Bombay High Court Hears Appeals Against Orders in Section 9 Applications for Injunction in Water Supply Project Dispute. Court Examines Whether Injunction Preventing Contract Termination Amounts to Impermissible Specific Performance Under Specific Relief Act, 1963.

High Court: Bombay High Court Bench: AURANGABAD
  • 7
Judgement Image
Font size:
Print

Case Note & Summary

The matter involved two arbitration appeals arising from interim applications under Section 9 of the Arbitration and Conciliation Act, 1996. The dispute pertained to a water supply concession agreement between Aurangabad City Water Utility Company Ltd. (the contractor) and Aurangabad Municipal Corporation (the employer). After the employer issued a termination notice, the contractor filed MARJI No. 214/2016 before the District Court seeking injunctions to restrain the employer from taking coercive steps, taking over the project, and encashing a bank guarantee. The District Court only partly allowed the application, restraining the employer from acting without following the contractual due process, but refused the other substantial reliefs. Aggrieved, the contractor filed Arbitration Appeal No. 12 of 2016 before the High Court. While this appeal was pending, the contractor filed a fresh application, MARJI No. 326/2016, ostensibly based on the subsequent termination of the contract, and obtained an injunction restraining the employer from acting on the termination notice. The employer then challenged that order in Arbitration Appeal No. 13 of 2016. The High Court admitted both appeals and heard them together. The court examined whether the second application was maintainable and whether an injunction restraining termination could be granted. It observed that the reliefs sought by the contractor would effectively amount to specific performance of the contract, which is barred under Section 14 of the Specific Relief Act, 1963, as compensation would be an adequate remedy. The court further noted that under Section 41(h) of the Act, an injunction cannot be granted when an equally efficacious remedy is available. The court also held that the principles of Order 39 Rule 1 CPC and the limitations of the Specific Relief Act apply to Section 9 applications. The employer argued that the second application was an abuse of process and forum shopping. The court found force in this argument, stating that the termination did not create a fresh cause of action for a new Section 9 application. However, as the provided judgment text is incomplete, the final operative order of the High Court is not recorded in the excerpt. The judgment discussed the legal principles governing the discretionary power under Section 9 and indicated that the contractor's application was not tenable. The decision in the matter would have turned on these principles, but the exact reasoning and final outcome remain unknown from the available text.

Headnote

A) Arbitration - Interim Measures - Section 9, Arbitration and Conciliation Act, 1996 - When considering an application for injunction under Section 9, courts must apply the principles governing temporary injunctions under Order 39 Rule 1 CPC and the limitations under Sections 14 and 41 of the Specific Relief Act, 1963. The relief sought must not amount to specific performance of a contract which is not specifically enforceable. Held that granting an injunction preventing the employer from terminating the contract would be impermissible as it would imply specific performance of a determinable contract (Paras 7-10).

B) Contract Law - Specific Performance - Contracts not specifically enforceable - Specific Relief Act, 1963, Section 14 - A contract for which compensation in money is an adequate remedy cannot be specifically enforced. In the context of a water supply concession agreement, the contractor's claim to continue operating the project and collecting user charges could be compensated monetarily. Held that an injunction under Section 9 amounting to specific performance was barred under Section 14(1)(a) of the Specific Relief Act, 1963 (Paras 8-10).

C) Civil Procedure - Forum Shopping - Multiple Section 9 Applications - Arbitration and Conciliation Act, 1996, Section 9 - Filing a second application under Section 9 after the first was rejected, while an appeal was pending, and obtaining relief from a different judge, amounts to forum shopping. The termination of the contract did not give rise to a fresh cause of action for a new Section 9 application. Held that the contractor's conduct in filing MARJI No. 326/2016 was improper and an abuse of process (Paras 5-6).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the contractor is entitled to interim injunction under Section 9 of the Arbitration and Conciliation Act, 1996 to restrain the employer from terminating the concession agreement and taking over the water supply project, particularly in light of the bar on specific performance of contracts under Sections 14 and 41 of the Specific Relief Act, 1963.

Subscribe to unlock Issue of Consideration Subscribe Now

Law Points

  • principles under section 38 of Specific Relief Act
  • limitations under sections 14 and 41 of Specific Relief Act
  • procedure under Order 39 CPC
  • contract not specifically enforceable if compensation is an adequate relief
  • injunction cannot be granted if equally efficacious relief is available
Subscribe to unlock Law Points Subscribe Now

Case Details

2016 LawText (BOM) (10) 23

Arbitration Appeal No. 12 of 2016 with Civil Application No. 14220 of 2016 with Civil Application No. 12942 of 2016 & Arbitration Appeal No. 13 of 2016 with Civil Application No. 14221 of 2016 with Civil Application No. 14156 of 2016 with Civil Application No. 14155 of 2016

2016-10-24

T.V. Nalawade, J.

Mr. R.F. Totala, Mr. A.S. Bajaj

Aurangabad City Water Utility Co. Ltd. (Appellant in Arb. Appeal No. 12/2016) and Aurangabad Municipal Corporation (Appellant in Arb. Appeal No. 13/2016)

Aurangabad Municipal Corporation (Respondent in Arb. Appeal No. 12/2016) and Aurangabad City Water Utility Co. Ltd. (Respondent in Arb. Appeal No. 13/2016)

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Arbitration appeals challenging orders under Section 9 of the Arbitration and Conciliation Act, 1996 regarding interim injunctions in a water supply project dispute.

Remedy Sought

The contractor sought injunction to restrain the employer from terminating the concession agreement and taking over the project without due process, and from encashing bank guarantee.

Filing Reason

The employer had issued a termination notice; the contractor filed Section 9 applications to prevent termination and takeover.

Previous Decisions

In MARJI No. 214/2016, the District Court partly allowed the application, restraining the employer from taking coercive action without following the agreement but refused the main injunction preventing takeover and encashment of bank guarantee. The contractor appealed (Arb. Appeal No. 12/2016). While appeal pending, the contractor filed a second application MARJI No. 326/2016 and obtained an injunction restraining the employer from acting on the termination notice, which the employer challenged in Arb. Appeal No. 13/2016.

Issues

Whether the second Section 9 application was maintainable after rejection of the first and during pendency of appeal Whether the termination of contract after the first application gave a fresh cause of action Whether granting injunction to restrain termination of the contract would amount to specific performance of a contract not specifically enforceable under Sections 14 and 41 of the Specific Relief Act, 1963 Whether the contractor was entitled to an order preventing the employer from taking over the project

Submissions/Arguments

Contractor argued that the termination of the contract gave a new cause of action, making the second Section 9 application tenable. Employer contended that filing the second application was forum shopping because the judge who decided the first application was not available, and the contractor obtained an order from another judge. The court observed that the reliefs sought would amount to specific performance of a contract, which is barred under Sections 14 and 41 of the Specific Relief Act, 1963.

Judgment Excerpts

For such relief, the principles which are applicable under the provision of section 38 of the Specific Relief Act, 1963 are applicable. In the present matters, granting of relief of injunction would amount to enable the contractor to see that only the contractor is allowed to execute the work of the project and this work is not withdrawn from the contractor. A contract for the non-performance of which compensation in money is an adequate relief cannot be specifically enforced.

Procedural History

Contractor filed MARJI No. 214/2016 under Section 9 seeking various injunctions; District Court on 08/09/2016 partly allowed, refusing main reliefs; Contractor appealed in Arb. Appeal No. 12/2016; During pendency, employer terminated contract; Contractor filed MARJI No. 326/2016 and obtained injunction; Employer appealed in Arb. Appeal No. 13/2016; High Court admitted both appeals and heard together on 24/10/2016; Judgment discussing principles but final order missing from provided text.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: 9
  • Specific Relief Act, 1963: 14, 41, 38
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Judicature at Bombay Hears Customs Appeals on Domestic Clearance of Duty-Free Input Products Under Advance Authorizations. Core Issue Whether Tribunal Correctly Interpreted Foreign Trade Policy 2004-2009 Paras 4.1.3 and 4.1.5 to Permit ...
Related Judgement
High Court Bombay High Court Hears Appeals Against Orders in Section 9 Applications for Injunction in Water Supply Project Dispute. Court Examines Whether Injunction Preventing Contract Termination Amounts to Impermissible Specific Performance Under Specific Re...