the respondent to pay these amounts with interest under Section 28 of the Act. The judgment was delivered by Honourable Mrs. Justice M. K. Thakker on 15/01/2026.
Headnote
A) Land Acquisition - Compensation Enhancement - Additional Amount under Section 23(1A) - The appellant-claimant sought enhancement of compensation for acquired land, contending that the Reference Court failed to award 12% additional amount under Section 23(1A) of the Land Acquisition Act, 1894, from the date of notification under Section 4(1) to the date of award or possession. The Court held that the claimant is entitled to such additional amount as per law, and directed the respondent to pay the same. (Paras 1-8) B) Land Acquisition - Compensation Enhancement - Solatium under Section 23(2) - The appellant-claimant argued that the Reference Court did not grant solatium at 30% on the enhanced market value under Section 23(2) of the Land Acquisition Act, 1894. The Court held that solatium is a statutory right and must be awarded, and accordingly directed the respondent to pay solatium on the enhanced compensation. (Paras 1-8) C) Land Acquisition - Compensation Enhancement - Market Value Determination - The appellant-claimant challenged the market value fixed by the Reference Court at Rs.4.50 per sq.mtr., seeking enhancement. The Court, after considering the evidence and previous awards for similar lands, enhanced the market value to Rs.7 per sq.mtr., noting that the acquired land was irrigated and had potential for development. (Paras 1-8)
Issue of Consideration
Whether the Reference Court erred in not granting the statutory benefits under Section 23(1A) and Section 23(2) of the Land Acquisition Act, 1894, and whether the compensation awarded was just and proper.
Final Decision
The High Court allowed the appeals, set aside the impugned judgment and award to the extent it denied the statutory benefits, and directed the respondent to pay the appellant-claimant the additional amount under Section 23(1A) at 12% per annum from the date of Section 4 notification (09.04.2005) to the date of award or possession, and solatium under Section 23(2) at 30% on the enhanced market value, with interest under Section 28 of the Act.
Law Points
- Land Acquisition Act
- 1894
- Section 23(1A)
- Section 23(2)
- Section 4
- Section 6
- Section 11
- Section 54
- Civil Procedure Code
- 1908
- Section 96
- Compensation Enhancement
- Additional Amount
- Solatium
- Market Value




